| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2024 | Signed-off | RRP PLUMBING CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2024 | Signed-off | WATSON'S PLBG, HTG, & BDG | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/19/2024 | Complete | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| MATHEW LAMPSHADE CORP. | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ARC CONSULTING ENGINEERS | 8 | 07/27/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| AMERILAND BROOK LLC | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| THC CONSTRUCTION INC | General Contractor | 5 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 3 | 07/08/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ARC CONSULTING ENGINEERS, | 4083 | 8 | 07/27/2024 |
| AMERILAND BROOK LLC | 1506 | 2 | 11/04/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | THC CONSTRUCTION INC | 06/18/2024 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 06/12/2024 |
| DOB NOW | Plumbing | Signed-off | RALPH W. LANDOLFI JR. | 11/09/2023 |
| DOB NOW | Boiler Equipment | Signed-off | WATSON'S PLBG, HTG, & BDG | 10/30/2023 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 02/28/2023 |
| DOB NOW | General Construction | Permit Issued | THC CONSTRUCTION INC | 02/06/2023 |
| DOB NOW | General Construction | Permit Issued | THC CONSTRUCTION INC | 01/27/2023 |
| BIS | — | ISSUED | TBC CONSTRUCTION INC | 03/12/2013 |
| BIS | PL | ISSUED | BARMOR REHAB INC | 01/16/2013 |
| BIS | — | ISSUED | TBC CONSTRUCTION INC | 12/03/2012 |
| BIS | BL | ISSUED | NEAL M. RUDIKOFF | 03/10/1999 |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/02/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/31/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/18/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/16/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/14/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/06/2023 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 10/27/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/24/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/19/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/14/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/14/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/02/2024 | Lighting in dwelling units | JAN PEREZ | energy_progress |
| 08/02/2024 | Sprayed fire-resistant materials | JAN PEREZ | special |
| 08/02/2024 | Tenant Protection Plan Compliance | JAN PEREZ | special |
| 08/02/2024 | Fire-Resistant Penetrations and Joints | JAN PEREZ | special |
| 08/02/2024 | Chimneys and vents | JAN PEREZ | special |
| 08/02/2024 | Construction Operations Influencing Adjacent Structures | JAN PEREZ | special |
| 08/02/2024 | Structural Stability – Alterations of existing buildings | JAN PEREZ | special |
| 08/02/2024 | Fire-Resistance Rated Construction | JAN PEREZ | progress |
| 08/02/2024 | Energy Code Compliance Inspections | JAN PEREZ | progress |
| 08/02/2024 | HVAC-R and service water heating system controls | JAN PEREZ | energy_progress |
| 08/02/2024 | HVAC-R and service water piping design and insulation | JAN PEREZ | energy_progress |
| 08/02/2024 | HVAC-R and service water heating equipment | JAN PEREZ | energy_progress |
| 08/02/2024 | Insulation placement and R values | JAN PEREZ | energy_progress |
| 08/02/2024 | Maintenance information | JAN PEREZ | energy_progress |
| 08/02/2024 | Permanent certificate | JAN PEREZ | energy_progress |
| 08/02/2024 | Lighting controls | JAN PEREZ | energy_progress |
| 08/02/2024 | Metering | JAN PEREZ | energy_progress |
| 07/27/2024 | Construction Operations Influencing Adjacent Structures | JAN PEREZ | special |
| 07/27/2024 | Fire-Resistant Penetrations and Joints | JAN PEREZ | special |
| 07/27/2024 | Sprayed fire-resistant materials | JAN PEREZ | special |
| 07/27/2024 | Structural Stability – Alterations of existing buildings | JAN PEREZ | special |
| 07/27/2024 | Tenant Protection Plan Compliance | — | special |
| 07/27/2024 | Energy Code Compliance Inspections | JAN PEREZ | progress |
| 07/27/2024 | Fire-Resistance Rated Construction | JAN PEREZ | progress |
| 07/27/2024 | Insulation placement and R values | JAN PEREZ | energy_progress |