← Back
Predominantly retail with other uses
9502 CHURCH AVENUE
BROOKLYN · BIN 3103561
💬 Discuss this project
1931Year Built
2Stories
K4Building Class
R6Zoning
3,820 sfGross Floor Area
4Units
4 Open Violations ▸FDNY Report ↗
Predominantly retail with other uses · 2,000 sf lot · 1.91 FAR built · Flood zone X
Locations of Work
Architecture
Floor 23p · 1 filing · 14 docs
Floor 14p · 1 filing · 14 docs
Cellar3p · 1 filing · 14 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AA BLDG & INSP SVC LLC309/11/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MARIA203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JOHN EVAN CONTRACTING CORGeneral Contractor603/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519210/21/2024
Building Lifecycle
All (42)Filed (3)Permit Issued (2)Violation (4)Inspection (2)Objection (22)Special Inspection (9)
09/11/2026
Filed — Alteration
INSTALL ONE NEW DOUBLE SINK ON FIRST FLOOR AT EXISTING EATING AND DRINKING ESTABLISHMENT
B01456197-I1
09/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/10/2026
Special inspection requirement — Energy Code Compliance Inspections
06/03/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/15/2025
Objection resolved — Addressed
01/07/2025
Objection resolved — Addressed
01/07/2025
Objection resolved — Addressed
11/15/2024
Objection resolved — Addressed
10/24/2024
Objection raised — Zoning
10/24/2024
Objection raised — Scope
10/24/2024
Objection raised — Admin
10/24/2024
Objection raised — Scope
10/21/2024
Filed — Alteration CO
FILING TO CORRECT INCONSISTENCY WITH EXISTING CERTIFICATE OF OCCUPANCY.
B00751330-P1
10/01/2024
Special inspection requirement — Concrete - Cast-In-Place
Younes Abouyaala
10/01/2024
Special inspection requirement — Masonry
Younes Abouyaala
10/01/2024
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
10/01/2024
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
10/01/2024
Special inspection requirement — Lighting in dwelling units
Younes Abouyaala
10/01/2024
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
10/01/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
09/30/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/03/2024
Permit issued — General Construction
B00751330-I1-GC
01/11/2024
Permit issued — General Construction
B00751330-I1-GC
12/11/2023
Objection resolved — Addressed
11/21/2023
Objection resolved — Addressed
10/17/2023
Objection resolved — Addressed
08/18/2023
Objection resolved — Addressed
05/03/2023
Objection resolved — Addressed
03/20/2023
Objection resolved — Addressed
03/20/2023
Objection resolved — Addressed
02/06/2023
Objection raised — Zoning
02/06/2023
Objection raised — Zoning
02/06/2023
Objection raised — Other
02/06/2023
Objection raised — Structural
02/06/2023
Objection raised — Scope
02/06/2023
Objection raised — Admin
02/06/2023
Objection raised — Structural
02/01/2023
Filed — Alteration CO
FILING TO CORRECT INCONSISTENCY WITH EXISTING CERTIFICATE OF OCCUPANCY.
B00751330-I1
03/21/2004
Violation issued (HPD, open)
C
03/21/2004
Violation issued (HPD, open)
C
01/20/2004
Violation issued (HPD, open)
C
01/20/2004
Violation issued (HPD, open)
C
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedJOHN EVAN CONTRACTING COR05/03/2024
DOB NOWGeneral ConstructionPermit IssuedJOHN EVAN CONTRACTING COR01/11/2024
BISPLISSUEDD & D PLUMBING & HEATING INC04/12/2005
BIS—ISSUEDDARRARANCIO & SANZONE CONTRACT03/28/2005
BISOTISSUEDTRI-TOWER CONST INC05/26/2004
1 project · most recent 09/11/2026
Water/Sanitary
FiledStatusContractorScope
09/11/2026——Water/Sanitary
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
06/03/2026Pass-Final CND-Occupancy InspectionPassView ↗
09/30/2024Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
09/10/2026Fire-Resistant Penetrations and Joints—special
09/10/2026Energy Code Compliance Inspections—progress
10/01/2024Concrete - Cast-In-PlaceYounes Abouyaalaspecial
10/01/2024MasonryYounes Abouyaalaspecial
10/01/2024Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
10/01/2024HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
10/01/2024Lighting in dwelling unitsYounes Abouyaalaenergy_progress
10/01/2024HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
10/01/2024HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
▾Documents — 17 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
09/22/2026B01456197-I1Request digital key ↗
08/15/2026B00751330-I1Request digital key ↗
08/14/2026B00751330-P1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026B00751330-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature3
09/22/2026B01456197-I1Open ↗
08/23/2026B00751330-P1Open ↗
08/23/2026B00751330-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026B00751330-P1Open ↗
08/23/2026B00751330-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/23/2026B00751330-P1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/15/2026B00751330-I1Open ↗
08/14/2026B00751330-P1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
09/22/2026B01456197-I1Open ↗
08/15/2026B00751330-I1Open ↗
08/14/2026B00751330-P1Open ↗
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
08/15/2026B00751330-I1Open ↗
08/14/2026B00751330-P1Open ↗