1925Year Built
2Stories
B3Building Class
R5Zoning
1,472 sfGross Floor Area
2Units
Rent Stabilized26 Open Violations ▸FDNY Report ↗
Two family converted from one family · Owner of record: 143 E 39TH LLC · 2,600 sf lot · 0.57 FAR built · Flood zone X
Locations of Work
Architecture
Floor 25p · 1 filing · 12 docs
Floor 13p · 1 filing · 12 docs
Cellar1p · 1 filing · 4 docs
1 job · most recent 08/08/2025
General Wiring
FiledStatusContractorScope
08/08/2025Permit IssuedEASTERN ELEC'L CONST INCGeneral Wiring
Building Lifecycle
All (62)Filed (2)Permit Issued (2)Signed Off (1)Violation (31)Inspection (2)Objection (14)Special Inspection (10)
11/24/2025
Violation issued (HPD, open)
I
12/03/2024
Violation issued (HPD, open)
I
08/26/2024
Permit issued — General Construction
B01046478-I1-GC
07/08/2024
Objection resolved — Addressed
07/08/2024
Objection resolved — Addressed
07/08/2024
Objection resolved — Addressed
07/03/2024
Objection resolved — Addressed
07/03/2024
Objection resolved — Addressed
07/03/2024
Objection resolved — Addressed
07/03/2024
Objection resolved — Addressed
05/20/2024
Objection raised — Scope
05/20/2024
Objection raised — Structural
05/20/2024
Objection raised — Scope
05/20/2024
Objection raised — Structural
05/20/2024
Objection raised — Structural
05/20/2024
Objection raised — Scope
05/20/2024
Objection raised — Structural
05/14/2024
Filed — Alteration
HEREWITH FILING FOR APPLICATION FOR INTERIOR RENOVATIONOF EXISITING 2 FAMILY HOUSE WITH REGARDS TO FIRE DAMAGE. NO CHANGE TO USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01046478-I1
05/14/2024
Special inspection requirement — Fenestration air leakage
RONALD VILLANO
05/14/2024
Special inspection requirement — Lighting in dwelling units
RONALD VILLANO
05/14/2024
Special inspection requirement — Lighting controls
RONALD VILLANO
05/14/2024
Special inspection requirement — Interior lighting power
RONALD VILLANO
05/14/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
RONALD VILLANO
05/14/2024
Special inspection requirement — Duct leakage testing, insulation and design
RONALD VILLANO
05/07/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Luis Pichardo
05/07/2024
Special inspection requirement — Sprayed fire-resistant materials
Luis Pichardo
05/06/2024
Special inspection requirement — Final
RONALD VILLANO
02/15/2024
Signed off — Alteration
B00872170-I1
02/09/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
01/17/2024
Violation issued (HPD, open)
B
01/17/2024
Violation issued (HPD, open)
B
01/17/2024
Violation issued (HPD, open)
C
01/17/2024
Violation issued (HPD, open)
C
01/17/2024
Violation issued (HPD, open)
B
01/15/2024
Violation issued (HPD, closed)
C
12/27/2023
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
12/20/2023
Violation issued (HPD, open)
C
12/20/2023
Violation issued (HPD, open)
C
12/17/2023
Violation issued (HPD, open)
B
12/17/2023
Violation issued (HPD, open)
B
12/17/2023
Violation issued (HPD, open)
C
12/17/2023
Violation issued (HPD, open)
C
12/01/2023
Violation issued (HPD, closed)
C
12/01/2023
Violation issued (HPD, open)
C
08/21/2023
Violation issued (HPD, closed)
I
08/19/2023
Violation issued (HPD, open)
B
08/19/2023
Violation issued (HPD, open)
B
08/19/2023
Violation issued (HPD, open)
C
06/22/2023
Violation issued (HPD, open)
B
06/22/2023
Violation issued (HPD, open)
B
06/22/2023
Violation issued (HPD, open)
B
06/22/2023
Violation issued (HPD, open)
A
06/22/2023
Violation issued (HPD, open)
B
06/22/2023
Violation issued (HPD, open)
B
06/22/2023
Violation issued (HPD, open)
B
06/22/2023
Violation issued (HPD, open)
B
06/22/2023
Violation issued (HPD, open)
A
05/12/2023
Permit issued — General Construction
B00872170-I1-GC
05/09/2023
Filed — Alteration
B00872170-I1
05/09/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
NASHAT IBRAHIM
Latest 60 of 62 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
EWART503/22/2026
143 E 39 TH LLC103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AZSK ARCHITECTS PC105/14/2024
NMI ARCHITECTURE, PLLC105/09/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NMI ARCHITECTURE PLLC203/21/2026
MMSR CONSULTING GROUP LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ARIES CONSTRUCTION CO,INCGeneral Contractor303/21/2026
KINGDOM CONTRACTING LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUILDTECH ENGINEERING6369105/14/2024
NMI ARCHITECTURE, PLLC6825105/09/2023
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedARIES CONSTRUCTION CO,INC08/26/2024
DOB NOWGeneral ConstructionSigned-offKINGDOM CONTRACTING LLC05/12/2023
BISOTISSUEDCENTURION SOLAR ENERGY09/12/2016
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
02/09/2024Pass-Final General Construction Non-Directive 14PassView ↗
12/27/2023Fail-Final General Construction Non-Directive 14FailView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
05/14/2024Fenestration air leakageRONALD VILLANOenergy_progress
05/14/2024Lighting in dwelling unitsRONALD VILLANOenergy_progress
05/14/2024Lighting controlsRONALD VILLANOenergy_progress
05/14/2024Interior lighting powerRONALD VILLANOenergy_progress
05/14/2024Fenestration and door U-factor and product ratingsRONALD VILLANOenergy_progress
05/14/2024Duct leakage testing, insulation and designRONALD VILLANOenergy_progress
05/07/2024Fire-Resistant Penetrations and JointsLuis Pichardospecial
05/07/2024Sprayed fire-resistant materialsLuis Pichardospecial
05/06/2024FinalRONALD VILLANOprogress
05/09/2023Fire-Resistant Penetrations and JointsNASHAT IBRAHIMspecial
▾Documents — 33 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/27/2026B00872170-I1Request digital key ↗
08/25/2026B01046478-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
09/07/2016340419540Open ↗
▸BISWORK PERMIT APPLICATION1
09/12/2016340419540Open ↗
▸Seals & Professional Certifications13
▸DOB NOWProgress Inspector Seal & Signature7
08/31/2026B01046478-I1Open ↗
08/31/2026B01046478-I1Open ↗
08/31/2026B01046478-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/31/2026B01046478-I1Open ↗
08/31/2026B01046478-I1Open ↗
08/22/2026B00872170-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/27/2026B00872170-I1Open ↗
08/13/2026B01046478-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
09/09/2016340419540Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
09/09/2016340419540Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/27/2026B00872170-I1Open ↗
08/13/2026B01046478-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
09/09/2016340419540Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
01/06/2017340419540Open ↗
09/07/2016340419540Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
12/29/2016340419540Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
09/09/2016340419540Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/29/2016340419540Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
12/29/2016340419540Open ↗
09/07/2016340419540Open ↗
▸Approvals, Objections & Sign-offs2
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
12/29/2016340419540Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/29/2016340419540Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
12/29/2016340419540Open ↗
09/09/2016340419540Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
09/07/2016340419540Open ↗