← Back
Five to six families
1060 ROGERS AVENUE
BROOKLYN · BIN 3119108
💬 Discuss this project
1910Year Built
3Stories
C2Building Class
R6Zoning
4,800 sfGross Floor Area
5Units
Rent Stabilized39 Open Violations ▸FDNY Report ↗
Five to six families · Owner of record: 1060 ROGERS CORP. · 2,000 sf lot · 2.4 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 13p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TAQWA REALTY INVESTMENT603/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TSL ARCHITECT,P.C.310/16/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DAVILAS CONTRACTOR CORPGeneral Contractor203/21/2026
DYNAMIC PLBG & SPRKLR CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
IP CONCRETE TESTING AND I6252210/16/2025
AA BUILDING & INSPECTION1519108/21/2023
Building Lifecycle
All (105)Filed (3)Permit Issued (2)Violation (60)Inspection (8)Objection (24)Special Inspection (8)
05/05/2026
Violation issued (HPD, closed)
A
11/20/2025
Violation issued (HPD, closed)
I
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/30/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
10/17/2025
Special inspection requirement — Energy Code Compliance Inspections
TAI LAWAL
10/16/2025
Filed — Alteration CO
Provide a new 3-piece fixture bathroom and kitchen sink, add a new range/stove, and connect to the existing gas meter for the water heater
B00904460-P1
09/22/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/30/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/16/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
07/16/2025
Special inspection requirement — Energy Code Compliance Inspections
TAI LAWAL
07/14/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/02/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/02/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/27/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/10/2025
Permit issued — Plumbing
B00904460-S1-PL
06/10/2025
Violation issued (HPD, closed)
A
02/05/2025
Permit issued — General Construction
B00904460-I1-GC
01/15/2025
Filed — Alteration CO
Provide a new 3-piece fixture bathroom and kitchen sink, add a new range/stove, and connect to the existing gas meter for the water heater
B00904460-S1
12/10/2024
Objection resolved — Addressed
12/10/2024
Objection resolved — Addressed
12/04/2024
Objection resolved — Addressed
12/04/2024
Objection resolved — Addressed
12/04/2024
Objection resolved — Addressed
12/04/2024
Objection resolved — Addressed
11/01/2024
Objection resolved — Addressed
10/20/2024
Objection resolved — Addressed
10/08/2024
Objection resolved — Addressed
10/08/2024
Objection resolved — Addressed
10/08/2024
Objection resolved — Addressed
10/08/2024
Objection resolved — Addressed
10/03/2024
Objection raised — Accessibility
10/03/2024
Objection raised — Structural
10/03/2024
Objection raised — Accessibility
10/03/2024
Objection raised — Other
10/03/2024
Objection raised — Other
10/03/2024
Objection raised — Other
10/03/2024
Objection raised — Fire_Protection
10/03/2024
Objection raised — Accessibility
10/03/2024
Objection raised — Scope
10/03/2024
Objection raised — Accessibility
10/02/2024
Objection raised — Fire_Protection
08/28/2024
Violation issued (HPD, closed)
B
08/28/2024
Violation issued (HPD, closed)
C
07/10/2024
Violation issued (HPD, open)
C
07/10/2024
Violation issued (HPD, open)
B
06/01/2024
Violation issued (HPD, open)
B
06/01/2024
Violation issued (HPD, open)
B
06/01/2024
Violation issued (HPD, open)
B
06/01/2024
Violation issued (HPD, open)
B
06/01/2024
Violation issued (HPD, open)
A
06/01/2024
Violation issued (HPD, open)
B
06/01/2024
Violation issued (HPD, closed)
A
06/01/2024
Violation issued (HPD, open)
A
06/01/2024
Violation issued (HPD, open)
B
06/01/2024
Violation issued (HPD, closed)
C
11/28/2023
Violation issued (HPD, open)
B
11/28/2023
Violation issued (HPD, open)
B
08/30/2023
Objection raised — Zoning
Latest 60 of 105 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCITYWIDE PLBG HTG & SPKLS06/10/2025
DOB NOWGeneral ConstructionPermit IssuedDAVILAS CONTRACTOR CORP02/05/2025
BISBLISSUEDABC FUEL OIL CO INC12/28/1993
BISPLISSUEDPULLINI WATER MAIN & SEWER08/26/1993
BISOTISSUEDLUIFRAN CONSTRUCTION CO08/26/1993
1 project · most recent 10/16/2025
Gas Water/Sanitary
FiledStatusContractorScope
10/16/2025Signed-offDYNAMIC PLBG & SPRKLR CORGas, Water/Sanitary
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
10/30/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/22/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/30/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/16/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/14/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/02/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/02/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/27/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
10/17/2025Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
10/17/2025Energy Code Compliance InspectionsTAI LAWALprogress
07/16/2025Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
07/16/2025Energy Code Compliance InspectionsTAI LAWALprogress
08/17/2023Lighting in dwelling unitsTAI LAWALenergy_progress
08/17/2023Insulation placement and R valuesTAI LAWALenergy_progress
07/14/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
07/14/2023Energy Code Compliance InspectionsTAI LAWALprogress
▾Documents — 29 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/20/2026B00904460-P1Request digital key ↗
08/20/2026B00904460-S1Request digital key ↗
08/15/2026B00904460-I1Request digital key ↗
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION3
05/22/2024300291743Open ↗
05/21/2024300291743Open ↗
09/22/2021302281386Open ↗
▸Seals & Professional Certifications11
▸DOB NOWProgress Inspector Seal & Signature5
09/01/2026B00904460-P1Open ↗
08/31/2026B00904460-I1Open ↗
08/31/2026B00904460-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026B00904460-P1Open ↗
08/31/2026B00904460-I1Open ↗
08/26/2026B00904460-S1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/20/2026B00904460-P1Open ↗
08/20/2026B00904460-S1Open ↗
08/20/2026B00904460-I1Open ↗
▸Safety & Tenant Protection2
▸BIS* TENANT PROTECTION PLAN MEMO1/6/841
05/23/2024300291743Open ↗
▸DOB NOWStreet Tree Checklist1
08/15/2026B00904460-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/20/2026B00904460-P1Open ↗
08/20/2026B00904460-S1Open ↗
08/15/2026B00904460-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY1
08/20/2024300291743Open ↗
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
05/23/2024300291743Open ↗
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
09/06/2024300291743Open ↗
▸Other Documents4
▸BISDHCR DOCUMENT1
05/30/2024300291743Open ↗
▸BIS* FIRE STOPS 27-3451
05/23/2024300291743Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00904460-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/15/2026B00904460-I1Open ↗