| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/28/2023 | Complete | J Y ELECTRIC INC | 1 meters, 1 new_meters |
| 01/16/2019 | Complete | A ELECTRICAL MAIN SVC INC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| SEAFOOD MARKET 836 LLC | 23 | 03/22/2026 |
| DHM CONSTRUCTION | 5 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Z & T ENGINEERING, P.C. | 1 | 06/12/2024 |
| GLOBAL ARCH DESIGN & BUILD INC. | 6 | 04/09/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KLE CONSTRUCTION INC | General Contractor | 9 | 03/21/2026 |
| A ELECTRICAL MAIN SVC INC | Electrical | 1 | 03/22/2026 |
| VMC PLUMBING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Z & T ENGINEERING, P.C. | 591 | 1 | 06/12/2024 |
| G ENGINEERING PC | 7778 | 3 | 04/09/2024 |
| M. INT'L ENGINEERING PLLC | 3129 | 3 | 02/23/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | KLE CONSTRUCTION INC | 06/21/2024 |
| DOB NOW | General Construction | Signed-off | KLE CONSTRUCTION INC | 11/14/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KLE CONSTRUCTION INC | 11/14/2023 |
| DOB NOW | Plumbing | Signed-off | M. SPINELLI PLB & HTG INC | 10/12/2023 |
| BIS | SP | ISSUED | AUTOMATIC FIRE SPRKLR INSTALL | 04/03/1997 |
| BIS | EQ | ISSUED | DHM CONST CORP | 06/27/1995 |
| BIS | OT | ISSUED | DHM CONST CORP | 06/27/1995 |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/28/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/02/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/30/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/11/2024 | Air barrier - visual inspection | XIONGCAI GU | energy_progress |
| 04/11/2024 | Mechanical Systems | XIONGCAI GU | special |
| 04/11/2024 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 04/11/2024 | Final | XIONGCAI GU | progress |
| 04/11/2024 | Fire-Resistance Rated Construction | XIONGCAI GU | progress |
| 04/11/2024 | Interior lighting power | XIONGCAI GU | energy_progress |
| 04/11/2024 | Maintenance information | XIONGCAI GU | energy_progress |
| 02/26/2024 | HVAC-R and service water heating equipment | NANIK MASSAND | energy_progress |
| 02/26/2024 | HVAC-R and service water piping design and insulation | NANIK MASSAND | energy_progress |
| 02/26/2024 | HVAC-R and service water heating system controls | NANIK MASSAND | energy_progress |
| 02/26/2024 | Maintenance information | NANIK MASSAND | energy_progress |
| 02/26/2024 | Fire-Resistant Penetrations and Joints | NANIK MASSAND | special |
| 02/21/2024 | Fire-Resistant Penetrations and Joints | NANIK MASSAND | special |
| 02/21/2024 | Maintenance information | NANIK MASSAND | energy_progress |
| 02/21/2024 | HVAC-R and service water heating equipment | NANIK MASSAND | energy_progress |
| 02/21/2024 | HVAC-R and service water piping design and insulation | NANIK MASSAND | energy_progress |
| 02/21/2024 | HVAC-R and service water heating system controls | NANIK MASSAND | energy_progress |
| 11/28/2023 | Final | XIONGCAI GU | progress |
| 11/28/2023 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 11/28/2023 | Fire-Resistant Penetrations and Joints | NANIK MASSAND | special |
| 11/28/2023 | HVAC-R and service water piping design and insulation | NANIK MASSAND | energy_progress |
| 11/28/2023 | HVAC-R and service water heating equipment | NANIK MASSAND | energy_progress |
| 11/28/2023 | Maintenance information | NANIK MASSAND | energy_progress |
| 11/28/2023 | HVAC-R and service water heating system controls | NANIK MASSAND | energy_progress |
| 11/28/2023 | Air barrier - visual inspection | XIONGCAI GU | energy_progress |