← Back
Three families
1165 OVINGTON AVENUE
BROOKLYN · BIN 3142828
💬 Discuss this project
1925Year Built
2Stories
C0Building Class
R5BZoning
3,240 sfGross Floor Area
3Units
Rent Stabilized3 Open Violations 1 unresolved · 2 paperwork only ▸
Three families · 3,933 sf lot · 0.82 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction2p · 1 filing · 20 docs
Floor 1Under Construction2p · 1 filing · 20 docs
CellarUnder Construction11p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
INNOSPARK DESIGN609/13/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AARON MCDONALD ARCHITECT607/23/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BUILDWISE CONSTRUCTION GRGeneral Contractor107/08/2026
W.R. PLBG AND HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AARON MCDONALD ARCHITECT5118607/23/2026
Building Lifecycle
All (19)Filed (6)Permit Issued (2)Violation (11)
07/23/2026
Filed — Alteration
INSTALL NEW H.W.H, BOILER, BATHROOM AND KITCHEN FIXTURES IN THE EXISTING 2 STORY BUILDING, PLUMBING WORKS AS PER PLAN, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01385683-P4
07/22/2026
Filed — Alteration
INSTALL NEW H.W.H, BOILER, BATHROOM AND KITCHEN FIXTURES IN THE EXISTING 2 STORY BUILDING, PLUMBING WORKS AS PER PLAN, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01385683-P3
06/22/2026
Violation issued (ECB, open)
Construction
06/22/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/22/2026
Violation issued (ECB, open)
Construction
05/12/2026
Filed — Alteration
INSTALL NEW H.W.H, BOILER, BATHROOM AND KITCHEN FIXTURES IN THE EXISTING 2 STORY BUILDING, PLUMBING WORKS AS PER PLAN, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01385683-P1
05/12/2026
Filed — Alteration
INSTALL NEW H.W.H, BOILER, BATHROOM AND KITCHEN FIXTURES IN THE EXISTING 2 STORY BUILDING, PLUMBING WORKS AS PER PLAN, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01385683-P2
04/29/2026
Permit issued — Plumbing
B01385683-S1-PL
04/29/2026
Permit issued — Mechanical Systems
B01385683-I1-GC-CX
04/23/2026
Filed — Alteration
INSTALL NEW H.W.H, BOILER, BATHROOM AND KITCHEN FIXTURES IN THE EXISTING 2 STORY BUILDING, PLUMBING WORKS AS PER PLAN, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01385683-S1
04/23/2026
Filed — Alteration
INSTALL NEW H.W.H, BOILER, BATHROOM AND KITCHEN FIXTURES IN THE EXISTING 2 STORY BUILDING, PLUMBING WORKS AS PER PLAN, NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
B01385683-I1
06/10/2025
Violation issued (HPD, closed)
A
04/11/2024
Violation issued (HPD, closed)
A
03/24/2023
Violation issued (HPD, closed)
A
03/01/2022
Violation issued (HPD, closed)
I
03/01/2022
Violation issued (HPD, closed)
A
04/12/2021
Violation issued (HPD, closed)
I
04/12/2021
Violation issued (HPD, closed)
A
02/24/2015
Violation issued (HPD, closed)
I
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedW.R. PLBG AND HTG CORP04/29/2026
DOB NOWMechanical SystemsPermit IssuedBUILDWISE CONSTRUCTION GR04/29/2026
1 project · most recent 07/23/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/23/2026Permit IssuedBUILDWISE CONSTRUCTION GRAir Conditioning Systems
Cooling
Mitsubishi Electric N/A 25,000 BTU · Condensing Unit ×15
1 project · most recent 07/23/2026
Gas Water/Sanitary
FiledStatusContractorScope
07/23/2026Permit IssuedW.R. PLBG AND HTG CORPGas, Water/Sanitary
1 project · most recent 05/31/2026
General Wiring
FiledStatusContractorScope
05/31/2026Permit IssuedCL ELECTRICAL CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
08/24/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/12/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
06/12/2026Pass-Final PL - UndergroundPassView ↗
06/04/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 58
DateRequirementInspectorRole
07/23/2026Fire-Resistant Penetrations and JointsAaron McDonaldspecial
07/23/2026Mechanical SystemsAaron McDonaldspecial
07/23/2026FinalAaron McDonaldprogress
07/23/2026Fire-Resistance Rated ConstructionAaron McDonaldprogress
07/23/2026Energy Code Compliance InspectionsAaron McDonaldprogress
07/23/2026HVAC-R and service water heating equipmentAaron McDonaldenergy_progress
07/23/2026Fenestration air leakageAaron McDonaldenergy_progress
07/23/2026Fenestration and door U-factor and product ratingsAaron McDonaldenergy_progress
07/23/2026HVAC-R and service water piping design and insulationAaron McDonaldenergy_progress
07/23/2026Duct leakage testing, insulation and designAaron McDonaldenergy_progress
07/23/2026Maintenance informationAaron McDonaldenergy_progress
07/23/2026Insulation placement and R valuesAaron McDonaldenergy_progress
07/23/2026Interior lighting powerAaron McDonaldenergy_progress
07/23/2026HVAC-R and service water heating system controlsAaron McDonaldenergy_progress
07/23/2026Air barrier - visual inspectionAaron McDonaldenergy_progress
07/23/2026Fenestration areasAaron McDonaldenergy_progress
07/06/2026Fenestration and door U-factor and product ratingsAaron McDonaldenergy_progress
07/06/2026Insulation placement and R valuesAaron McDonaldenergy_progress
07/06/2026HVAC-R and service water piping design and insulationAaron McDonaldenergy_progress
07/06/2026Fenestration air leakageAaron McDonaldenergy_progress
07/06/2026Maintenance informationAaron McDonaldenergy_progress
07/06/2026Air barrier - visual inspectionAaron McDonaldenergy_progress
07/06/2026Energy Code Compliance InspectionsAaron McDonaldprogress
07/06/2026HVAC-R and service water heating system controlsAaron McDonaldenergy_progress
07/06/2026HVAC-R and service water heating equipmentAaron McDonaldenergy_progress
Latest 25 of 58.
▾Documents — 67 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/17/2026B01385683-P4Request digital key ↗
08/17/2026B01385683-I1Request digital key ↗
08/17/2026B01385683-S1Request digital key ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications55
▸DOB NOWProgress Inspector Seal & Signature44
09/01/2026B01385683-P1Open ↗
09/01/2026B01385683-P1Open ↗
09/01/2026B01385683-P1Open ↗
Showing 3 of 44 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/17/2026B01385683-P4Open ↗
08/17/2026B01385683-I1Open ↗
08/17/2026B01385683-S1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026B01385683-P1Open ↗
09/01/2026B01385683-I1Open ↗
08/31/2026B01385683-P2Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/17/2026B01385683-P4Open ↗
08/17/2026B01385683-I1Open ↗
08/17/2026B01385683-S1Open ↗
Showing 3 of 6 on file for this type