1960Year Built
1Stories
E2Building Class
R6BZoning
3,100 sfGross Floor Area
3Units
0 Open ViolationsFDNY Report ↗
Contractors warehouse · Owner of record: 6803 9TH MANAGEMENT LLC · 3,124 sf lot · 0.99 FAR built · Flood zone X
Locations of Work
ArchitectureFire Protection
Bulkhead1p · 1 filing · 16 docs
Floor 32p · 1 filing · 16 docs
Floor 22p · 1 filing · 16 docs
Floor 12p · 1 filing · 16 docs
Cellar2p · 1 filing · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
6803 9TH MANAGEMENT LLC703/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/25/2025$2.0M—Private party → 6803 9TH MANAGEMENT LLC$645/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
A PLUS DESIGN INC311/21/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A PLUS DESIGN INC.603/21/2026
Building Lifecycle
All (55)Filed (3)Violation (1)Objection (44)Special Inspection (7)
04/29/2026
Objection raised — Zoning
04/29/2026
Objection raised — Fire_Protection
04/29/2026
Objection raised — Zoning
01/22/2026
Objection resolved — Addressed
01/14/2026
Objection resolved — Addressed
01/06/2026
Objection resolved — Addressed
12/02/2025
Objection raised — Fire_Protection
12/02/2025
Objection raised — Fire_Protection
11/21/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
INSTALL NEW SPRINKLER SYSTEM COMPLYING TO NFPA-13, 2022 (AS MODIFIED BY APPENDIX Q OF NYC BUILDING CODE) REQUIREMENTS ON ALL FLOORS THROUGHOUT THE BUILDING.
B01241926-S6
11/21/2025
Special inspection requirement — Post-installed Anchors
11/18/2025
Objection raised — Scope
11/18/2025
Objection raised — Cost
11/18/2025
Objection raised — Plumbing
11/11/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
INSTALL NEW SPRINKLER SYSTEM COMPLYING TO NFPA-13, 2022 (AS MODIFIED BY APPENDIX Q OF NYC BUILDING CODE) REQUIREMENTS ON ALL FLOORS THROUGHOUT THE BUILDING.
B01241926-S5
11/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
11/11/2025
Special inspection requirement — Energy Code Compliance Inspections
11/11/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
11/11/2025
Special inspection requirement — Maintenance information
11/11/2025
Special inspection requirement — HVAC-R and service water heating equipment
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Objection resolved — Addressed
09/23/2025
Special inspection requirement — Sprinkler Systems
07/23/2025
Objection raised — Fire_Protection
07/23/2025
Objection raised — Other
07/23/2025
Objection raised — Other
07/23/2025
Objection raised — Scope
07/23/2025
Objection raised — Admin
07/23/2025
Objection raised — Zoning
07/23/2025
Objection raised — Scope
07/23/2025
Objection raised — Plumbing
07/23/2025
Objection raised — Admin
07/16/2025
Objection raised — Zoning
07/16/2025
Objection raised — Scope
07/16/2025
Objection raised — Zoning
07/16/2025
Objection raised — Zoning
07/16/2025
Objection raised — Admin
07/16/2025
Objection raised — Zoning
07/16/2025
Objection raised — Admin
07/16/2025
Objection raised — Scope
07/16/2025
Objection raised — Zoning
07/07/2025
Objection raised — Code
07/07/2025
Objection raised — Zoning
07/07/2025
Objection raised — Structural
06/19/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
INSTALL NEW SPRINKLER SYSTEM COMPLYING TO NFPA-13, 2022 (AS MODIFIED BY APPENDIX Q OF NYC BUILDING CODE) REQUIREMENTS ON ALL FLOORS THROUGHOUT THE BUILDING.
B01241926-I1
11/02/2007
Violation issued (ECB, closed)
Construction
Nothing on file for this building.
1 project · most recent 11/21/2025
Sprinkler System
FiledStatusContractorScope
11/21/2025——Sprinkler System
1 project · most recent 11/21/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
11/21/2025——Gas, Storm, Water/Sanitary
1 project · most recent 11/21/2025
FiledStatusContractorScope
11/21/2025——1 scope_items
1 project · most recent 11/21/2025
Fence
FiledStatusContractorScope
11/21/2025——Fence
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
11/21/2025Post-installed Anchors—special
11/11/2025Fire-Resistant Penetrations and Joints—special
11/11/2025Energy Code Compliance Inspections—progress
11/11/2025HVAC-R and service water piping design and insulation—energy_progress
11/11/2025Maintenance information—energy_progress
11/11/2025HVAC-R and service water heating equipment—energy_progress
09/23/2025Sprinkler Systems—special
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/19/2026B01241926-I1Request digital key ↗
08/19/2026B01241926-S6Request digital key ↗
08/14/2026B01241926-S5Request digital key ↗
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram2
08/19/2026B01241926-I1Open ↗
08/13/2026B01241926-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01241926-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B01241926-I1Open ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/19/2026B01241926-S5Open ↗
08/19/2026B01241926-I1Open ↗
08/19/2026B01241926-S6Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B01241926-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B01241926-I1Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification1
08/19/2026B01241926-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01241926-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01241926-I1Open ↗