| Firm | Filings | Most Recent |
|---|---|---|
| GREAT WALL CONSULTANT PROFESSIONAL | 5 | 07/14/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMC PLBG, HTG & CLNG, INC | Plumbing | 5 | 07/08/2026 |
| PETER LI | Electrical | 4 | 03/21/2026 |
| MBC CONSTRUCTION CORP | General Contractor | 4 | 03/22/2026 |
| P L ELECL CONTRG CORP 003654 | General Contractor | 4 | 03/22/2026 |
| P.L. ELEC'L CONTR'G CORP | Electrical | 2 | 03/22/2026 |
| JZ CONSTRUCTION GROUP INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GREAT WALL CONSULTANT P.E | 5633 | 5 | 07/14/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | JZ CONSTRUCTION GROUP INC | 07/14/2021 |
| DOB NOW | Plumbing | Signed-off | AMC PLBG, HTG & CLNG, INC | 05/21/2021 |
| DOB NOW | General Construction | Signed-off | MBC CONSTRUCTION CORP | 05/14/2021 |
| BIS | OT | ISSUED | A-1 WATER MAIN & SEWER CR | 09/26/2005 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2021 | Complete | P.L. ELEC'L CONTR'G CORP | 3 meters, 3 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/27/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/27/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/02/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 05/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/25/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 08/25/2023 | HVAC-R and service water piping design and insulation | Xiong Wei Wu | energy_progress |
| 08/25/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 08/07/2023 | Fire-Resistance Rated Construction | Xiong Wei Wu | progress |
| 08/07/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 08/07/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 08/07/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 08/07/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 08/07/2023 | Fire-Resistance Rated Construction | Xiong Wei Wu | progress |
| 07/14/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 07/14/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 07/14/2023 | Fire-Resistance Rated Construction | Xiong Wei Wu | progress |
| 03/15/2023 | HVAC-R and service water piping design and insulation | Xiong Wei Wu | energy_progress |
| 03/15/2023 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 03/15/2023 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |