| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/26/2026 | — | — | Air Conditioning Systems, Heating Systems | Cooling Mitsubishi Electric MXZ-SM96TL-U1 8 tons · Vrf Outdoor ×8 Heating Mitsubishi Electric MXZ-SM96TL-U1 108,000 BTU · Vrf Outdoor ×2 mxz-sm120tl-u1 123,000 BTU · Vrf Outdoor ×2 mxz-sm96tl-U1 108,000 BTU · Vrf Outdoor ×2 mxz-sm96tl-u1 96,000 BTU · Vrf Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | — | — | 81 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | — | — | 3 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | — | — | Fence |
| Firm | Filings | Most Recent |
|---|---|---|
| BLUELION ENGINEERING LLC | 4 | 08/26/2026 |
| EYAL LEVITT ARCHITECT PC | 2 | 08/07/2026 |
| A&D ASSOCIATES, INC. | 2 | 08/07/2026 |
| J.L.RAMIREZ ARCHITECTS PC | 1 | 06/30/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | OT | ISSUED | NEW LINE CONSTRUCTIOB CORP. | 12/06/1999 |
| BIS | PL | ISSUED | FOUNTAIN OF TREVI, INC | 03/03/1999 |
| BIS | OT | ISSUED | NEW LINE CONSTRUCTIOB CORP. | 02/03/1999 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 08/20/2026 | Structural Steel - Welding | — | special |
| 08/18/2026 | Concrete - Cast-In-Place | — | special |
| 08/18/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 08/18/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 08/18/2026 | Underpinning | — | special |
| 08/18/2026 | Final | — | progress |
| 08/18/2026 | Footing and Foundation | — | progress |
| 08/18/2026 | Subgrade Inspections | — | special |
| 08/04/2026 | Ventilation and air distribution system | — | energy_progress |
| 08/04/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/04/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/04/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 08/03/2026 | Final | — | progress |
| 08/03/2026 | Sprinkler Systems | — | special |
| 08/03/2026 | Mechanical Systems | — | special |
| 06/30/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 06/30/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 06/30/2026 | Final | — | progress |
| 06/30/2026 | Footing and Foundation | — | progress |
| 06/30/2026 | Concrete - Cast-In-Place | — | special |
| 06/30/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/30/2026 | Masonry | — | special |
| 06/30/2026 | Post-installed Anchors | — | special |
| 06/30/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |