| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/19/2024 | Permit Issued | BUILDERS JOSEPH AND SONS | Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/31/2025 | Permit Issued | GREGG NY PLUMBING, INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/04/2024 | Permit Issued | KINGS ELECTRIC CO., INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/12/2023 | Permit Issued | BUILDERS JOSEPH AND SONS | Steel, Concrete |
| Owner | Filings | Most Recent |
|---|---|---|
| HIDROCK PROPERTIES | 37 | 07/08/2026 |
| BUILDERS JOSEPH AND SONS | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/10/2014 | $2.7M | — | — → — | $1,103/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CORNERSTONE DESIGNS | 5 | 03/31/2025 |
| SOLOMON ROSENZWEIG P.E P.C. | 4 | 07/12/2023 |
| LEVIN ENGINEERING PLLC | 1 | 07/26/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| CORNERSTONE DESIGNS | 4 | 03/21/2026 |
| LEVIN ENGINEERING PLLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BUILDERS JOSEPH AND SONS | General Contractor | 10 | 07/08/2026 |
| FIVE BOROUGH NYC LLC | Fire Protection | 2 | 07/08/2026 |
| GREGG NY PLUMBING, INC | Plumbing | 2 | 07/08/2026 |
| 24 SEVEN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CITY-WIDE TESTING INC | 416 | 9 | 03/31/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | GREGG NY PLUMBING, INC | 03/19/2025 |
| DOB NOW | General Construction | Permit Issued | BUILDERS JOSEPH AND SONS | 02/18/2025 |
| DOB NOW | Sprinklers | Permit Issued | FIVE BOROUGH NYC LLC | 02/13/2025 |
| DOB NOW | Plumbing | Signed-off | 24 SEVEN PLUMBING INC | 04/12/2024 |
| DOB NOW | Plumbing | Permit Issued | GREGG NY PLUMBING, INC | 03/13/2024 |
| DOB NOW | General Construction | Permit Issued | BUILDERS JOSEPH AND SONS | 02/27/2024 |
| DOB NOW | Sprinklers | Permit Issued | FIVE BOROUGH NYC LLC | 02/07/2024 |
| DOB NOW | Construction Fence | Permit Issued | BUILDERS JOSEPH AND SONS | 02/05/2024 |
| DOB NOW | Foundation | Permit Issued | BUILDERS JOSEPH AND SONS | 03/22/2023 |
| DOB NOW | Earth Work | Permit Issued | BUILDERS JOSEPH AND SONS | 03/21/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | BUILDERS JOSEPH AND SONS | 03/17/2023 |
| DOB NOW | Construction Fence | Permit Issued | BUILDERS JOSEPH AND SONS | 03/02/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/05/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/20/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/16/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/25/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/24/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/28/2025 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 09/11/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 05/07/2024 | Fail-Final SD - Fire Pump | Fail | View ↗ |
| 04/17/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/22/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/22/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/17/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/28/2025 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 03/28/2025 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 12/02/2024 | Heating Systems | ELIAS RASABI | special |
| 12/02/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | ELIAS RASABI | special |
| 12/02/2024 | Fire-Resistant Penetrations and Joints | ELIAS RASABI | special |
| 12/02/2024 | Mechanical Systems | ELIAS RASABI | special |
| 12/02/2024 | Fire-Resistance Rated Construction | ELIAS RASABI | progress |
| 12/02/2024 | Final | ELIAS RASABI | progress |
| 12/02/2024 | Energy Code Compliance Inspections | ELIAS RASABI | progress |
| 12/02/2024 | Metering | ELIAS RASABI | energy_progress |
| 12/02/2024 | Insulation placement and R values | ELIAS RASABI | energy_progress |
| 12/02/2024 | Electric vehicle service equipment requirements | ELIAS RASABI | energy_progress |
| 12/02/2024 | Permanent certificate | ELIAS RASABI | energy_progress |
| 12/02/2024 | Maintenance information | ELIAS RASABI | energy_progress |
| 12/02/2024 | Duct leakage testing, insulation and design | ELIAS RASABI | energy_progress |
| 12/02/2024 | Fenestration areas | ELIAS RASABI | energy_progress |
| 12/02/2024 | Fenestration and door U-factor and product ratings | ELIAS RASABI | energy_progress |
| 12/02/2024 | Interior lighting power | ELIAS RASABI | energy_progress |
| 12/02/2024 | HVAC-R and service water heating equipment | ELIAS RASABI | energy_progress |
| 12/02/2024 | Fenestration air leakage | ELIAS RASABI | energy_progress |
| 12/02/2024 | Protection of exposed foundation insulation | ELIAS RASABI | energy_progress |
| 12/02/2024 | Air barrier — testing | ELIAS RASABI | energy_progress |
| 12/02/2024 | HVAC-R and service water heating system controls | ELIAS RASABI | energy_progress |
| 12/02/2024 | Air barrier - visual inspection | ELIAS RASABI | energy_progress |
| 12/02/2024 | HVAC-R and service water piping design and insulation | ELIAS RASABI | energy_progress |