| Firm | Filings | Most Recent |
|---|---|---|
| AL FFRED ARCHITECTURE PLLC | 5 | 12/14/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| MISTER EXPEDITER | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KHAIKA CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| BHY CONTRACTOR INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| M. INT'L ENGINEERING PLLC | 3129 | 3 | 09/06/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | KHAIKA CONSTRUCTION INC | 12/03/2022 |
| DOB NOW | General Construction | Permit Issued | BHY CONTRACTOR INC | 11/22/2022 |
| BIS | OT | ISSUED | RICHY INC | 05/27/2005 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/14/2022 | Permit Issued | KHAIKA CONSTRUCTION INC | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/14/2022 | Permit Issued | KHAIKA CONSTRUCTION INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/06/2022 | Fire-Resistant Penetrations and Joints | NANIK MASSAND | special |
| 09/06/2022 | Energy Code Compliance Inspections | NANIK MASSAND | progress |
| 09/06/2022 | Fire-Resistance Rated Construction | NANIK MASSAND | progress |
| 09/06/2022 | Insulation placement and R values | — | energy_progress |
| 08/29/2022 | Final | Kevin McCray | progress |
| 08/29/2022 | Structural Stability – Alterations of existing buildings | NANIK MASSAND | special |
| 08/29/2022 | Footing and Foundation | NANIK MASSAND | progress |
| 08/15/2022 | Structural Stability – Alterations of existing buildings | NANIK MASSAND | special |
| 08/15/2022 | Structural Wood Frame | NANIK MASSAND | progress |
| 07/01/2022 | Final | Kevin McCray | progress |
| 05/19/2022 | Lighting in dwelling units | NANIK MASSAND | energy_progress |
| 05/19/2022 | Fire-Resistant Penetrations and Joints | NANIK MASSAND | special |
| 05/19/2022 | Energy Code Compliance Inspections | NANIK MASSAND | progress |
| 05/19/2022 | Fire-Resistance Rated Construction | NANIK MASSAND | progress |
| 05/19/2022 | Fenestration areas | NANIK MASSAND | energy_progress |
| 05/19/2022 | Air barrier - visual inspection | NANIK MASSAND | energy_progress |
| 05/19/2022 | Fenestration and door U-factor and product ratings | NANIK MASSAND | energy_progress |
| 05/19/2022 | Fenestration air leakage | NANIK MASSAND | energy_progress |
| 05/19/2022 | Insulation placement and R values | NANIK MASSAND | energy_progress |
| 05/19/2022 | Interior lighting power | NANIK MASSAND | energy_progress |