| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/10/2025 | $4.9M | — | Private party → Private party | $1,487/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| HESHAM ELSHAMY PE | 4 | 07/07/2026 |
| EYAL LEVITT ARCHITECT PC | 3 | 06/15/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| DCS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RHY CONSTRUCTION LLC | General Contractor | 3 | 09/25/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CITY-WIDE TESTING INC | 416 | 2 | 07/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | RHY CONSTRUCTION LLC | 09/24/2026 |
| DOB NOW | Earth Work | Permit Issued | RHY CONSTRUCTION LLC | 09/24/2026 |
| DOB NOW | Construction Fence | Permit Issued | RHY CONSTRUCTION LLC | 08/14/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/07/2026 | Permit Issued | RHY CONSTRUCTION LLC | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2026 | Permit Issued | RHY CONSTRUCTION LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/22/2026 | Structural Steel - Details | — | special |
| 06/22/2026 | Structural Cold-Formed Steel | — | special |
| 06/08/2026 | Energy Code Compliance Inspections | — | progress |
| 06/08/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/08/2026 | Maintenance information | — | energy_progress |
| 06/08/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/08/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/08/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/08/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/08/2026 | Post-installed Anchors | — | special |
| 06/08/2026 | Energy Code Compliance Inspections | — | progress |
| 06/08/2026 | Duct leakage testing, insulation and design | — | energy_progress |
| 06/08/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/08/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 06/08/2026 | Maintenance information | — | energy_progress |
| 06/08/2026 | Ventilation and air distribution system | — | energy_progress |
| 06/08/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/08/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 02/09/2026 | Final | — | progress |
| 02/05/2026 | Final | — | progress |
| 02/05/2026 | Mechanical Systems | — | special |