| Firm | Filings | Most Recent |
|---|---|---|
| BASIC GROUPS CORP | 2 | 08/14/2023 |
| KL INNOVATIVE DESIGN INC | 1 | 09/30/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BASIC GROUPS | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SEGA CONTRACTING CORP | General Contractor | 4 | 07/08/2026 |
| AMM GEN'L CONTRACTING INC | Plumbing | 4 | 07/08/2026 |
| VMC PLUMBING & HEATING IN | Plumbing | 3 | 07/08/2026 |
| SIGNATURE CONSTRUCTION GROUP | General Contractor | 2 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ANDREW GOODRICH, P.E., PL | 965 | 1 | 08/14/2023 |
| BEALIN GROUPS CORP | 9869 | 1 | 09/30/2021 |
| KL INNOVATIVE DESIGN INC | 7225 | 1 | 09/30/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | M. SPINELLI PLB & HTG INC | 01/17/2024 |
| DOB NOW | General Construction | Permit Issued | SEGA CONTRACTING CORP | 09/22/2023 |
| DOB NOW | Plumbing | Signed-off | AMM GEN'L CONTRACTING INC | 10/28/2021 |
| DOB NOW | General Construction | Permit Issued | SEGA CONTRACTING CORP | 10/13/2021 |
| BIS | OT | ISSUED | NEW PROTECHT CONTRACTING INC. | 08/08/2003 |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/05/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/20/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/30/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/15/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/17/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/14/2023 | HVAC-R and service water heating system controls | ANDREW GOODRICH | energy_progress |
| 08/14/2023 | Fire-Resistant Penetrations and Joints | ANDREW GOODRICH | special |
| 08/14/2023 | Energy Code Compliance Inspections | ANDREW GOODRICH | progress |
| 08/14/2023 | HVAC-R and service water heating equipment | ANDREW GOODRICH | energy_progress |
| 08/14/2023 | HVAC-R and service water piping design and insulation | ANDREW GOODRICH | energy_progress |
| 08/11/2023 | Fire-Resistant Penetrations and Joints | ANDREW GOODRICH | special |
| 08/11/2023 | Energy Code Compliance Inspections | ANDREW GOODRICH | progress |
| 08/11/2023 | HVAC-R and service water heating system controls | ANDREW GOODRICH | energy_progress |
| 08/11/2023 | HVAC-R and service water piping design and insulation | ANDREW GOODRICH | energy_progress |
| 08/11/2023 | HVAC-R and service water heating equipment | ANDREW GOODRICH | energy_progress |