← Back
Primarily 1 family with 1 store or office
1431 CONEY ISLAND AVENUE
BROOKLYN · BIN 3179843
💬 Discuss this project
1931Year Built
2Stories
S1Building Class
R5Zoning
2,480 sfGross Floor Area
2Units
1 Open Violation ▸FDNY Report ↗
Primarily 1 family with 1 store or office · Owner of record: 1431 CONEY ISLAND AVE LLC · 2,000 sf lot · 1.24 FAR built · Flood zone X
Locations of Work
Mechanical
Roof3p · 1 filing · 6 docs
Floor 13p · 1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ASHRAF CORP102/28/2022
ALBERTO ROMAN312/13/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AN TONG FAN203/21/2026
XPDITE GROUP LLC (104)603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYC CONSTRUCTION INCGeneral Contractor307/08/2026
IDEAL KITCHEN & VENTILATIGeneral Contractor107/08/2026
H BRONNER & SON PLBG & HTGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JAY KAVI CORPORATION8500102/28/2022
ESNYC CONSULTING INC4099312/13/2021
Building Lifecycle
All (52)Filed (4)Permit Issued (4)Signed Off (4)Violation (8)Inspection (2)Objection (6)Special Inspection (24)
06/12/2025
Violation issued (FDNY_ORDER, closed)
05/02/2024
Violation issued (FDNY_ORDER, closed)
02/13/2023
Signed off — Alteration
FILING FOR THE NEW KITCHEN HOOD, EXHAUST FAN AND ASSOCIATED DUCT WORK AS PER PLAN SHOWS. THERE IS NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00654979-I1
06/03/2022
Signed off — Alteration
APPLICATION FILED HEREWITH FOR MINOR INTERIOR RENOVATION TO "FRONT OF HOUSE" OF A BAGEL SHOP LOCATED ON THE FIRST FLOOR, NO CHANGE OF USE, EGRESS, OR CERTIFICATE OF OCCUPANCY.
B00577703-I1
06/02/2022
Signed off — Alteration
APPLICATION FILED HEREWITH FOR MINOR INTERIOR RENOVATION TO "FRONT OF HOUSE" OF A BAGEL SHOP LOCATED ON THE FIRST FLOOR, NO CHANGE OF USE, EGRESS, OR CERTIFICATE OF OCCUPANCY.
B00577703-S2
06/02/2022
Signed off — Alteration
APPLICATION FILED HEREWITH FOR MINOR INTERIOR RENOVATION TO "FRONT OF HOUSE" OF A BAGEL SHOP LOCATED ON THE FIRST FLOOR, NO CHANGE OF USE, EGRESS, OR CERTIFICATE OF OCCUPANCY.
B00577703-S1
04/09/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/10/2022
Permit issued — Mechanical Systems
B00654979-I1-MS
02/28/2022
Filed — Alteration
FILING FOR THE NEW KITCHEN HOOD, EXHAUST FAN AND ASSOCIATED DUCT WORK AS PER PLAN SHOWS. THERE IS NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B00654979-I1
01/21/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/05/2022
Permit issued — Mechanical Systems
B00577703-S2-MS
12/29/2021
Permit issued — Plumbing
B00577703-S1-PL
12/29/2021
Special inspection requirement — Mechanical Systems
Jay Kavi
12/29/2021
Special inspection requirement — Final
BRIAN MCCAFFREY
12/29/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jay Kavi
12/27/2021
Permit issued — General Construction
B00577703-I1-GC
12/13/2021
Filed — Alteration
APPLICATION FILED HEREWITH FOR MINOR INTERIOR RENOVATION TO "FRONT OF HOUSE" OF A BAGEL SHOP LOCATED ON THE FIRST FLOOR, NO CHANGE OF USE, EGRESS, OR CERTIFICATE OF OCCUPANCY.
B00577703-S2
12/10/2021
Special inspection requirement — Energy Code Compliance Inspections
sajjad javaid
12/10/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
sajjad javaid
12/10/2021
Special inspection requirement — Fire-Resistance Rated Construction
sajjad javaid
12/10/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
sajjad javaid
12/10/2021
Special inspection requirement — HVAC-R and service water heating equipment
sajjad javaid
12/10/2021
Special inspection requirement — Shutoff dampers
sajjad javaid
12/10/2021
Special inspection requirement — Permanent certificate
sajjad javaid
12/10/2021
Special inspection requirement — HVAC-R and service water heating system controls
sajjad javaid
12/10/2021
Special inspection requirement — Maintenance information
sajjad javaid
11/01/2021
Special inspection requirement — Mechanical Systems
sajjad javaid
11/01/2021
Special inspection requirement — Final
sajjad javaid
10/11/2021
Filed — Alteration
APPLICATION FILED HEREWITH FOR MINOR INTERIOR RENOVATION TO "FRONT OF HOUSE" OF A BAGEL SHOP LOCATED ON THE FIRST FLOOR, NO CHANGE OF USE, EGRESS, OR CERTIFICATE OF OCCUPANCY.
B00577703-S1
08/31/2021
Objection resolved — Addressed
08/27/2021
Objection resolved — Addressed
08/27/2021
Objection resolved — Addressed
08/24/2021
Objection raised — Other
08/24/2021
Objection raised — Other
08/24/2021
Objection raised — Other
08/19/2021
Filed — Alteration
APPLICATION FILED HEREWITH FOR MINOR INTERIOR RENOVATION TO "FRONT OF HOUSE" OF A BAGEL SHOP LOCATED ON THE FIRST FLOOR, NO CHANGE OF USE, EGRESS, OR CERTIFICATE OF OCCUPANCY.
B00577703-I1
08/19/2021
Special inspection requirement — Final
sajjad javaid
08/19/2021
Special inspection requirement — Fenestration areas
sajjad javaid
08/19/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
sajjad javaid
08/19/2021
Special inspection requirement — Air barrier - visual inspection
sajjad javaid
08/19/2021
Special inspection requirement — Fenestration air leakage
sajjad javaid
08/19/2021
Special inspection requirement — Insulation placement and R values
sajjad javaid
08/19/2021
Special inspection requirement — Interior lighting power
sajjad javaid
08/19/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
sajjad javaid
08/19/2021
Special inspection requirement — Fire-Resistance Rated Construction
sajjad javaid
08/19/2021
Special inspection requirement — Energy Code Compliance Inspections
sajjad javaid
05/04/1998
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/10/1997
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/29/1995
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/01/1994
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/16/1993
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/01/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedIDEAL KITCHEN & VENTILATI03/10/2022
DOB NOWMechanical SystemsSigned-offNYC CONSTRUCTION INC01/05/2022
DOB NOWPlumbingSigned-offH BRONNER & SON PLBG & HT12/29/2021
DOB NOWGeneral ConstructionSigned-offNYC CONSTRUCTION INC12/27/2021
BISMHISSUEDMIDTOWN AIR CONDITIONING08/27/1998
6 projects · most recent 06/26/2022
General Wiring
FiledStatusContractorScope
06/26/2022CompleteSIDNEY ELEC'L CONT'G INC.General Wiring
06/16/2022CompleteSIDNEY ELEC'L CONT'G INC.General Wiring
01/02/2022CompleteSIDNEY ELEC'L CONT'G INC.—
10/25/2021CompleteSIDNEY ELEC'L CONT'G INC.2 meters, 1 new_meters
08/25/2021CompleteSIDNEY ELEC'L CONT'G INC.General Wiring
12/01/2020CompleteSIDNEY ELEC'L CONT'G INC.General Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
04/09/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/21/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
12/29/2021Mechanical SystemsJay Kavispecial
12/29/2021FinalBRIAN MCCAFFREYprogress
12/29/2021Fire-Resistant Penetrations and JointsJay Kavispecial
12/10/2021Energy Code Compliance Inspectionssajjad javaidprogress
12/10/2021Fire-Resistant Penetrations and Jointssajjad javaidspecial
12/10/2021Fire-Resistance Rated Constructionsajjad javaidprogress
12/10/2021HVAC-R and service water piping design and insulationsajjad javaidenergy_progress
12/10/2021HVAC-R and service water heating equipmentsajjad javaidenergy_progress
12/10/2021Shutoff damperssajjad javaidenergy_progress
12/10/2021Permanent certificatesajjad javaidenergy_progress
12/10/2021HVAC-R and service water heating system controlssajjad javaidenergy_progress
12/10/2021Maintenance informationsajjad javaidenergy_progress
11/01/2021Mechanical Systemssajjad javaidspecial
11/01/2021Finalsajjad javaidprogress
08/19/2021Finalsajjad javaidprogress
08/19/2021Fenestration areassajjad javaidenergy_progress
08/19/2021Fenestration and door U-factor and product ratingssajjad javaidenergy_progress
08/19/2021Air barrier - visual inspectionsajjad javaidenergy_progress
08/19/2021Fenestration air leakagesajjad javaidenergy_progress
08/19/2021Insulation placement and R valuessajjad javaidenergy_progress
08/19/2021Interior lighting powersajjad javaidenergy_progress
08/19/2021Fire-Resistant Penetrations and Jointssajjad javaidspecial
08/19/2021Fire-Resistance Rated Constructionsajjad javaidprogress
08/19/2021Energy Code Compliance Inspectionssajjad javaidprogress
▾Documents — 39 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/01/2026B00577703-S2Request digital key ↗
09/01/2026B00577703-S1Request digital key ↗
08/31/2026B00654979-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications28
▸DOB NOWProgress Inspector Seal & Signature19
09/01/2026B00577703-S2Open ↗
09/01/2026B00577703-S2Open ↗
09/01/2026B00577703-S2Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026B00577703-S2Open ↗
09/01/2026B00577703-S2Open ↗
08/24/2026B00577703-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/01/2026B00577703-I1Open ↗
09/01/2026B00577703-S1Open ↗
09/01/2026B00577703-S2Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
09/01/2026B00577703-S2Open ↗
09/01/2026B00577703-S1Open ↗
08/14/2026B00577703-I1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance3
▸DOB NOWEN2: As Built Energy Analysis.3
08/13/2026B00577703-I1Open ↗
08/13/2026B00577703-S1Open ↗
08/13/2026B00577703-S2Open ↗