← Back
General warehouse
26 COBECK COURT
BROOKLYN · BIN 3195645
💬 Discuss this project
1930Year Built
2Stories
E1Building Class
M1-1Zoning
10,300 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
General warehouse · Owner of record: LOPOPOLO PROPERTIES L · 11,741 sf lot · 0.88 FAR built · Flood zone X500
Locations of Work
Plumbing
Roof1p · 1 filing · 3 docs
Floor 11p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
300 AVE Y403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ATOZ CONSULTING ENGINEERS, PC106/21/2022
MORALI ARCHITECTURE103/30/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ANTHONY MORALI ARCHITECT PLLC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JUAN RAMIREZElectrical103/21/2026
Building Lifecycle
All (60)Filed (2)Violation (2)Objection (36)Special Inspection (20)
06/27/2022
Special inspection requirement — Mastic and Intumescent Fire-resistant Coatings
06/21/2022
Filed — Alteration
B00736425-I1
06/03/2022
Objection raised — Other
06/03/2022
Objection resolved — Addressed
06/03/2022
Objection raised — Other
06/03/2022
Objection resolved — Addressed
06/03/2022
Objection raised — Other
06/03/2022
Objection resolved — Addressed
02/09/2022
Objection raised — Admin
02/09/2022
Objection resolved — Addressed
01/13/2022
Objection raised — Zoning
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection raised — Zoning
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection raised — Other
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection raised — Zoning
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection raised — Admin
01/13/2022
Objection resolved — Addressed
01/13/2022
Objection raised — 1998-AN FC 504.4.4 TPPN 5/98-F
01/13/2022
Objection resolved — Addressed
05/28/2021
Objection raised — Zoning
05/28/2021
Objection resolved — Addressed
05/26/2021
Objection raised — Admin
05/26/2021
Objection resolved — Addressed
04/06/2021
Special inspection requirement — Air barrier - visual inspection
04/06/2021
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
04/06/2021
Special inspection requirement — Exterior lighting power
04/06/2021
Special inspection requirement — Concrete - Cast-In-Place
04/06/2021
Special inspection requirement — Energy Code Compliance Inspections
04/06/2021
Special inspection requirement — Insulation placement and R values
04/06/2021
Special inspection requirement — Fire-Resistance Rated Construction
04/01/2021
Objection raised — Other
04/01/2021
Objection resolved — Addressed
04/01/2021
Objection raised — Other
04/01/2021
Objection resolved — Addressed
04/01/2021
Objection raised — Other
04/01/2021
Objection resolved — Addressed
04/01/2021
Objection raised — Other
04/01/2021
Objection resolved — Addressed
04/01/2021
Objection raised — Other
04/01/2021
Objection resolved — Addressed
04/01/2021
Objection raised — Inspection report required for
04/01/2021
Objection resolved — Addressed
03/30/2021
Filed — Alteration CO
enlarging existing two story warehouse/office building. convert to commercial retail with accessory storage. related construction work, facade work, structural and foundation work for enlargement. install one fresh air intake.
B00479801-I1
03/03/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
03/03/2021
Special inspection requirement — Lighting controls
03/03/2021
Special inspection requirement — Fenestration air leakage
03/03/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
03/03/2021
Special inspection requirement — Fenestration areas
03/03/2021
Special inspection requirement — Mechanical Systems
03/03/2021
Special inspection requirement — Structural Cold-Formed Steel
03/03/2021
Special inspection requirement — Structural Steel - Details
03/03/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/03/2021
Special inspection requirement — Final
03/03/2021
Special inspection requirement — Footing and Foundation
03/03/2021
Special inspection requirement — Interior lighting power
08/23/1999
Violation issued (FDNY_NOV, closed)
11/01/1988
Violation issued (FDNY_NOV, closed)
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISCCISSUEDPARTINICO CONSTRUCTION CORP08/24/2005
BISPLISSUEDMARINO PLBG AND HTG, INC12/14/2004
BIS—ISSUEDPARTINICO CONSTRUCTION CORP08/31/2004
BISEQISSUEDPARTINICO CONSTRUCTION CORP04/09/2004
BIS—ISSUEDPARTINICO CONSTRUCTION CORP07/23/2003
BISEQISSUEDPARTINICO CONSTRUCTION CORP07/08/2003
BISEQISSUEDPARTINICO CONSTRUCTION CORP01/30/2003
BIS—ISSUEDPARTINICO CONSTRUCTION CORP01/15/2003
1 project · most recent 03/30/2021
Others
FiledStatusContractorScope
03/30/2021——Others
1 project · most recent 03/03/2018
General Wiring
FiledStatusContractorScope
03/03/2018CompleteDENALI ELECTRIC CORPGeneral Wiring
1 project · most recent 03/30/2021
Steel Concrete
FiledStatusContractorScope
03/30/2021——Steel, Concrete
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
06/27/2022Mastic and Intumescent Fire-resistant Coatings—special
04/06/2021Air barrier - visual inspection—energy_progress
04/06/2021Exterior Insulation and Finish Systems (EIFS)—special
04/06/2021Exterior lighting power—energy_progress
04/06/2021Concrete - Cast-In-Place—special
04/06/2021Energy Code Compliance Inspections—progress
04/06/2021Insulation placement and R values—energy_progress
04/06/2021Fire-Resistance Rated Construction—progress
03/03/2021Fenestration and door U-factor and product ratings—energy_progress
03/03/2021Lighting controls—energy_progress
03/03/2021Fenestration air leakage—energy_progress
03/03/2021Structural Stability – Alterations of existing buildings—special
03/03/2021Fenestration areas—energy_progress
03/03/2021Mechanical Systems—special
03/03/2021Structural Cold-Formed Steel—special
03/03/2021Structural Steel - Details—special
03/03/2021Fire-Resistant Penetrations and Joints—special
03/03/2021Final—progress
03/03/2021Footing and Foundation—progress
03/03/2021Interior lighting power—energy_progress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/29/2026B00736425-I1Request digital key ↗
08/14/2026B00479801-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/14/2026B00479801-I1Open ↗
▸Seals & Professional Certifications2
▸DOB NOWDPL-1: Design Professional Seal & Signature2
09/01/2026B00479801-I1Open ↗
08/13/2026B00736425-I1Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/14/2026B00479801-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/14/2026B00479801-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/14/2026B00479801-I1Open ↗
08/13/2026B00736425-I1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/14/2026B00479801-I1Open ↗
▸DOB NOWPlot Diagram1
08/14/2026B00479801-I1Open ↗
▸DOB NOWFinal Survey1
08/14/2026B00479801-I1Open ↗