| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2024 | Permit Issued | CL ELECTRICAL CORP | General Wiring |
| 07/29/2023 | Permit Issued | CL ELECTRICAL CORP | — |
| Firm | Filings | Most Recent |
|---|---|---|
| LEVIN ENGINEERING PLLC | 2 | 03/10/2023 |
| CORNERSTONE DESIGNS | 2 | 05/15/2020 |
| HY PE STRUCTURAL ENGINEERING | 1 | 01/07/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEVIN ENGINEERING PLLC | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RHY CONSTRUCTION LLC | General Contractor | 16 | 07/08/2026 |
| SARCONA MASONRY CONTRACTING | General Contractor | 4 | 07/08/2026 |
| CHAO HONG LIANG | Electrical | 2 | 03/21/2026 |
| A + SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| 24 SEVEN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| KATAN P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HESHAM ELSHAMY ENGINEERIN | 1508 | 1 | 01/07/2020 |
| LEVIN ENGINEERING PLLC | 1267 | 1 | 10/11/2019 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | RHY CONSTRUCTION LLC | 06/04/2026 |
| DOB NOW | Construction Fence | Permit Issued | RHY CONSTRUCTION LLC | 06/03/2026 |
| DOB NOW | Construction Fence | Permit Issued | RHY CONSTRUCTION LLC | 06/20/2024 |
| DOB NOW | Structural | Permit Issued | RHY CONSTRUCTION LLC | 06/20/2024 |
| DOB NOW | Plumbing | Permit Issued | 24 SEVEN PLUMBING INC | 05/06/2024 |
| DOB NOW | Sprinklers | Permit Issued | KATAN P & H INC | 02/05/2024 |
| DOB NOW | Sprinklers | Permit Issued | A + SPRINKLER CORP | 02/02/2024 |
| DOB NOW | Structural | Permit Issued | RHY CONSTRUCTION LLC | 09/06/2023 |
| DOB NOW | Construction Fence | Permit Issued | RHY CONSTRUCTION LLC | 06/24/2023 |
| DOB NOW | Construction Fence | Permit Issued | RHY CONSTRUCTION LLC | 06/01/2023 |
| DOB NOW | Curb Cut | Permit Issued | RHY CONSTRUCTION LLC | 05/30/2023 |
| DOB NOW | Construction Fence | Permit Issued | SARCONA MASONRY CONTRACTI | 06/27/2022 |
| DOB NOW | Construction Fence | Permit Issued | SARCONA MASONRY CONTRACTI | 07/19/2021 |
| DOB NOW | Construction Fence | Permit Issued | SARCONA MASONRY CONTRACTI | 05/21/2021 |
| BIS | PL | ISSUED | KATAN P & H INC | 04/08/2024 |
| BIS | — | ISSUED | RHY CONSTRUCTION LLC | 07/12/2023 |
| BIS | — | ISSUED | RHY CONSTRUCTION LLC | 07/10/2023 |
| BIS | — | ISSUED | OMNI BUILD INC | 06/22/2023 |
| BIS | — | ISSUED | RHY CONSTRUCTION LLC | 06/22/2023 |
| BIS | — | ISSUED | RHY CONSTRUCTION LLC | 05/26/2023 |
| BIS | — | ISSUED | RHY CONSTRUCTION LLC | 05/26/2023 |
| BIS | — | ISSUED | SARCONA MASONRY CONTRACTING | 06/24/2022 |
| BIS | — | ISSUED | SARCONA MASONRY CONTRACTING | 06/24/2022 |
| BIS | — | ISSUED | SARCONA MASONRY CONTRACTING | 10/15/2021 |
| BIS | — | ISSUED | SARCONA MASONRY CONTRACTING | 10/15/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/24/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/21/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/23/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/27/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 05/13/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/07/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/04/2024 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 02/16/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/16/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/10/2023 | Sprinkler Systems | — | special |