Two stories - detached, small or mid-size · 2,600 sf lot · 0.48 FAR built · Flood zone X500
Locations of Work
Structural
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 20 docs
Floor 2Under Construction4p · 1 filing · 20 docs
Floor 1Under Construction4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SHAFAI CONSTRUCTION404/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/15/2020$785K—— → —$629/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BAALBAKI&ASSOCIATES ENGINEERING, PC410/28/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
B A INSPECTIONS803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SHAFAI CONSTRUCTION INCGeneral Contractor908/12/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BAALBAKI&ASSOCIATES ENGIN1858105/02/2023
BZINSPECTION8294105/02/2023
Building Lifecycle
All (80)Filed (4)Permit Issued (5)Violation (1)Objection (50)Special Inspection (20)
08/11/2026
Permit issued — Foundation
B00866946-I1-GC-CX
08/11/2026
Permit issued — Construction Fence
B00866946-S1-FN
03/17/2026
Permit issued — Support of Excavation
B00866946-S3-SE
01/15/2026
Objection resolved — Addressed
01/15/2026
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/30/2025
Objection resolved — Addressed
12/29/2025
Objection resolved — Addressed
12/29/2025
Objection resolved — Addressed
12/29/2025
Objection resolved — Addressed
12/29/2025
Objection resolved — Addressed
12/29/2025
Objection resolved — Addressed
12/06/2025
Violation issued (ECB, closed)
Construction
12/02/2025
Objection raised — Structural
12/02/2025
Objection raised — Structural
12/02/2025
Objection raised — Structural
12/02/2025
Objection raised — Structural
12/01/2025
Objection raised — Structural
12/01/2025
Objection raised — Structural
12/01/2025
Objection raised — Structural
12/01/2025
Objection raised — Structural
12/01/2025
Objection raised — Structural
12/01/2025
Objection raised — Structural
10/28/2025
Filed — Alteration
SUPPORT OF EXCAVATION IN CONJUNCTION WITH JOB # B00866946-I1
B00866946-S3
08/11/2025
Permit issued — Structural
B00866946-I1-GC-CX
08/01/2025
Permit issued — Construction Fence
B00866946-S1-FN
09/12/2023
Objection raised — Other
09/12/2023
Objection resolved — Addressed
07/18/2023
Special inspection requirement — Chimneys and vents
Barry Berg
07/07/2023
Objection raised — Other
07/07/2023
Objection resolved — Addressed
07/07/2023
Objection raised — Scope
07/07/2023
Objection resolved — Addressed
06/27/2023
Objection resolved — Addressed
06/26/2023
Objection raised — Structural
06/26/2023
Special inspection requirement — Subgrade Inspections
Mohammad Baalbaki
06/21/2023
Objection raised — Scope
06/21/2023
Objection resolved — Addressed
06/21/2023
Objection raised — Scope
06/21/2023
Objection resolved — Addressed
06/15/2023
Filed — Alteration
SUPPORT OF EXCAVATION IN CONJUNCTION WITH JOB # B00866946-I1
B00866946-S2
06/15/2023
Filed — Alteration
SUPPORT OF EXCAVATION IN CONJUNCTION WITH JOB # B00866946-I1
B00866946-S1
05/09/2023
Objection raised — Scope
05/09/2023
Objection resolved — Addressed
05/09/2023
Objection raised — Scope
05/09/2023
Objection resolved — Addressed
05/09/2023
Objection raised — Structural
05/09/2023
Objection resolved — Addressed
05/09/2023
Objection raised — Scope
05/09/2023
Objection resolved — Addressed
05/09/2023
Objection raised — Scope
05/09/2023
Objection resolved — Addressed
05/09/2023
Objection raised — Other
05/09/2023
Objection resolved — Addressed
05/09/2023
Objection raised — Scope
05/09/2023
Objection resolved — Addressed
05/09/2023
Objection raised — Scope
05/09/2023
Objection resolved — Addressed
05/04/2023
Objection raised — Scope
Latest 60 of 80 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedSHAFAI CONSTRUCTION INC08/11/2026
DOB NOWConstruction FencePermit IssuedSHAFAI CONSTRUCTION INC08/11/2026
DOB NOWSupport of ExcavationPermit IssuedSHAFAI CONSTRUCTION INC03/17/2026
DOB NOWStructuralPermit IssuedSHAFAI CONSTRUCTION INC08/11/2025
DOB NOWConstruction FencePermit IssuedSHAFAI CONSTRUCTION INC08/01/2025
1 job · most recent 10/28/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
10/28/2025Permit IssuedSHAFAI CONSTRUCTION INCHeating and Air Conditioning Systems
Heat / Cool
Fujitsu AOU48RLXFZ1 48,000 BTU · Condensing Unit ×1
1 job · most recent 10/28/2025
Gas Water/Sanitary
FiledStatusContractorScope
10/28/2025——Gas, Water/Sanitary
1 job · most recent 10/28/2025
Wood
FiledStatusContractorScope
10/28/2025Permit IssuedSHAFAI CONSTRUCTION INCWood
1 job · most recent 10/28/2025
Fence
FiledStatusContractorScope
10/28/2025Permit IssuedSHAFAI CONSTRUCTION INCFence
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
07/18/2023Chimneys and ventsBarry Bergspecial
06/26/2023Subgrade InspectionsMohammad Baalbakispecial
04/29/2023Interior lighting powerMohammad Baalbakienergy_progress
04/29/2023Maintenance informationMohammad Baalbakienergy_progress
04/29/2023HVAC-R and service water piping design and insulationMohammad Baalbakienergy_progress
04/29/2023Permanent certificateMohammad Baalbakienergy_progress
04/29/2023Protection of exposed foundation insulationMohammad Baalbakienergy_progress
04/29/2023Insulation placement and R valuesMohammad Baalbakienergy_progress
04/29/2023Air barrier - visual inspectionMohammad Baalbakienergy_progress
04/28/2023Fenestration areasMohammad Baalbakienergy_progress
04/28/2023HVAC-R and service water heating equipmentMohammad Baalbakienergy_progress
04/28/2023Concrete - Cast-In-PlaceBarry Bergspecial
04/28/2023Fenestration and door U-factor and product ratingsMohammad Baalbakienergy_progress
04/28/2023HVAC-R and service water heating system controlsMohammad Baalbakienergy_progress
04/28/2023Fire-Resistant Penetrations and JointsBarry Bergspecial
04/28/2023Structural Stability – Alterations of existing buildingsBarry Bergspecial
04/28/2023Mechanical SystemsBarry Bergspecial
04/28/2023FinalBarry Bergprogress
04/28/2023Footing and FoundationBarry Bergprogress
04/28/2023Fenestration air leakageMohammad Baalbakienergy_progress
▾Documents — 37 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/20/2026B00866946-S3Request digital key ↗
08/20/2026B00866946-I1Request digital key ↗
08/20/2026B00866946-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B00866946-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B00866946-I1Open ↗
▸Seals & Professional Certifications24
▸DOB NOWProgress Inspector Seal & Signature14
08/26/2026B00866946-I1Open ↗
08/26/2026B00866946-I1Open ↗
08/26/2026B00866946-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
08/26/2026B00866946-I1Open ↗
08/26/2026B00866946-I1Open ↗
08/26/2026B00866946-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/13/2026B00866946-I1Open ↗
08/13/2026B00866946-S1Open ↗
08/13/2026B00866946-S2Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026B00866946-S2Open ↗
08/13/2026B00866946-I1Open ↗
▸Inspections & Test Reports1
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026B00866946-S3Open ↗
▸Other Documents4
▸DOB NOWPlot Diagram2
08/13/2026B00866946-S3Open ↗
08/13/2026B00866946-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B00866946-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1