| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/06/2023 | Permit Issued | A.M. SAGE PLG & HTG LLC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2023 | Permit Issued | TRINCITY ELECTRIC, INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/18/2023 | Permit Issued | A I N CONTRACTING CORP | Fence |
| Owner | Filings | Most Recent |
|---|---|---|
| GREENLINE BLDG CONSULTANTS | 11 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/02/2022 | $650K | — | Private party → Private party | $374/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ACV DESIGN LTD | 2 | 11/09/2023 |
| LESLIE M. GOOD ARCHITECTS | 4 | 10/06/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A I N CONTRACTING CORP | General Contractor | 4 | 07/08/2026 |
| A.M. SAGE PLG & HTG LLC | Plumbing | 1 | 07/08/2026 |
| M & M PIPING AND HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ACV DESIGN LTD | 3864 | 2 | 11/09/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | A.M. SAGE PLG & HTG LLC | 09/27/2023 |
| DOB NOW | Plumbing | Permit Issued | M & M PIPING AND HEATING | 07/21/2023 |
| DOB NOW | General Construction | Permit Issued | A I N CONTRACTING CORP | 05/30/2023 |
| DOB NOW | Construction Fence | Permit Issued | A I N CONTRACTING CORP | 05/25/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/15/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/11/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/11/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/28/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/28/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/17/2023 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/02/2023 | Fire-Resistant Penetrations and Joints | ANTHONY VILLANO | special |
| 11/02/2023 | Structural Stability – Alterations of existing buildings | ANTHONY VILLANO | special |
| 11/02/2023 | Subsurface Investigations (Borings/Test Pits) | Soorjbally Harilall | special |
| 11/02/2023 | Energy Code Compliance Inspections | ANTHONY VILLANO | progress |
| 11/02/2023 | Lowest Floor Elevation | ANTHONY VILLANO | progress |
| 11/02/2023 | Air barrier - visual inspection | ANTHONY VILLANO | energy_progress |
| 11/02/2023 | Fenestration and door U-factor and product ratings | ANTHONY VILLANO | energy_progress |
| 11/02/2023 | Fenestration areas | ANTHONY VILLANO | energy_progress |
| 11/02/2023 | Insulation placement and R values | ANTHONY VILLANO | energy_progress |
| 11/02/2023 | Interior lighting power | ANTHONY VILLANO | energy_progress |
| 11/02/2023 | Permanent certificate | ANTHONY VILLANO | energy_progress |
| 11/02/2023 | Fenestration air leakage | ANTHONY VILLANO | energy_progress |