| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/11/2025 | — | — | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/11/2025 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/11/2025 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/03/2026 | Permit Issued | DYNAMIC DEVELOPMENT AND C | Fence |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/05/2025 | $2.2M | — | — → — | $840/sf building |
| 01/11/2016 | $1.5M | — | — → — | $552/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| VERSATILE ENGINEERING, P.C. | 6 | 06/23/2026 |
| YAKER ENGINEERING, P.C. | 1 | 02/20/2026 |
| MENZAK ARCHITECT, P.C. | 1 | 09/30/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| VERSATILE ENGINEERING, P.C. | 2 | 03/21/2026 |
| MENZAK ARCHITECT P C | 6 | 03/21/2026 |
| ALISTAS SERVICES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DYNAMIC DEVELOPMENT AND C | General Contractor | 3 | 08/05/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Full Demolition | Permit Issued | DYNAMIC DEVELOPMENT AND C | 08/04/2026 |
| DOB NOW | Full Demolition | Permit Issued | DYNAMIC DEVELOPMENT AND C | 07/29/2026 |
| DOB NOW | Full Demolition | Permit Issued | DYNAMIC DEVELOPMENT AND C | 07/10/2026 |
| DOB NOW | Construction Fence | Permit Issued | K.W.MCINTOSH CONSTRUCTION | 07/10/2026 |
| BIS | PL | ISSUED | BELL FUEL OIL, LLC | 04/23/2001 |
| BIS | OT | ISSUED | S & L CONSTRUCTION CORP. | 03/14/2001 |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/10/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/31/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/31/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/16/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/04/2026 | Preliminary | — | progress |
| 08/04/2026 | Chimneys and vents | — | special |
| 08/04/2026 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 08/04/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 08/04/2026 | Luminous Exit Path Markings | — | special |
| 08/04/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 08/04/2026 | Subgrade Inspections | — | special |
| 08/04/2026 | Wall Panels, Curtain Walls, and Veneers | — | special |
| 08/04/2026 | Energy Code Compliance Inspections | — | progress |
| 08/04/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/16/2026 | Interior lighting power | — | energy_progress |
| 06/16/2026 | Lighting in dwelling units | — | energy_progress |
| 06/16/2026 | Exterior lighting power | — | energy_progress |
| 06/16/2026 | Metering | — | energy_progress |
| 06/16/2026 | Lighting controls | — | energy_progress |
| 06/16/2026 | Electrical motors and elevators | — | energy_progress |
| 06/16/2026 | Maintenance information | — | energy_progress |
| 10/31/2025 | Sprinkler Systems | — | special |
| 10/17/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 10/17/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 10/17/2025 | Shutoff dampers | — | energy_progress |
| 10/17/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 10/12/2025 | Mechanical Systems | — | special |
| 10/12/2025 | Final | — | progress |
| 09/30/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |