← Back
Miscellaneous two family
2770 EAST 65 STREET
BROOKLYN · BIN 3242751
💬 Discuss this project
1960Year Built
2Stories
B9Building Class
R5Zoning
2,170 sfGross Floor Area
2Units
2 Open Violations 1 unresolved · 1 paperwork only ▸FDNY Report ↗
Miscellaneous two family · Owner of record: EAST 65 HOLDING LLC · 2,683 sf lot · 0.81 FAR built · Flood zone AE
Locations of Work
ArchitecturePlumbingFire Protection
Roof4p · 1 filing · 10 docs
Penthouse5p · 1 filing · 10 docs
Floor 34p · 1 filing · 10 docs
Floor 24p · 1 filing · 10 docs
Floor 12p · 1 filing · 10 docs
Cellar4p · 1 filing · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
I G GROUP803/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LAM & LAM ENGINEERING D.P.C.201/19/2026
BILD ARCHITECTURE110/22/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LAM & LAM DESIGNS DPC403/21/2026
Building Lifecycle
All (99)Filed (3)Violation (5)Objection (65)Special Inspection (26)
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
09/02/2026
Objection resolved — Resolved
08/17/2026
Objection resolved — Addressed
08/17/2026
Objection resolved — Addressed
08/17/2026
Objection resolved — Resolved
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/13/2026
Objection raised — Scope
07/07/2026
Special inspection requirement — Interior lighting power
07/07/2026
Special inspection requirement — Lighting in dwelling units
07/07/2026
Special inspection requirement — Exterior lighting power
07/07/2026
Special inspection requirement — Protection of exposed foundation insulation
07/07/2026
Special inspection requirement — Permanent certificate
07/07/2026
Special inspection requirement — Lighting controls
05/07/2026
Objection resolved — Addressed
05/07/2026
Objection resolved — Addressed
05/07/2026
Objection resolved — Addressed
05/07/2026
Objection resolved — Addressed
05/07/2026
Objection resolved — Addressed
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/31/2026
Objection raised — Scope
03/11/2026
Objection resolved — Addressed
01/29/2026
Objection raised — Scope
01/29/2026
Objection raised — Structural
01/29/2026
Objection raised — Structural
01/29/2026
Objection raised — Inspections
01/29/2026
Objection raised — Structural
01/29/2026
Objection raised — Structural
01/29/2026
Objection raised — Energy
01/29/2026
Objection raised — Mechanical
Latest 60 of 99 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDI & G GROUP, INC03/02/2020
BISPLISSUEDZONE PLUMBING & HEATING C02/18/2020
BISOTISSUEDI & G GROUP, INC02/04/2019
BISOTISSUEDI & G GROUP, INC05/01/2018
BISOTISSUEDI & G GROUP, INC05/05/2017
BISOTISSUEDI & G GROUP, INC07/30/2015
1 project · most recent 01/19/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
01/19/2026——Air Conditioning Systems
Cooling
1 project · most recent 01/19/2026
FiledStatusContractorScope
01/19/2026——126 heads
1 project · most recent 01/19/2026
Storm Water/Sanitary
FiledStatusContractorScope
01/19/2026——Storm, Water/Sanitary
2 projects · most recent 03/17/2020
General Wiring
FiledStatusContractorScope
03/17/2020Permit IssuedMARTINEZ ELECTRICAL CONTGeneral Wiring
06/07/2018Permit IssuedR.A. PHILLIPS ELEC'L CONTGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
07/07/2026Interior lighting power—energy_progress
07/07/2026Lighting in dwelling units—energy_progress
07/07/2026Exterior lighting power—energy_progress
07/07/2026Protection of exposed foundation insulation—energy_progress
07/07/2026Permanent certificate—energy_progress
07/07/2026Lighting controls—energy_progress
01/19/2026Shutoff dampers—energy_progress
12/19/2025Mechanical Systems—special
12/19/2025Final—progress
12/19/2025HVAC-R and service water heating equipment—energy_progress
12/19/2025HVAC-R and service water piping design and insulation—energy_progress
12/19/2025Fire-Resistant Penetrations and Joints—special
12/19/2025Duct leakage testing, insulation and design—energy_progress
12/19/2025HVAC-R and service water heating system controls—energy_progress
12/19/2025Energy Code Compliance Inspections—progress
12/19/2025HVAC-R and service water piping design and insulation—energy_progress
12/19/2025HVAC-R and service water heating equipment—energy_progress
12/19/2025HVAC-R and service water heating system controls—energy_progress
12/19/2025Maintenance information—energy_progress
12/19/2025Fire-Resistant Penetrations and Joints—special
12/17/2025Sprinkler Systems—special
11/07/2025Fenestration and door U-factor and product ratings—energy_progress
11/07/2025Fenestration areas—energy_progress
11/07/2025Insulation placement and R values—energy_progress
11/07/2025Fenestration air leakage—energy_progress
Latest 25 of 26.
▾Documents — 32 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/18/2026B01307174-I1Request digital key ↗
08/15/2026B01307174-S2Request digital key ↗
08/15/2026B01307174-S1Request digital key ↗
▸Applications & Permits7
▸BISWORK PERMIT APPLICATION4
03/05/2020321173350Open ↗
02/05/2019321173350Open ↗
05/09/2017321173350Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION2
06/25/2020321173350Open ↗
07/30/2015321173350Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
05/19/2017321173350Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01307174-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/18/2026B01307174-I1Open ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/18/2026B01307174-S2Open ↗
08/18/2026B01307174-S1Open ↗
08/18/2026B01307174-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
08/05/2015321173350Open ↗
07/30/2015321173350Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
07/30/2015321173350Open ↗
▸BISSCHEDULE B - PLUMBING1
06/25/2020321173350Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
07/30/2015321173350Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/30/2015321173350Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
08/05/2015321173350Open ↗
07/30/2015321173350Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
10/29/2020321173350Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
07/30/2015321173350Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
07/19/2020321173350Open ↗
07/14/2020321173350Open ↗
07/30/2015321173350Open ↗
▸Filing & Intake Forms2
▸BISADDITIONAL INFORMATION1
06/23/2020321173350Open ↗
▸BISEFILING COVER SHEET1
07/30/2015321173350Open ↗
▸Other Documents2
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/18/2026B01307174-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01307174-I1Open ↗