| Firm | Filings | Most Recent |
|---|---|---|
| SERDAR CEYLAN ARCHITECT, PC | 2 | 08/07/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ELITE GC NY INC | General Contractor | 1 | 09/25/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | ELITE GC NY INC | 09/24/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/07/2026 | Permit Issued | ELITE GC NY INC | Air Conditioning Systems | Cooling Cooper & Hunter CH-UC36-230VO 360,000 BTU · Condensing Unit ×1 CH-UC48-230VO 46,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | — | — | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2026 | Mechanical Systems | — | special |
| 08/07/2026 | Energy Code Compliance Inspections | — | progress |
| 08/07/2026 | Final | — | progress |
| 08/07/2026 | Air barrier - visual inspection | — | energy_progress |
| 08/07/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/07/2026 | Fenestration air leakage | — | energy_progress |
| 08/07/2026 | Insulation placement and R values | — | energy_progress |
| 08/07/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/07/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 08/07/2026 | Fenestration areas | — | energy_progress |
| 08/07/2026 | Interior lighting power | — | energy_progress |
| 08/07/2026 | HVAC-R and service water heating system controls | — | energy_progress |