SRO - single room occupancy, affordable housing
506 OCEAN VIEW AVENUE
BROOKLYN · BIN 3244886
💬 Discuss this project
1931Year Built
2Stories
HRBuilding Class
R6Zoning
3,060 sfGross Floor Area
20Units
Rent Stabilized6 Open Violations 3 unresolved · 3 paperwork only ▸FDNY Report ↗
SRO - single room occupancy, affordable housing · 2,400 sf lot · 1.28 FAR built · Flood zone AE
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ENGINEERING PROFESSIONAL SERVICE P.204/06/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ENGINEERING PROFESSIONAL6393204/06/2026
Building Lifecycle
All (26)Filed (2)Violation (15)Objection (5)Special Inspection (4)
05/05/2026
Violation issued (HPD, open)
A
04/06/2026
Filed — Alteration
Partial demolition horizontal extension building only, the main building remains intact. Remove violation no. 39148215L work without a permit. No change in use, egress, bulk, and/or occupancy.
B01382555-I1
04/03/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
OLEG RUDITSER
04/03/2026
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
OLEG RUDITSER
04/03/2026
Special inspection requirement — Final
OLEG RUDITSER
03/16/2026
Violation issued (ECB, open)
Construction
11/20/2025
Violation issued (HPD, closed)
I
07/22/2025
Objection resolved — Addressed
07/22/2025
Objection resolved — Addressed
07/07/2025
Objection raised — Other
07/07/2025
Objection raised — Admin
07/07/2025
Objection raised — Other
06/18/2025
Filed — Alteration
Filing underground storm pipes to connect the existing roof gutters to existing underground storm drainage system in conjunction with primary application #B01382555-I1 and remove violation number 39148216N. No change in use, egress, bulk, and/or occupancy
B01241441-S1
06/13/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
OLEG RUDITSER
06/10/2025
Violation issued (HPD, open)
A
05/16/2025
Violation issued (ECB, open)
Construction
05/16/2025
Violation issued (ECB, open)
Plumbing
12/18/2024
Violation issued (HPD, closed)
C
12/18/2024
Violation issued (HPD, open)
B
04/11/2024
Violation issued (HPD, closed)
A
03/24/2023
Violation issued (HPD, closed)
A
03/01/2022
Violation issued (HPD, closed)
I
03/01/2022
Violation issued (HPD, closed)
A
04/12/2021
Violation issued (HPD, closed)
I
04/12/2021
Violation issued (HPD, closed)
A
10/19/2018
Violation issued (HPD, closed)
I
Nothing on file for this building.
1 project · most recent 06/18/2025
Storm
FiledStatusContractorScope
06/18/2025——Storm
1 project · most recent 06/18/2025
FiledStatusContractorScope
06/18/2025——1 scope_items
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
04/03/2026Structural Stability – Alterations of existing buildingsOLEG RUDITSERspecial
04/03/2026Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)OLEG RUDITSERspecial
04/03/2026FinalOLEG RUDITSERprogress
06/13/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationOLEG RUDITSERspecial
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/21/2026B01241441-I1Request digital key ↗
08/17/2026B01382555-I1Request digital key ↗
08/15/2026B01241441-S1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/21/2026B01241441-I1Open ↗
08/21/2026B01241441-S1Open ↗
08/17/2026B01382555-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026B01241441-S1Open ↗
08/24/2026B01382555-I1Open ↗
08/24/2026B01382555-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/24/2026B01382555-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/17/2026B01382555-I1Open ↗