1967Year Built
2Stories
E1Building Class
M1-1DZoning
10,720 sfGross Floor Area
1Units
General warehouse · Owner of record: JENNIE & RAY INC · 7,725 sf lot · 1.39 FAR built · Flood zone X
Locations of Work
Plumbing
Roof1p · 1 filing · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 11p · 1 filing · 20 docs
Nothing on file for this building.
Building Lifecycle
All (19)Filed (3)Permit Issued (1)Signed Off (1)Inspection (4)Special Inspection (10)
03/14/2022
Signed off — Alteration
INSTALL 7 GAS HEATERS THROUGHT THE SPACE. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED
B00551408-I1
02/02/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/28/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
01/25/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
12/29/2021
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
12/13/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Spencer Goroff
12/13/2021
Special inspection requirement — Post-installed Anchors
Spencer Goroff
12/13/2021
Special inspection requirement — Energy Code Compliance Inspections
Adrian Figueroa
12/13/2021
Special inspection requirement — Maintenance information
Adrian Figueroa
12/13/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Adrian Figueroa
12/09/2021
Filed — Alteration
INSTALL 7 GAS HEATERS THROUGHT THE SPACE. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED
B00551408-P2
10/26/2021
Permit issued — Plumbing
B00551408-I1-PL
09/22/2021
Filed — Alteration
INSTALL 7 GAS HEATERS THROUGHT THE SPACE. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED
B00551408-P1
09/22/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Spencer Goroff
09/22/2021
Special inspection requirement — Post-installed Anchors
Spencer Goroff
09/22/2021
Special inspection requirement — Energy Code Compliance Inspections
Adrian Figueroa
09/22/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Adrian Figueroa
09/22/2021
Special inspection requirement — Maintenance information
Adrian Figueroa
08/04/2021
Filed — Alteration
INSTALL 7 GAS HEATERS THROUGHT THE SPACE. NO CHANGE IN USE, EGRESS OR OCCUPANCY IS REQUIRED
B00551408-I1
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SRA ARCHITECTURE + ENGINEERING, PC312/09/2021
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AMERICAN STANDARD P&H CORORP.Plumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SE INSPECTIONS7486312/09/2021
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offAMERICAN STANDARD P&H CORORP.10/26/2021
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
02/02/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/28/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/25/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
12/29/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
12/13/2021Fire-Resistant Penetrations and JointsSpencer Goroffspecial
12/13/2021Post-installed AnchorsSpencer Goroffspecial
12/13/2021Energy Code Compliance InspectionsAdrian Figueroaprogress
12/13/2021Maintenance informationAdrian Figueroaenergy_progress
12/13/2021HVAC-R and service water piping design and insulationAdrian Figueroaenergy_progress
09/22/2021Fire-Resistant Penetrations and JointsSpencer Goroffspecial
09/22/2021Post-installed AnchorsSpencer Goroffspecial
09/22/2021Energy Code Compliance InspectionsAdrian Figueroaprogress
09/22/2021HVAC-R and service water piping design and insulationAdrian Figueroaenergy_progress
09/22/2021Maintenance informationAdrian Figueroaenergy_progress
▾Documents — 20 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
09/01/2026B00551408-I1Request digital key ↗
09/01/2026B00551408-P2Request digital key ↗
09/01/2026B00551408-P1Request digital key ↗
▸Seals & Professional Certifications13
▸DOB NOWProgress Inspector Seal & Signature6
08/28/2026B00551408-I1Open ↗
08/28/2026B00551408-I1Open ↗
08/28/2026B00551408-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026B00551408-I1Open ↗
08/28/2026B00551408-I1Open ↗
08/25/2026B00551408-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
09/01/2026B00551408-P2Open ↗
09/01/2026B00551408-P1Open ↗
09/01/2026B00551408-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
09/01/2026B00551408-P2Open ↗
09/01/2026B00551408-P1Open ↗
09/01/2026B00551408-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1