General warehouse · Owner of record: GROUP 58 REALTY LLC · 3,005 sf lot · 1.75 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
JUNO CONTRACTING2403/22/2026
GROUP 58 REALTY203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SW ENGINEERING COMPANY604/10/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MUNICIPAL BUILDING CONSULTANTS603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JUNO CONTRACTING CORPGeneral Contractor803/21/2026
A.G.M. P & H INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SWL ENGINEERING INSPECTIO6912504/10/2024
SW ENGINEERING COMPANY, P1832110/17/2023
Building Lifecycle
All (115)Filed (6)Permit Issued (5)Signed Off (4)Violation (2)Inspection (6)Objection (62)Special Inspection (30)
05/23/2024
Signed off — Alteration
HORIZONTAL ENLARGEMENT ON 1ST AND 2ND FLOOR OF EXISTING STORAGE WAREHOUSE AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00834328-S1
05/22/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
05/15/2024
Signed off — Alteration
NEW PLUMBING FIXTURES FOR TWO NEW POWDER ROOMS AT 2ND FLOOR EXTENSION AND ROOF DRAIN AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00929174-I1
05/15/2024
Signed off — Alteration
PROVIDE VENTILATION FOR NEW BATHROOM AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00947850-I1
05/13/2024
Signed off — Alteration
HORIZONTAL ENLARGEMENT ON 1ST AND 2ND FLOOR OF EXISTING STORAGE WAREHOUSE AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00834328-I1
04/17/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSHUA LUCKRITZ
04/17/2024
Special inspection requirement — Final
Yakov Weinstein
04/17/2024
Special inspection requirement — Construction Operations Influencing Adjacent Structures
JOSHUA LUCKRITZ
04/17/2024
Special inspection requirement — Structural Steel - Details
JOSHUA LUCKRITZ
04/17/2024
Special inspection requirement — Concrete - Cast-In-Place
JOSHUA LUCKRITZ
04/17/2024
Special inspection requirement — Structural Steel - Welding
JOSHUA LUCKRITZ
04/17/2024
Special inspection requirement — Masonry
JOSHUA LUCKRITZ
04/10/2024
Filed — Alteration
HORIZONTAL ENLARGEMENT ON 1ST AND 2ND FLOOR OF EXISTING STORAGE WAREHOUSE AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00834328-P2
04/05/2024
Special inspection requirement — Fenestration air leakage
Yakov Weinstein
04/05/2024
Special inspection requirement — Air barrier - visual inspection
Yakov Weinstein
04/05/2024
Special inspection requirement — Fenestration areas
Yakov Weinstein
04/05/2024
Special inspection requirement — Insulation placement and R values
Yakov Weinstein
04/05/2024
Special inspection requirement — Fire-Resistance Rated Construction
Yakov Weinstein
04/05/2024
Special inspection requirement — Energy Code Compliance Inspections
Yakov Weinstein
04/05/2024
Special inspection requirement — Masonry
JOSHUA LUCKRITZ
04/05/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSHUA LUCKRITZ
04/05/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSHUA LUCKRITZ
04/02/2024
Objection resolved — Addressed
04/01/2024
Special inspection requirement — Concrete - Cast-In-Place
JOSHUA LUCKRITZ
04/01/2024
Special inspection requirement — Construction Operations Influencing Adjacent Structures
JOSHUA LUCKRITZ
04/01/2024
Special inspection requirement — Masonry
JOSHUA LUCKRITZ
04/01/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSHUA LUCKRITZ
04/01/2024
Special inspection requirement — Structural Steel - Details
JOSHUA LUCKRITZ
04/01/2024
Special inspection requirement — Structural Steel - Welding
JOSHUA LUCKRITZ
04/01/2024
Special inspection requirement — Final
Yakov Weinstein
03/26/2024
Objection raised — Scope
03/22/2024
Filed — Alteration
HORIZONTAL ENLARGEMENT ON 1ST AND 2ND FLOOR OF EXISTING STORAGE WAREHOUSE AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00834328-P1
03/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOSHUA LUCKRITZ
03/21/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOSHUA LUCKRITZ
03/21/2024
Special inspection requirement — Energy Code Compliance Inspections
Yakov Weinstein
03/21/2024
Special inspection requirement — Fire-Resistance Rated Construction
Yakov Weinstein
03/21/2024
Special inspection requirement — Fenestration air leakage
Yakov Weinstein
03/21/2024
Special inspection requirement — Fenestration areas
Yakov Weinstein
03/21/2024
Special inspection requirement — Insulation placement and R values
Yakov Weinstein
03/19/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/19/2024
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
03/19/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/14/2024
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
11/15/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/08/2023
Permit issued — Plumbing
B00929174-I1-PL
10/25/2023
Permit issued — Mechanical Systems
B00947850-I1-MS
10/18/2023
Objection resolved — Addressed
10/17/2023
Filed — Alteration
PROVIDE VENTILATION FOR NEW BATHROOM AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00947850-I1
10/16/2023
Objection resolved — Addressed
10/10/2023
Objection resolved — Addressed
10/10/2023
Objection resolved — Addressed
10/02/2023
Objection raised — Mechanical
10/02/2023
Objection raised — Fire_Protection
10/02/2023
Objection raised — Scope
10/02/2023
Objection raised — Structural
09/26/2023
Filed — Alteration
NEW PLUMBING FIXTURES FOR TWO NEW POWDER ROOMS AT 2ND FLOOR EXTENSION AND ROOF DRAIN AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B00929174-I1
09/05/2023
Violation issued (ECB, closed)
Construction
09/01/2023
Permit issued — General Construction
B00834328-S1-GC
07/26/2023
Permit issued — General Construction
B00834328-S1-GC
07/18/2023
Permit issued — Structural
B00834328-I1-ST
Latest 60 of 115 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offA.G.M. P & H INC11/08/2023
DOB NOWMechanical SystemsSigned-offJUNO CONTRACTING10/25/2023
DOB NOWGeneral ConstructionSigned-offJUNO CONTRACTING09/01/2023
DOB NOWGeneral ConstructionSigned-offJUNO CONTRACTING07/26/2023
DOB NOWStructuralSigned-offJUNO CONTRACTING07/18/2023
BISMHISSUEDJUNO CONTRACTING CORP03/29/2012
BISPLISSUEDACE CONTRACTING INC03/23/2005
BIS—ISSUEDAXIUM CONSTRUCTION CORP03/14/2005
1 project · most recent 08/29/2023
General Wiring
FiledStatusContractorScope
08/29/2023Permit IssuedTESTA ELECTRIC CO., INCGeneral Wiring
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
05/22/2024Pass-Final General Construction Non-Directive 14PassView ↗
03/19/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/19/2024Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
03/19/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/14/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
11/15/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
04/17/2024Structural Stability – Alterations of existing buildingsJOSHUA LUCKRITZspecial
04/17/2024FinalYakov Weinsteinprogress
04/17/2024Construction Operations Influencing Adjacent StructuresJOSHUA LUCKRITZspecial
04/17/2024Structural Steel - DetailsJOSHUA LUCKRITZspecial
04/17/2024Concrete - Cast-In-PlaceJOSHUA LUCKRITZspecial
04/17/2024Structural Steel - WeldingJOSHUA LUCKRITZspecial
04/17/2024MasonryJOSHUA LUCKRITZspecial
04/05/2024Fenestration air leakageYakov Weinsteinenergy_progress
04/05/2024Air barrier - visual inspectionYakov Weinsteinenergy_progress
04/05/2024Fenestration areasYakov Weinsteinenergy_progress
04/05/2024Insulation placement and R valuesYakov Weinsteinenergy_progress
04/05/2024Fire-Resistance Rated ConstructionYakov Weinsteinprogress
04/05/2024Energy Code Compliance InspectionsYakov Weinsteinprogress
04/05/2024MasonryJOSHUA LUCKRITZspecial
04/05/2024Fire-Resistant Penetrations and JointsJOSHUA LUCKRITZspecial
04/05/2024Structural Stability – Alterations of existing buildingsJOSHUA LUCKRITZspecial
04/01/2024Concrete - Cast-In-PlaceJOSHUA LUCKRITZspecial
04/01/2024Construction Operations Influencing Adjacent StructuresJOSHUA LUCKRITZspecial
04/01/2024MasonryJOSHUA LUCKRITZspecial
04/01/2024Structural Stability – Alterations of existing buildingsJOSHUA LUCKRITZspecial
04/01/2024Structural Steel - DetailsJOSHUA LUCKRITZspecial
04/01/2024Structural Steel - WeldingJOSHUA LUCKRITZspecial
04/01/2024FinalYakov Weinsteinprogress
03/21/2024Fire-Resistant Penetrations and JointsJOSHUA LUCKRITZspecial
03/21/2024Structural Stability – Alterations of existing buildingsJOSHUA LUCKRITZspecial
Latest 25 of 40.
▾Documents — 61 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/27/2026B00834328-P2Request digital key ↗
08/27/2026B00834328-P1Request digital key ↗
08/26/2026B00947850-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits2
▸BISWORK PERMIT APPLICATION1
04/03/2012320362344Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
02/01/2012320362344Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026B00834328-S1Open ↗
08/13/2026B00834328-P1Open ↗
▸Seals & Professional Certifications32
▸DOB NOWProgress Inspector Seal & Signature14
09/20/2026B00834328-S1Open ↗
09/20/2026B00834328-S1Open ↗
09/20/2026B00834328-S1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/20/2026B00834328-S1Open ↗
08/29/2026B00929174-I1Open ↗
08/29/2026B00834328-P2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/27/2026B00834328-P2Open ↗
08/27/2026B00834328-I1Open ↗
08/27/2026B00834328-P1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION4
05/07/2012320362344Open ↗
04/03/2012320362344Open ↗
03/29/2012320362344Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment3
▸BISEQUIPMENT USE APPLICATION/PERMIT2
02/01/2012320362344Open ↗
05/07/2012320362344Open ↗
▸BISEQUIPMENT USE PERMITS1
05/07/2012320362344Open ↗
▸Environmental & Asbestos1
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
02/01/2012320362344Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY3
05/07/2012320362344Open ↗
03/27/2012320362344Open ↗
02/01/2012320362344Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
05/07/2012320362344Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/07/2012320362344Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
02/01/2012320362344Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
05/07/2012320362344Open ↗
02/01/2012320362344Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
02/01/2012320362344Open ↗
▸Other Documents6
▸DOB NOWSite Survey: Initial2
08/13/2026B00834328-S1Open ↗
08/13/2026B00834328-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B00834328-S1Open ↗
08/13/2026B00834328-P1Open ↗
▸DOB NOWPlot Diagram2
08/13/2026B00834328-P1Open ↗
08/13/2026B00834328-S1Open ↗