| Owner | Filings | Most Recent |
|---|---|---|
| L&L CONSTRUCTION DEVELOP | 6 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TOM PETERSEN ARCHITECT, LLC | 1 | 12/16/2025 |
| CARUSONE & CHERRES ARCHITECTS, LLC | 3 | 04/17/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| AB WORKS PROCESSING | 3 | 03/21/2026 |
| KAMTECH RESTORATION CORP | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SIGNORE & SONS PLBG CORP | Plumbing | 2 | 07/08/2026 |
| JOHN EVAN CONTRACTING COR | General Contractor | 1 | 04/09/2026 |
| KAMTECH RESTORATION CORP | General Contractor | 1 | 04/09/2026 |
| L&L CONSTRUCTION DEVELOP | General Contractor | 1 | 04/09/2026 |
| OASIS PLOMO CORP | General Contractor | 1 | 04/09/2026 |
| VILLAGE P & H NY INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| THOMAS PETERSEN ARCHITECT | 7854 | 1 | 12/16/2025 |
| ECOPLUSDESIGN | 2887 | 2 | 04/17/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | VILLAGE P & H NY INC | 05/06/2026 |
| DOB NOW | Solar | Signed-off | KAMTECH RESTORATION CORP | 12/30/2025 |
| DOB NOW | Construction Fence | Permit Issued | JOHN EVAN CONTRACTING COR | 12/24/2025 |
| DOB NOW | Plumbing | Permit Issued | SIGNORE & SONS PLBG CORP | 07/07/2025 |
| DOB NOW | Plumbing | Permit Issued | SIGNORE & SONS PLBG CORP | 02/05/2025 |
| DOB NOW | General Construction | Permit Issued | L&L CONSTRUCTION DEVELOP | 11/08/2024 |
| DOB NOW | Construction Fence | Permit Issued | OASIS PLOMO CORP | 08/21/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2023 | Permit Issued | PARAMOUNT SERVICES, LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/17/2026 | Permit Issued | POWER SURGE ELECTRIC, INC | General Wiring |
| 12/16/2025 | Complete | BERGER QUALITY ELEC'L CON | — |
| 12/02/2024 | Permit Issued | WCK ELECTRIC CORP. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/16/2025 | Signed-off | KAMTECH RESTORATION CORP | 24 panels, 10.56 kw, 470.94 roof_area_sqft |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2023 | Permit Issued | JOHN EVAN CONTRACTING COR | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/16/2025 | Air barrier - visual inspection | TOM PETERSEN | energy_progress |
| 12/16/2025 | Fire-Resistant Penetrations and Joints | TOM PETERSEN | special |
| 12/16/2025 | Structural Stability – Alterations of existing buildings | TOM PETERSEN | special |
| 12/16/2025 | Energy Code Compliance Inspections | TOM PETERSEN | progress |
| 12/16/2025 | Final | TOM PETERSEN | progress |
| 04/04/2023 | Energy Code Compliance Inspections | Seungchul Ok | progress |
| 04/04/2023 | Fire-Resistance Rated Construction | Seungchul Ok | progress |
| 04/04/2023 | Fenestration air leakage | Seungchul Ok | energy_progress |
| 04/04/2023 | Fenestration areas | Seungchul Ok | energy_progress |
| 04/04/2023 | Insulation placement and R values | Seungchul Ok | energy_progress |
| 04/04/2023 | Fenestration and door U-factor and product ratings | Seungchul Ok | energy_progress |
| 04/04/2023 | Air barrier - visual inspection | Seungchul Ok | energy_progress |
| 04/04/2023 | Interior lighting power | Seungchul Ok | energy_progress |
| 04/04/2023 | Maintenance information | Seungchul Ok | energy_progress |
| 04/04/2023 | Electric vehicle service equipment requirements | Seungchul Ok | energy_progress |
| 04/04/2023 | Metering | Seungchul Ok | energy_progress |
| 04/04/2023 | Permanent certificate | Seungchul Ok | energy_progress |
| 04/04/2023 | HVAC-R and service water heating system controls | Seungchul Ok | energy_progress |
| 04/04/2023 | Concrete - Cast-In-Place | Seungchul Ok | special |
| 04/04/2023 | Exterior Insulation and Finish Systems (EIFS) | Seungchul Ok | special |
| 04/04/2023 | Fire-Resistant Penetrations and Joints | Seungchul Ok | special |
| 04/04/2023 | Subgrade Inspections | Seungchul Ok | special |
| 04/04/2023 | HVAC-R and service water piping design and insulation | Seungchul Ok | energy_progress |
| 04/04/2023 | Permanent certificate | Seungchul Ok | energy_progress |
| 04/04/2023 | Metering | Seungchul Ok | energy_progress |