Factory, industrial, miscellaneous
292 STAGG STREET
BROOKLYN · BIN 3325782
💬 Discuss this project
1950Year Built
1Stories
F9Building Class
M1-1Zoning
16,500 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Factory, industrial, miscellaneous · Owner of record: SMALL MEDIUM LARGE BATCH LLC · 15,000 sf lot · 1.1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction11p · 1 filing · 20 docs
Floor 1Under Construction16p · 1 filing · 20 docs
MezzanineUnder Construction15p · 1 filing · 20 docs
CellarUnder Construction15p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SMALL MEDIUM LARGE BATCH LLC1004/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/20/2023$7.3M—SCHOLES STREET ASSOCIATES → SMALL MEDIUM LARGE BATCH LLC$442/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
DERIVE ENGINEERS212/19/2025
CAREY NGAI CONSULTING ENGINEER108/26/2025
AYON STUDIO ARCHITECTURE AND PRESER106/06/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AC BUILDING CONSULTANTS803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
OVERALL MURALS INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MTD GROUP INSPECTIONS,INC9388312/19/2025
Building Lifecycle
All (60)Filed (4)Permit Issued (1)Violation (1)Objection (24)Special Inspection (30)
06/22/2026
Objection resolved — Addressed
06/22/2026
Objection resolved — Addressed
02/25/2026
Permit issued — Structural
B01202945-S3-ST
02/02/2026
Special inspection requirement — Energy Code Compliance Inspections
Tommaso Di Gesaro
01/14/2026
Objection resolved — Resolved
01/14/2026
Special inspection requirement — Maintenance information
01/14/2026
Special inspection requirement — Interior lighting power
01/14/2026
Special inspection requirement — Lighting controls
01/14/2026
Special inspection requirement — Preliminary
01/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
01/05/2026
Objection raised — Other
01/05/2026
Objection raised — Other
12/19/2025
Filed — Alteration CO
Establishment of new commercial space.
B01202945-S1
12/19/2025
Filed — Alteration CO
Establishment of new commercial space.
B01202945-S2
09/29/2025
Objection resolved — Addressed
09/12/2025
Objection resolved — Addressed
09/12/2025
Objection resolved — Addressed
09/12/2025
Objection resolved — Addressed
09/12/2025
Objection resolved — Addressed
09/08/2025
Objection raised — Admin
09/08/2025
Objection raised — Structural
09/08/2025
Objection raised — Structural
09/08/2025
Objection raised — Structural
09/08/2025
Objection raised — Inspections
08/27/2025
Special inspection requirement — Maintenance information
Tommaso Di Gesaro
08/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Tommaso Di Gesaro
08/27/2025
Special inspection requirement — Heating Systems
Tommaso Di Gesaro
08/27/2025
Special inspection requirement — Shutoff dampers
Tommaso Di Gesaro
08/27/2025
Special inspection requirement — Duct leakage testing, insulation and design
Tommaso Di Gesaro
08/26/2025
Filed — Alteration CO
Establishment of new commercial space.
B01202945-S3
08/15/2025
Objection resolved — Addressed
08/15/2025
Objection resolved — Resolved
08/15/2025
Special inspection requirement — Insulation placement and R values
08/15/2025
Special inspection requirement — Fenestration air leakage
08/15/2025
Special inspection requirement — Fenestration areas
08/15/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
08/15/2025
Special inspection requirement — Air barrier - visual inspection
08/13/2025
Special inspection requirement — HVAC-R and service water heating system controls
Tommaso Di Gesaro
08/13/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Tommaso Di Gesaro
08/13/2025
Special inspection requirement — HVAC-R and service water heating equipment
Tommaso Di Gesaro
08/12/2025
Special inspection requirement — Masonry
Tommaso Di Gesaro
08/12/2025
Special inspection requirement — Structural Wood Frame
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Final
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Structural Steel - High Strength Bolting
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Demolition
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Structural Steel - Details
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Structural Cold-Formed Steel
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Structural Steel - Welding
Tommaso Di Gesaro
08/11/2025
Special inspection requirement — Subgrade Inspections
Tommaso Di Gesaro
06/17/2025
Objection raised — Other
06/17/2025
Objection raised — Other
06/17/2025
Objection raised — Other
06/17/2025
Objection raised — Other
06/17/2025
Objection raised — Other
06/17/2025
Objection raised — Other
06/17/2025
Objection raised — Other
06/06/2025
Filed — Alteration CO
Establishment of new commercial space.
B01202945-I1
08/31/2021
Violation issued (FDNY_ORDER, closed)
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedOVERALL MURALS INC02/25/2026
1 project · most recent 12/19/2025
Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
12/19/2025Permit IssuedOVERALL MURALS INCVentilation Systems
Ventilation
Mitsubishi Electric PKFY-P12NHMU-E2 120 BTU · Vrf Indoor ×5
PKFY-P18NHMU-E2 180 BTU · Vrf Indoor ×3
PKFY-P24-NKMU-E2 240 BTU · Vrf Indoor ×3
PAC-LV48AC-1 480 BTU ×2
MSZ-GL18NA-U1 180 BTU · Split System ×1
PEFY-P48NMAU-E3 480 BTU · Vrf Indoor ×1
PKFY-P06NBMU-E2 60 BTU · Vrf Indoor ×1
PKFY-P08NHMU-E2 80 BTU · Vrf Indoor ×1
1 project · most recent 12/19/2025
Gas Plumbing-Sprinkler Water/Sanitary
FiledStatusContractorScope
12/19/2025——Gas, Plumbing-Sprinkler, Water/Sanitary
1 project · most recent 12/19/2025
Steel Masonry
FiledStatusContractorScope
12/19/2025Permit IssuedOVERALL MURALS INCSteel, Masonry
▾Special Inspection Requirements (DOB NOW) — 37
DateRequirementInspectorRole
02/02/2026Energy Code Compliance InspectionsTommaso Di Gesaroprogress
01/14/2026Maintenance information—energy_progress
01/14/2026Interior lighting power—energy_progress
01/14/2026Lighting controls—energy_progress
01/14/2026Preliminary—progress
01/14/2026Fire-Resistant Penetrations and Joints—special
08/27/2025Maintenance informationTommaso Di Gesaroenergy_progress
08/27/2025Fire-Resistant Penetrations and JointsTommaso Di Gesarospecial
08/27/2025Heating SystemsTommaso Di Gesarospecial
08/27/2025Shutoff dampersTommaso Di Gesaroenergy_progress
08/27/2025Duct leakage testing, insulation and designTommaso Di Gesaroenergy_progress
08/15/2025Insulation placement and R values—energy_progress
08/15/2025Fenestration air leakage—energy_progress
08/15/2025Fenestration areas—energy_progress
08/15/2025Fenestration and door U-factor and product ratings—energy_progress
08/15/2025Air barrier - visual inspection—energy_progress
08/13/2025HVAC-R and service water heating system controlsTommaso Di Gesaroenergy_progress
08/13/2025HVAC-R and service water piping design and insulationTommaso Di Gesaroenergy_progress
08/13/2025HVAC-R and service water heating equipmentTommaso Di Gesaroenergy_progress
08/12/2025MasonryTommaso Di Gesarospecial
08/12/2025Structural Wood FrameTommaso Di Gesaroprogress
08/11/2025FinalTommaso Di Gesaroprogress
08/11/2025Structural Steel - High Strength BoltingTommaso Di Gesarospecial
08/11/2025DemolitionTommaso Di Gesarospecial
08/11/2025Construction Operations Influencing Adjacent StructuresTommaso Di Gesarospecial
Latest 25 of 37.
▾Documents — 37 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/19/2026B01202945-P1Request digital key ↗
08/15/2026B01202945-S3Request digital key ↗
08/15/2026B01202945-S1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications28
▸DOB NOWSpecial Inspector Seal & Signature13
09/01/2026B01202945-S3Open ↗
09/01/2026B01202945-S3Open ↗
09/01/2026B01202945-S3Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
09/01/2026B01202945-S3Open ↗
09/01/2026B01202945-S3Open ↗
08/22/2026B01202945-S2Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/19/2026B01202945-P1Open ↗
08/19/2026B01202945-S3Open ↗
08/19/2026B01202945-S1Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/15/2026B01202945-S1Open ↗
08/14/2026B01202945-I1Open ↗
08/14/2026B01202945-S2Open ↗
▸Other Documents1
▸DOB NOWProperty Ownership Certification1
08/14/2026B01202945-I1Open ↗