← Back
Single or multiple dwelling with stores or offices
200 FLUSHING AVENUE
BROOKLYN · BIN 3334429
💬 Discuss this project
1930Year Built
3Stories
S9Building Class
M1-2Zoning
5,760 sfGross Floor Area
6Units
0 Open ViolationsFDNY Report ↗
Single or multiple dwelling with stores or offices · Owner of record: FLUSHING BROOKLYN, INC. · 6,141 sf lot · 0.94 FAR built · Flood zone X
Locations of Work
MechanicalPlumbing
Floor 11p · 1 filing · 16 docs
Cellar2p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OLD MASTER CONTRACTING507/08/2026
RELIABLE ENTERPRISES407/08/2026
BAYRIDGE FUNDING INC1303/22/2026
WASHINGTON GROUP103/22/2026
NEW MARK REALTY203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MJE PROFESSIONAL SERVICES103/05/2024
BANGASH ASSOCIATES INC.111/15/2023
SOHAIL HUMAYUN P E INC403/09/2021
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GLOBAL LUXURY SRVCS INCGeneral Contractor203/21/2026
OLD MASTER CONTRACTING COGeneral Contractor207/08/2026
RELIABLE ENTERPRISES INCGeneral Contractor107/08/2026
STARLITE PLBG & HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BANGASH ASSOCIATES INC8488111/15/2023
ASHRAF CORPORATION1973203/09/2021
Building Lifecycle
All (49)Filed (6)Permit Issued (5)Signed Off (3)Violation (10)Special Inspection (25)
03/04/2026
Violation issued (FDNY_ORDER, closed)
03/04/2026
Violation issued (FDNY_ORDER, closed)
02/12/2026
Violation issued (FDNY_ORDER, closed)
12/06/2024
Signed off — Alteration
FACADE REPAIR, GRINDING AND POINTING AND STONE REPAIR AS PER PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B00919119-I1
03/21/2024
Permit issued — General Construction
B00919119-I1-GC
03/11/2024
Permit issued — Sidewalk Shed
B01014521-I1-SH
03/05/2024
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01014521-I1
11/22/2023
Permit issued — General Construction
B00919119-I1-GC
11/15/2023
Filed — Alteration
FACADE REPAIR, GRINDING AND POINTING AND STONE REPAIR AS PER PLAN. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
B00919119-I1
11/15/2023
Special inspection requirement — Tenant Protection Plan Compliance
FAZAL BANGASH
08/14/2023
Special inspection requirement — Final
FAZAL BANGASH
08/14/2023
Special inspection requirement — Masonry
FAZAL BANGASH
11/05/2021
Signed off — Alteration
FILING FOR KITCHEN EXHAUST SYSTEM IN COMMERCIAL STORE.
B00425341-I1
06/14/2021
Signed off — Alteration
APPLICATION FILED TO INSTALL NEW PLUMBING FIXTURES AND PIPING INCONJUNCTION WITH ALT 2 JOB #340789757. NO CHANGE TO USE, EGRESS, OROCCUPANCY.
B00425343-I1
03/09/2021
Filed — Alteration
FILING FOR KITCHEN EXHAUST SYSTEM IN COMMERCIAL STORE.
B00425341-P1
03/09/2021
Filed — Alteration
APPLICATION FILED TO INSTALL NEW PLUMBING FIXTURES AND PIPING INCONJUNCTION WITH ALT 2 JOB #340789757. NO CHANGE TO USE, EGRESS, OROCCUPANCY.
B00425343-P1
03/09/2021
Special inspection requirement — HVAC and service water heating system controls
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — Energy Code Compliance Inspections
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — HVAC and service water heating equipment
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — HVAC insulation and sealing
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — Mechanical Systems
AKM HOQUE
03/09/2021
Special inspection requirement — Final
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — Energy Code Compliance Inspections
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — HVAC and service water heating system controls
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — Maintenance information
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — HVAC insulation and sealing
SOHAIL HUMAYUN
03/09/2021
Special inspection requirement — HVAC and service water heating equipment
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — Final
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — HVAC and service water heating equipment
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — Maintenance information
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — HVAC insulation and sealing
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — Energy Code Compliance Inspections
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — HVAC and service water heating system controls
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — HVAC insulation and sealing
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — HVAC and service water heating equipment
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — Energy Code Compliance Inspections
SOHAIL HUMAYUN
03/08/2021
Special inspection requirement — Mechanical Systems
AKM HOQUE
03/08/2021
Special inspection requirement — HVAC and service water heating system controls
SOHAIL HUMAYUN
01/07/2021
Permit issued — Mechanical Systems
B00425341-I1-MS
01/07/2021
Permit issued — Plumbing
B00425343-I1-PL
12/21/2020
Filed — Alteration
FILING FOR KITCHEN EXHAUST SYSTEM IN COMMERCIAL STORE.
B00425341-I1
12/18/2020
Filed — Alteration
APPLICATION FILED TO INSTALL NEW PLUMBING FIXTURES AND PIPING INCONJUNCTION WITH ALT 2 JOB #340789757. NO CHANGE TO USE, EGRESS, OROCCUPANCY.
B00425343-I1
04/19/2005
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/01/2001
Violation issued (ECB, closed)
Elevators
07/02/1998
Violation issued (ECB, closed)
Elevators
06/26/1998
Violation issued (ECB, closed)
Elevators
06/26/1998
Violation issued (ECB, closed)
Elevators
06/26/1998
Violation issued (ECB, closed)
Elevators
04/21/1997
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offOLD MASTER CONTRACTING CO03/21/2024
DOB NOWSidewalk ShedPermit IssuedRELIABLE ENTERPRISES INC03/11/2024
DOB NOWGeneral ConstructionSigned-offOLD MASTER CONTRACTING CO11/22/2023
DOB NOWMechanical SystemsSigned-offGLOBAL LUXURY SRVCS01/07/2021
DOB NOWPlumbingSigned-offSTARLITE PLBG & HTG CORP01/07/2021
BISOTISSUEDGLOBAL LUXURY SRVCS INC01/08/2021
1 project · most recent 03/05/2024
FiledStatusContractorScope
03/05/2024Permit IssuedRICHARD NEU—
1 project · most recent 03/05/2024
Sidewalk Shed
FiledStatusContractorScope
03/05/2024Permit IssuedRELIABLE ENTERPRISES INCSidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
11/15/2023Tenant Protection Plan ComplianceFAZAL BANGASHspecial
08/14/2023FinalFAZAL BANGASHprogress
08/14/2023MasonryFAZAL BANGASHspecial
03/09/2021HVAC and service water heating system controls SOHAIL HUMAYUNenergy_progress
03/09/2021Energy Code Compliance InspectionsSOHAIL HUMAYUNprogress
03/09/2021HVAC and service water heating equipment SOHAIL HUMAYUNenergy_progress
03/09/2021HVAC insulation and sealing SOHAIL HUMAYUNenergy_progress
03/09/2021Mechanical SystemsAKM HOQUEspecial
03/09/2021FinalSOHAIL HUMAYUNprogress
03/09/2021Energy Code Compliance InspectionsSOHAIL HUMAYUNprogress
03/09/2021HVAC and service water heating system controls SOHAIL HUMAYUNenergy_progress
03/09/2021Maintenance informationSOHAIL HUMAYUNenergy_progress
03/09/2021HVAC insulation and sealing SOHAIL HUMAYUNenergy_progress
03/09/2021HVAC and service water heating equipment SOHAIL HUMAYUNenergy_progress
03/08/2021FinalSOHAIL HUMAYUNprogress
03/08/2021HVAC and service water heating equipment SOHAIL HUMAYUNenergy_progress
03/08/2021Maintenance informationSOHAIL HUMAYUNenergy_progress
03/08/2021HVAC insulation and sealing SOHAIL HUMAYUNenergy_progress
03/08/2021Energy Code Compliance InspectionsSOHAIL HUMAYUNprogress
03/08/2021HVAC and service water heating system controls SOHAIL HUMAYUNenergy_progress
03/08/2021HVAC insulation and sealing SOHAIL HUMAYUNenergy_progress
03/08/2021HVAC and service water heating equipment SOHAIL HUMAYUNenergy_progress
03/08/2021Energy Code Compliance InspectionsSOHAIL HUMAYUNprogress
03/08/2021Mechanical SystemsAKM HOQUEspecial
03/08/2021HVAC and service water heating system controls SOHAIL HUMAYUNenergy_progress
▾Documents — 75 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch - Plumbing2
09/02/2026B00425343-P1Request digital key ↗
09/02/2026B00425343-I1Request digital key ↗
▸DOB NOWPlans/Sketch2
08/26/2026B00919119-I1Request digital key ↗
08/25/2026B01014521-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/02/2026B00425341-P1Request digital key ↗
09/02/2026B00425341-I1Request digital key ↗
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION4
03/03/2021340789757Open ↗
12/14/2020340789757Open ↗
12/14/2020340789757Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION1
01/08/2021340789757Open ↗
▸Seals & Professional Certifications32
▸DOB NOWProgress Inspector Seal & Signature21
09/01/2026B00425343-I1Open ↗
09/01/2026B00425343-I1Open ↗
09/01/2026B00425343-I1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
09/02/2026B00425343-P1Open ↗
09/02/2026B00425343-I1Open ↗
09/02/2026B00425341-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/26/2026B00425341-P1Open ↗
08/25/2026B00425341-I1Open ↗
08/24/2026B00919119-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
11/25/2020340789757Open ↗
▸Trade Schedules & Equipment3
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
11/12/2021340789757Open ↗
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
11/12/2021340789757Open ↗
▸BISPLUMBING (PL) SIGNOFF1
11/12/2021340789757Open ↗
▸Safety & Tenant Protection5
▸DOB NOWTenant Protection Plan4
09/02/2026B00425343-P1Open ↗
09/02/2026B00425343-I1Open ↗
09/02/2026B00425341-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTPP1: TENANT PROTECTION PLAN1
01/07/2021340789757Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
09/02/2026B00425343-P1Open ↗
09/02/2026B00425343-I1Open ↗
09/02/2026B00425341-I1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/25/2020340789757Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
11/12/2021340789757Open ↗
01/07/2021340789757Open ↗
12/14/2020340789757Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/12/2021340789757Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY6
11/12/2021340789757Open ↗
11/12/2021340789757Open ↗
01/07/2021340789757Open ↗
Showing 3 of 6 on file for this type
▸Approvals, Objections & Sign-offs3
▸BISMECHANICAL (MH) SIGNOFF1
11/12/2021340789757Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
11/16/2021340789757Open ↗
▸BISFIRE SUPPRESSION SYSTEM (FP) SIGNOFF1
11/12/2021340789757Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
12/14/2020340789757Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
11/12/2021340789757Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
11/25/2020340789757Open ↗
▸BISADDITIONAL INFORMATION1
04/09/2021340789757Open ↗