← Back
Three families
281 KEAP STREET
BROOKLYN · BIN 3334980
💬 Discuss this project
1920Year Built
3Stories
C0Building Class
R6Zoning
—Gross Floor Area
3Units
1 Open Violation ▸FDNY Report ↗
Three families · Owner of record: B. M. PRINTING, LLC · 1.46 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Roof1p · 1 filing · 5 docs
Floor 41p · 1 filing · 5 docs
Floor 3
Floor 21p · 1 filing · 5 docs
Floor 1
Cellar2p · 1 filing · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
B. M. PRINTING, LLC403/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BAOBAB ARCHITECTS P.C.105/30/2026
Building Lifecycle
All (32)Filed (1)Violation (5)Objection (2)Special Inspection (24)
07/13/2026
Objection resolved — Open
07/10/2026
Objection raised — Other
05/30/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
HORIZONTAL AND VERTICAL ENLARGEMENT TO THE EXISTING 3 STORY + CELLAR BUILDING PROPOSED 5 STORY BUILDING, INTERIOR PARTITIONS, PLUMBING THROUGHOUT
B01404695-I1
05/20/2026
Special inspection requirement — Permanent certificate
05/20/2026
Special inspection requirement — Lighting controls
05/20/2026
Special inspection requirement — Concrete - Cast-In-Place
05/20/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
05/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/20/2026
Special inspection requirement — Masonry
05/20/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
05/20/2026
Special inspection requirement — Seismic Isolation Systems
05/20/2026
Special inspection requirement — Sprayed fire-resistant materials
05/20/2026
Special inspection requirement — Subgrade Inspections
05/20/2026
Special inspection requirement — Energy Code Compliance Inspections
05/20/2026
Special inspection requirement — Fire-Resistance Rated Construction
05/20/2026
Special inspection requirement — Insulation placement and R values
05/20/2026
Special inspection requirement — Lighting in dwelling units
05/20/2026
Special inspection requirement — Fenestration air leakage
05/20/2026
Special inspection requirement — Air barrier — testing
05/20/2026
Special inspection requirement — Air barrier - visual inspection
05/20/2026
Special inspection requirement — Interior lighting power
05/20/2026
Special inspection requirement — Maintenance information
05/20/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
05/20/2026
Special inspection requirement — Exterior lighting power
05/20/2026
Special inspection requirement — Metering
05/20/2026
Special inspection requirement — Fenestration areas
05/20/2026
Special inspection requirement — Protection of exposed foundation insulation
12/28/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/28/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/03/2016
Violation issued (ECB, closed)
Construction
10/03/2016
Violation issued (ECB, closed)
Plumbing
09/24/2008
Violation issued (HPD, open)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISPLISSUEDBT'S PLUMBING AND HEATING02/14/2017
1 project · most recent 05/30/2026
Sprinkler System
FiledStatusContractorScope
05/30/2026——Sprinkler System
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
05/20/2026Permanent certificate—energy_progress
05/20/2026Lighting controls—energy_progress
05/20/2026Concrete - Cast-In-Place—special
05/20/2026Excavations - Sheeting, Shoring, and Bracing—special
05/20/2026Fire-Resistant Penetrations and Joints—special
05/20/2026Masonry—special
05/20/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
05/20/2026Seismic Isolation Systems—special
05/20/2026Sprayed fire-resistant materials—special
05/20/2026Subgrade Inspections—special
05/20/2026Energy Code Compliance Inspections—progress
05/20/2026Fire-Resistance Rated Construction—progress
05/20/2026Insulation placement and R values—energy_progress
05/20/2026Lighting in dwelling units—energy_progress
05/20/2026Fenestration air leakage—energy_progress
05/20/2026Air barrier — testing —energy_progress
05/20/2026Air barrier - visual inspection—energy_progress
05/20/2026Interior lighting power—energy_progress
05/20/2026Maintenance information—energy_progress
05/20/2026Fenestration and door U-factor and product ratings—energy_progress
05/20/2026Exterior lighting power—energy_progress
05/20/2026Metering—energy_progress
05/20/2026Fenestration areas—energy_progress
05/20/2026Protection of exposed foundation insulation—energy_progress
▾Documents — 26 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/15/2026B01404695-I1Request digital key ↗
▸Applications & Permits8
▸BISPLAN / WORK APPROVAL APPLICATION4
04/28/2017321525961Open ↗
04/03/2017321525961Open ↗
03/15/2017321525961Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
03/23/2017321525961Open ↗
03/15/2017321525961Open ↗
03/03/2017321525961Open ↗
▸BISWORK PERMIT APPLICATION1
02/14/2017321525961Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/15/2026B01404695-I1Open ↗
▸Seals & Professional Certifications4
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/14/2017321525961Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
02/14/2017321525961Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
02/14/2017321525961Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/16/2026B01404695-I1Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
04/04/2017321525961Open ↗
03/15/2017321525961Open ↗
02/14/2017321525961Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/14/2017321525961Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/15/2026B01404695-I1Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
02/14/2017321525961Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
02/14/2017321525961Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
04/28/2017321525961Open ↗
03/15/2017321525961Open ↗
▸BISEFILING COVER SHEET1
02/15/2017321525961Open ↗
▸Other Documents2
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
02/14/2017321525961Open ↗
▸DOB NOWSite Survey: Initial1
08/15/2026B01404695-I1Open ↗