| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/15/2022 | — | — | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/26/2022 | — | — | Fence |
| Owner | Filings | Most Recent |
|---|---|---|
| 28 DODWORTH | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ARYEH SIEGEL ARCHITECT | 1 | 05/26/2022 |
| SH ENGINEERING PLLC | 1 | 04/15/2022 |
| MARK WEINBERGER ARCHITECT PLLC | 1 | 04/13/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| AVALON DESIGNS | 6 | 03/21/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/14/2023 | Maintenance information | — | energy_progress |
| 06/08/2022 | Metering | — | energy_progress |
| 05/02/2022 | Structural Steel - Welding | Withdrawn | special |
| 05/02/2022 | Post-installed Anchors | Withdrawn | special |
| 05/02/2022 | Structural Stability – Alterations of existing buildings | Withdrawn | special |
| 05/02/2022 | Structural Steel - Details | Withdrawn | special |
| 05/02/2022 | Structural Steel - High Strength Bolting | Withdrawn | special |
| 04/25/2022 | Subsurface Investigations (Borings/Test Pits) | Soorjbally Harilall | special |
| 04/14/2022 | Subgrade Inspections | Withdrawn | special |
| 04/14/2022 | Excavations - Sheeting, Shoring, and Bracing | Withdrawn | special |
| 04/14/2022 | Concrete - Cast-In-Place | Withdrawn | special |
| 04/14/2022 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 04/14/2022 | Footing and Foundation | Paul Raymond | progress |
| 04/14/2022 | Final | Paul Raymond | progress |
| 04/11/2022 | Insulation placement and R values | — | energy_progress |
| 04/11/2022 | Air barrier - visual inspection | — | energy_progress |
| 04/11/2022 | Protection of exposed foundation insulation | — | energy_progress |
| 04/11/2022 | Interior lighting power | — | energy_progress |
| 04/11/2022 | Air barrier continuity plan testing | — | energy_progress |
| 04/11/2022 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 04/11/2022 | Fire-Resistant Penetrations and Joints | — | special |
| 04/11/2022 | Energy Code Compliance Inspections | — | progress |
| 04/11/2022 | Duct leakage testing, insulation and design | — | energy_progress |
| 04/11/2022 | Electric vehicle service equipment requirements | — | energy_progress |
| 04/11/2022 | Lighting controls | — | energy_progress |