← Back
Primarily 1 family with 1 store or office
958 LIBERTY AVENUE
BROOKLYN · BIN 3389587
💬 Discuss this project
2003Year Built
2Stories
S1Building Class
R6AZoning
2,640 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Primarily 1 family with 1 store or office · 2,146 sf lot · 1.23 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Roof2p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ALEEN CONSTRUCTION INC103/22/2026
ALLEEM CONSTRUCTION INC103/22/2026
ALEEM COSNTRUCTION INC103/22/2026
GLENMORE PITKINSAVE LLC103/22/2026
ORTEGA703/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ALNOUR CONSULTING209/15/2025
ARQUITECTURA VARELA201/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CM3 DESIGN STUDIO403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DRUMSILLA PLUMBING CORPPlumbing707/08/2026
LENDY JONESElectrical303/21/2026
SMART LINE ELECTRIC LLC 005123General Contractor303/22/2026
SMART LINE ELECTRIC, LLCElectrical103/22/2026
DART RESTORATION CORPGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ALNOUR CONSULTING ENGINEE607106/23/2024
Building Lifecycle
All (31)Filed (4)Permit Issued (2)Signed Off (2)Violation (4)Inspection (2)Special Inspection (17)
11/12/2025
Signed off — Alteration
Application to replace and install new plumbing fixtures as shown in plans filed herewith.
B01068950-I1
11/12/2025
Signed off — Alteration
Application to replace and install new plumbing fixtures as shown in plans filed herewith.
B01068950-S1
09/15/2025
Filed — Alteration
Application to replace and install new plumbing fixtures as shown in plans filed herewith.
B01068950-P2
09/15/2025
Special inspection requirement — HVAC-R and service water heating equipment
Vicente Varela
09/15/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Vicente Varela
09/15/2025
Special inspection requirement — HVAC-R and service water heating system controls
Vicente Varela
09/11/2025
Special inspection requirement — HVAC-R and service water heating system controls
Vicente Varela
09/11/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Vicente Varela
09/11/2025
Special inspection requirement — HVAC-R and service water heating equipment
Vicente Varela
02/06/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/17/2025
Filed — Alteration
Application to replace and install new plumbing fixtures as shown in plans filed herewith.
B01068950-P1
01/15/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/14/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Vicente Varela
01/14/2025
Special inspection requirement — HVAC-R and service water heating equipment
Vicente Varela
01/14/2025
Special inspection requirement — HVAC-R and service water heating system controls
Vicente Varela
12/04/2024
Permit issued — Plumbing
B01068950-S1-PL
08/14/2024
Permit issued — General Construction
B01068950-I1-GC
06/27/2024
Filed — Alteration
Application to replace and install new plumbing fixtures as shown in plans filed herewith.
B01068950-S1
06/23/2024
Filed — Alteration
Application to replace and install new plumbing fixtures as shown in plans filed herewith.
B01068950-I1
06/20/2024
Special inspection requirement — Fire-Resistance Rated Construction
Vicente Varela
06/20/2024
Special inspection requirement — Air barrier - visual inspection
Vicente Varela
06/19/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Vicente Varela
06/19/2024
Special inspection requirement — Fenestration areas
Vicente Varela
06/19/2024
Special inspection requirement — Fenestration air leakage
Vicente Varela
06/19/2024
Special inspection requirement — Final
Vicente Varela
06/19/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Nouredine Benabdelhak
06/19/2024
Special inspection requirement — Insulation placement and R values
Vicente Varela
04/21/2005
Violation issued (ECB, closed)
Construction
01/07/2005
Violation issued (ECB, closed)
Construction
11/09/2004
Violation issued (ECB, closed)
Construction
11/09/2004
Violation issued (ECB, closed)
Site Safety
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offDRUMSILLA PLUMBING CORP12/04/2024
DOB NOWGeneral ConstructionSigned-offDART RESTORATION08/14/2024
BIS—ISSUEDA. ALEEM CONSTRUCTION INC.09/07/2005
BISPLISSUEDJUNIOR CARTER MECH. CORP05/20/2005
BIS—ISSUEDA. ALEEM CONSTRUCTION INC.03/30/2005
BIS—ISSUEDA. ALEEM CONSTRUCTION INC.01/25/2005
BIS—ISSUEDA. ALEEM CONSTRUCTION INC.09/01/2004
BIS—ISSUEDA. ALEEM CONSTRUCTION INC.02/18/2004
BISPLISSUEDBLAU MECHANICAL CORP06/27/2003
BIS—ISSUEDA. ALEEM CONSTRUCTION INC.05/05/2003
1 project · most recent 08/29/2025
General Wiring
FiledStatusContractorScope
08/29/2025CompleteSMART LINE ELECTRIC, LLCGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
02/06/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/15/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 17
DateRequirementInspectorRole
09/15/2025HVAC-R and service water heating equipmentVicente Varelaenergy_progress
09/15/2025HVAC-R and service water piping design and insulationVicente Varelaenergy_progress
09/15/2025HVAC-R and service water heating system controlsVicente Varelaenergy_progress
09/11/2025HVAC-R and service water heating system controlsVicente Varelaenergy_progress
09/11/2025HVAC-R and service water piping design and insulationVicente Varelaenergy_progress
09/11/2025HVAC-R and service water heating equipmentVicente Varelaenergy_progress
01/14/2025HVAC-R and service water piping design and insulationVicente Varelaenergy_progress
01/14/2025HVAC-R and service water heating equipmentVicente Varelaenergy_progress
01/14/2025HVAC-R and service water heating system controlsVicente Varelaenergy_progress
06/20/2024Fire-Resistance Rated ConstructionVicente Varelaprogress
06/20/2024Air barrier - visual inspectionVicente Varelaenergy_progress
06/19/2024Fenestration and door U-factor and product ratingsVicente Varelaenergy_progress
06/19/2024Fenestration areasVicente Varelaenergy_progress
06/19/2024Fenestration air leakageVicente Varelaenergy_progress
06/19/2024FinalVicente Varelaprogress
06/19/2024Fire-Resistant Penetrations and JointsNouredine Benabdelhakspecial
06/19/2024Insulation placement and R valuesVicente Varelaenergy_progress
▾Documents — 25 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/24/2026B01068950-I1Request digital key ↗
08/24/2026B01068950-S1Request digital key ↗
08/24/2026B01068950-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications21
▸DOB NOWProgress Inspector Seal & Signature16
09/02/2026B01068950-P1Open ↗
09/02/2026B01068950-P1Open ↗
09/02/2026B01068950-P1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/24/2026B01068950-P2Open ↗
08/24/2026B01068950-I1Open ↗
08/24/2026B01068950-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026B01068950-I1Open ↗