← Back
Two family brick
338 FENIMORE STREET
BROOKLYN · BIN 3390879
💬 Discuss this project
2006Year Built
4Stories
B1Building Class
R6Zoning
2,658 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family brick · 1,438 sf lot · 1.85 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
Floor 1Under Construction4p · 1 filing · 18 docs
Basement1p · 1 filing · 2 docs
Sub-BasementUnder Construction3p · 1 filing · 18 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SCALAR ARCHITECTURE PC507/22/2026
KN3 ENGINEERING LLC101/03/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AE DESIGN SOLUTION603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
INNOVACORE ENVIROMNENTALGeneral Contractor206/27/2026
Building Lifecycle
All (58)Filed (6)Permit Issued (2)Violation (2)Objection (28)Special Inspection (20)
08/27/2026
Objection resolved — Resolved
08/27/2026
Objection resolved — Resolved
07/28/2026
Objection raised — Scope
07/28/2026
Objection raised — Scope
07/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/23/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
07/23/2026
Special inspection requirement — Maintenance information
07/22/2026
Filed — Alteration
INSTALLATION OF NEW PIPING AND PLUMBING FIXTURES AT BASEMENT AND FIRST FLOOR AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPNACY. APPLICATION FILED IN CONJUNCTION WITH DOB ALTERATION TYPE 2# B01132395-I1.
B01132395-P3
07/21/2026
Special inspection requirement — Final
JULIO SALCEDO-FERNANDEZ
06/23/2026
Special inspection requirement — Final
JULIO SALCEDO-FERNANDEZ
06/17/2026
Objection resolved — Addressed
06/17/2026
Objection resolved — Addressed
06/16/2026
Objection raised — Other
06/16/2026
Objection raised — Other
06/11/2026
Objection raised — Scope
06/11/2026
Objection raised — Cost
06/05/2026
Objection resolved — Addressed
06/04/2026
Objection raised — Scope
06/03/2026
Filed — Alteration
INSTALLATION OF NEW PIPING AND PLUMBING FIXTURES AT BASEMENT AND FIRST FLOOR AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPNACY. APPLICATION FILED IN CONJUNCTION WITH DOB ALTERATION TYPE 2# B01132395-I1.
B01132395-P2
05/27/2026
Filed — Alteration
INSTALLATION OF NEW PIPING AND PLUMBING FIXTURES AT BASEMENT AND FIRST FLOOR AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPNACY. APPLICATION FILED IN CONJUNCTION WITH DOB ALTERATION TYPE 2# B01132395-I1.
B01132395-P1
05/27/2026
Special inspection requirement — Final
JULIO SALCEDO-FERNANDEZ
05/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/18/2026
Special inspection requirement — Maintenance information
05/18/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
03/13/2026
Permit issued — General Construction
B01132395-I1-GC
04/04/2025
Filed — Alteration
INSTALLATION OF NEW PIPING AND PLUMBING FIXTURES AT BASEMENT AND FIRST FLOOR AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPNACY. APPLICATION FILED IN CONJUNCTION WITH DOB ALTERATION TYPE 2# B01132395-I1.
B01132395-S1
02/28/2025
Permit issued — General Construction
B01132395-I1-GC
11/14/2024
Filed — Alteration
INSTALLATION OF NEW PIPING AND PLUMBING FIXTURES AT BASEMENT AND FIRST FLOOR AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPNACY. APPLICATION FILED IN CONJUNCTION WITH DOB ALTERATION TYPE 2# B01132395-I1.
B01132395-I1
06/18/2024
Objection resolved — Resolved
06/17/2024
Objection resolved — Resolved
06/17/2024
Objection resolved — Resolved
06/17/2024
Objection resolved — Resolved
06/17/2024
Objection resolved — Resolved
06/17/2024
Objection resolved — Resolved
06/17/2024
Objection resolved — Resolved
06/17/2024
Objection resolved — Resolved
01/11/2024
Objection raised — Zoning
01/11/2024
Objection raised — Fire_Protection
01/11/2024
Objection raised — Scope
01/11/2024
Objection raised — Scope
01/11/2024
Objection raised — Scope
01/11/2024
Objection raised — Zoning
01/11/2024
Objection raised — Structural
01/11/2024
Objection raised — Zoning
01/03/2024
Filed — Alteration CO
PROPOSED CHANGE OF USE AT BASEMENT; NEW GARAGE AT BASEMENT;PROPOSED INTERIOR WORK AT 1ST FLOOR.
B00832235-I1
12/14/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
12/14/2023
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
12/14/2023
Special inspection requirement — Fenestration areas
12/14/2023
Special inspection requirement — Fenestration air leakage
12/14/2023
Special inspection requirement — Insulation placement and R values
12/14/2023
Special inspection requirement — Energy Code Compliance Inspections
12/14/2023
Special inspection requirement — Fire-Resistance Rated Construction
12/14/2023
Special inspection requirement — Air barrier - visual inspection
10/23/2023
Special inspection requirement — Structural Steel - Details
02/20/2023
Special inspection requirement — Final
02/20/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
02/25/2011
Violation issued (ECB, closed)
Zoning
02/25/2011
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedINNOVACORE ENVIROMNENTAL03/13/2026
DOB NOWGeneral ConstructionPermit IssuedINNOVACORE ENVIROMNENTAL02/28/2025
BISOTISSUEDSASCO CONSTRUCTION SVCE L08/15/2017
BISCCISSUEDSASCO BUILDERS INC04/12/2012
BISPLISSUEDS.J. VISION & SON PLG & HTG03/28/2006
BIS—ISSUEDMASS CONST03/10/2006
BISEQISSUEDMASS CONST03/10/2006
BISEQISSUEDMASS CONST01/18/2006
BIS—ISSUEDMASS CONST01/18/2006
1 project · most recent 07/22/2026
Gas Water/Sanitary
FiledStatusContractorScope
07/22/2026——Gas, Water/Sanitary
2 projects · most recent 07/22/2026
Steel Concrete
FiledStatusContractorScope
07/22/2026Permit IssuedINNOVACORE ENVIROMNENTAL1 scope_items
01/03/2024——Steel, Concrete
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
07/23/2026Fire-Resistant Penetrations and Joints—special
07/23/2026HVAC-R and service water piping design and insulation—energy_progress
07/23/2026Maintenance information—energy_progress
07/21/2026FinalJULIO SALCEDO-FERNANDEZprogress
06/23/2026FinalJULIO SALCEDO-FERNANDEZprogress
05/27/2026FinalJULIO SALCEDO-FERNANDEZprogress
05/18/2026Fire-Resistant Penetrations and Joints—special
05/18/2026Maintenance information—energy_progress
05/18/2026HVAC-R and service water piping design and insulation—energy_progress
12/14/2023Fenestration and door U-factor and product ratings—energy_progress
12/14/2023Exterior Insulation and Finish Systems (EIFS)—special
12/14/2023Fenestration areas—energy_progress
12/14/2023Fenestration air leakage—energy_progress
12/14/2023Insulation placement and R values—energy_progress
12/14/2023Energy Code Compliance Inspections—progress
12/14/2023Fire-Resistance Rated Construction—progress
12/14/2023Air barrier - visual inspection—energy_progress
10/23/2023Structural Steel - Details—special
02/20/2023Final—progress
02/20/2023Structural Stability – Alterations of existing buildings—special
▾Documents — 45 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/16/2026B01132395-I1Request digital key ↗
08/16/2026B01132395-P3Request digital key ↗
08/16/2026B01132395-S1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION3
08/14/2017321612938Open ↗
04/09/2012320458982Open ↗
09/20/2011320347763Open ↗
▸BISWORK PERMIT APPLICATION2
08/16/2017321612938Open ↗
04/18/2012320458982Open ↗
▸Seals & Professional Certifications18
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/16/2026B01132395-P3Open ↗
08/16/2026B01132395-P1Open ↗
08/16/2026B01132395-S1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
10/05/2017321612938Open ↗
08/14/2017321612938Open ↗
04/09/2012320458982Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
09/02/2026B01132395-I1Open ↗
08/31/2026B01132395-P2Open ↗
08/24/2026B01132395-P3Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
08/14/2017321612938Open ↗
04/09/2012320458982Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
08/14/2017321612938Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
04/09/2012320458982Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
08/14/2017321612938Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/16/2026B01132395-P3Open ↗
08/16/2026B01132395-I1Open ↗
08/15/2026B01132395-P2Open ↗
▸Approvals, Objections & Sign-offs4
▸BISADMINISTRATIVE OBJECTIONS2
04/09/2012320458982Open ↗
09/20/2011320347763Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
11/20/2017321612938Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
10/05/2017321612938Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
10/05/2017321612938Open ↗
08/14/2017321612938Open ↗
09/20/2011320347763Open ↗
▸Filing & Intake Forms5
▸BISEFILING COVER SHEET2
04/09/2012320458982Open ↗
09/20/2011320347763Open ↗
▸BISADDITIONAL INFORMATION2
10/11/2012320347763Open ↗
04/18/2012320458982Open ↗
▸BISBOROUGH INTAKE FORM1
11/20/2017321612938Open ↗