| Owner | Filings | Most Recent |
|---|---|---|
| 46 ROEBLING CORP. | 1 | 03/22/2026 |
| ESER REALTY | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DESIGN INNOVATIONS FOR ARCHITECTURE | 2 | 08/10/2023 |
| KARACOBAN ENGINEERING PC | 4 | 07/31/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| QUICK FILING OF NY INC | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MKNK WASTE REMOVAL INC | General Contractor | 4 | 07/08/2026 |
| LIGHTEN UP ELEC'L SERVICE | Electrical | 1 | 03/22/2026 |
| DC BUILDING SERVICES INC | Fire Protection | 1 | 07/08/2026 |
| PAUL TRAKTMAN LIC PLBR IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIG APPLE GROUP NY A RMA | 9168 | 4 | 08/10/2023 |
| CEYLAN DESIGN AND CONSULT | 8422 | 5 | 07/31/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | PAUL TRAKTMAN LIC PLBR IN | 02/17/2023 |
| DOB NOW | Sprinklers | Signed-off | DC BUILDING SERVICES INC | 02/17/2023 |
| DOB NOW | General Construction | Signed-off | MKNK WASTE REMOVAL INC | 02/07/2023 |
| DOB NOW | Mechanical Systems | Signed-off | MKNK WASTE REMOVAL INC | 02/07/2023 |
| BIS | PL | ISSUED | PLBG P & H INC | 09/27/2020 |
| BIS | MH | ISSUED | RUBIN DEVEL AND CONST INC | 05/27/2020 |
| BIS | PL | ISSUED | PLBG P & H INC | 05/07/2020 |
| BIS | SP | ISSUED | BRUCHE MECHANICAL NY LLC | 05/07/2020 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 03/12/2020 |
| BIS | PL | ISSUED | PLBG P & H INC | 09/25/2019 |
| BIS | MH | ISSUED | RUBIN DEVEL AND CONST INC | 05/23/2019 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 05/23/2019 |
| BIS | SP | ISSUED | BRUCHE MECHANICAL NY LLC | 04/10/2019 |
| BIS | PL | ISSUED | PLBG P & H INC | 04/10/2019 |
| BIS | PL | ISSUED | PLBG P & H INC | 09/27/2018 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 09/12/2018 |
| BIS | MH | ISSUED | RUBIN DEVEL AND CONST INC | 05/24/2018 |
| BIS | MH | ISSUED | RUBIN DEVEL AND CONST INC | 11/30/2017 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 09/19/2017 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 09/19/2017 |
| BIS | PL | ISSUED | AJC PLUMBING & HTG CORP | 08/21/2017 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 12/01/2016 |
| BIS | MH | ISSUED | RUBIN DEVEL AND CONST INC | 12/01/2016 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 04/01/2016 |
| BIS | MH | ISSUED | RUBIN DEVEL AND CONST INC | 12/07/2015 |
| BIS | — | ISSUED | RUBIN DEVEL AND CONST INC | 04/21/2015 |
| BIS | MH | ISSUED | RUBIN DEVEL AND CONST INC | 04/08/2015 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/10/2023 | Signed-off | MKNK WASTE REMOVAL INC | Associated Ducts and Piping, Heating Systems, Ventilation Systems | Heating Warren Technology CBK 15 kW · Ductwork ×1 Ventilation Homewerks Worldwide Model No: 7114-01 50 CFM ×3 Warren Technology CBK 900 CFM ×1 Ducts & Piping Stelpro Model No: ASHU0381C24 900 CFM · Ductwork ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2023 | Signed-off | DC BUILDING SERVICES INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/10/2023 | Signed-off | PAUL TRAKTMAN LIC PLBR IN | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/28/2023 | Permit Issued | MAC ELECT'L CONTR. INC. | 2 meters |
| 01/04/2021 | Complete | LIGHTEN UP ELEC'L SERVICE | General Wiring |
| 04/29/2019 | Complete | R.C.M. ELECTRIC CORP. | General Wiring |
| 10/19/2018 | Complete | LIGHTEN UP ELEC'L SERVICE | General Wiring, Lighting |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/01/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/04/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/01/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 02/23/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/13/2023 | Lighting controls | Soorjbally Harilall | energy_progress |
| 08/13/2023 | Interior lighting power | Soorjbally Harilall | energy_progress |
| 08/13/2023 | Tenant Protection Plan Compliance | SERDAR CEYLAN | special |
| 08/13/2023 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 08/13/2023 | Preliminary | Soorjbally Harilall | progress |
| 08/13/2023 | Energy Code Compliance Inspections | Soorjbally Harilall | progress |
| 08/13/2023 | Fire-Resistance Rated Construction | Soorjbally Harilall | progress |
| 08/13/2023 | Final | SERDAR CEYLAN | progress |
| 08/02/2023 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 08/02/2023 | Tenant Protection Plan Compliance | — | special |
| 08/02/2023 | Energy Code Compliance Inspections | Soorjbally Harilall | progress |
| 08/02/2023 | Final | SERDAR CEYLAN | progress |
| 08/02/2023 | Fire-Resistance Rated Construction | Soorjbally Harilall | progress |
| 08/02/2023 | Preliminary | Soorjbally Harilall | progress |
| 08/02/2023 | Interior lighting power | Soorjbally Harilall | energy_progress |
| 08/02/2023 | Lighting controls | Soorjbally Harilall | energy_progress |
| 12/16/2022 | Tenant Protection Plan Compliance | SERDAR CEYLAN | special |
| 12/14/2022 | Sprinkler Systems | SOORJBALLY HARILALL | special |