← Back
Over six families without stores
BROOKLYN AVENUE
BROOKLYN · BIN 3429325
💬 Discuss this project
2022Year Built
5Stories
C1Building Class
R6Zoning
5,170 sfGross Floor Area
9Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Over six families without stores · Owner of record: 1665 SUITE LLC · 2,000 sf lot · 2.59 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof16p · 1 filing · 20 docs
Penthouse20p · 2 filings · 20 docs
Floor 421p · 2 filings · 20 docs
Floor 316p · 1 filing · 20 docs
Floor 217p · 1 filing · 20 docs
Floor 119p · 2 filings · 20 docs
1 job · most recent 09/12/2023
Sprinkler System
FiledStatusContractorScope
09/12/2023Signed-offPRIME PIPING & HEATING INSprinkler System
1 job · most recent 09/12/2023
Storm Water/Sanitary
FiledStatusContractorScope
09/12/2023Signed-offA M B MECHANICAL INCStorm, Water/Sanitary
2 jobs · most recent 03/22/2023
General Wiring
FiledStatusContractorScope
03/22/2023CompleteSPARK ELECTRICAL SVCS LLC10 meters, 10 new_meters
01/31/2023CompleteMANHATTAN FIRE & SEC ELECGeneral Wiring
Building Lifecycle
All (99)Filed (10)Permit Issued (10)Signed Off (5)Violation (3)Inspection (7)Objection (34)Special Inspection (30)
04/18/2024
Violation issued (HPD, closed)
A
10/25/2023
Signed off — New Building
Propose a plumbing scope of work filed in conjunction with NB# B00709787 -I1. There is no change in use, egress, or occupancy filed under this application.
B00709787-S2
10/03/2023
Special inspection requirement — Maintenance information
Younes Abouyaala
10/03/2023
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
10/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
10/03/2023
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
10/03/2023
Special inspection requirement — Post-installed Anchors
Younes Abouyaala
10/03/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Younes Abouyaala
10/03/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
10/03/2023
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
09/22/2023
Signed off — New Building
Propose a plumbing scope of work filed in conjunction with NB# B00709787 -I1. There is no change in use, egress, or occupancy filed under this application.
B00709787-S3
09/20/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
09/18/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/14/2023
Special inspection requirement — Sprinkler Systems
Younes Abouyaala
09/14/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
09/14/2023
Special inspection requirement — Post-installed Anchors
Younes Abouyaala
09/12/2023
Filed — New Building
Propose a plumbing scope of work filed in conjunction with NB# B00709787 -I1. There is no change in use, egress, or occupancy filed under this application.
B00709787-P4
09/12/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
09/12/2023
Special inspection requirement — Post-installed Anchors
Younes Abouyaala
09/12/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
09/12/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Younes Abouyaala
09/12/2023
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
09/12/2023
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
09/12/2023
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
09/12/2023
Special inspection requirement — Maintenance information
Younes Abouyaala
09/06/2023
Filed — New Building
Propose a plumbing scope of work filed in conjunction with NB# B00709787 -I1. There is no change in use, egress, or occupancy filed under this application.
B00709787-P2
08/22/2023
Special inspection requirement — Sprinkler Systems
Younes Abouyaala
08/22/2023
Special inspection requirement — Post-installed Anchors
Younes Abouyaala
08/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
07/11/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/06/2023
Signed off — New Building
Propose a plumbing scope of work filed in conjunction with NB# B00709787 -I1. There is no change in use, egress, or occupancy filed under this application.
B00709787-S1
05/31/2023
Signed off — Alteration
STRUCTURAL WORK TYPE IN CONJUNCTION WITH NEW BUILDING JOB APPLICATION #:B00709787-I1
B00739429-I1
05/31/2023
Signed off — Alteration
EARTHWORK AND FOUNDATION WORK IN CONJUCTIN WITH NB #B00709787-I1
B00719887-I1
05/31/2023
Permit issued — General Construction
B00709787-I1-GC
05/16/2023
Permit issued — Mechanical Systems
B00709787-S1-MS
04/03/2023
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
04/03/2023
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
04/03/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/03/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
02/21/2023
Permit issued — Plumbing
B00709787-S2-PL
02/21/2023
Permit issued — Sprinklers
B00709787-S3-EW-SP
02/13/2023
Violation issued (ECB, closed)
Construction
12/22/2022
Violation issued (ECB, closed)
Construction
12/08/2022
Permit issued — Structural
B00739429-I1-ST
10/14/2022
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
10/14/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
INDARDEO PARBHUNATH
10/14/2022
Special inspection requirement — Fenestration areas
Younes Abouyaala
10/14/2022
Special inspection requirement — Lighting in dwelling units
Younes Abouyaala
10/14/2022
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
INDARDEO PARBHUNATH
10/14/2022
Special inspection requirement — Metering
Younes Abouyaala
10/14/2022
Special inspection requirement — Interior lighting power
Younes Abouyaala
10/14/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
10/03/2022
Filed — New Building
Propose a plumbing scope of work filed in conjunction with NB# B00709787 -I1. There is no change in use, egress, or occupancy filed under this application.
B00709787-P1
08/09/2022
Objection raised — Admin
08/09/2022
Objection resolved — Addressed
08/09/2022
Objection raised — Inspections
08/09/2022
Objection resolved — Addressed
08/09/2022
Objection raised — Structural
08/09/2022
Objection resolved — Addressed
08/09/2022
Objection raised — Structural
Latest 60 of 99 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FOUR BORO ENTERPRISE203/22/2026
1665 SUITE203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ENGINEERING PROFESSIONAL SERVICE P.809/12/2023
HY PE STRUCTURAL ENGINEERING308/03/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMG GROUP USA903/21/2026
ADVANCED BUILDERS SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FOUR BORO ENTERPRISE INCGeneral Contractor707/08/2026
N TECH DESIGN OF AMERICAGeneral Contractor603/21/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
PRIME PIPING & HEATING INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519909/12/2023
IP CONCRETE TESTING AND I6252310/03/2022
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedFOUR BORO ENTERPRISE INC05/31/2023
DOB NOWMechanical SystemsSigned-offFOUR BORO ENTERPRISE INC05/16/2023
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN02/21/2023
DOB NOWSprinklersSigned-offA M B MECHANICAL INC02/21/2023
DOB NOWStructuralSigned-offFOUR BORO ENTERPRISE INC12/08/2022
DOB NOWGeneral ConstructionPermit IssuedFOUR BORO ENTERPRISE INC08/02/2022
DOB NOWGeneral ConstructionPermit IssuedFOUR BORO ENTERPRISE INC06/30/2022
DOB NOWEarth WorkSigned-offFOUR BORO ENTERPRISE INC06/29/2022
DOB NOWGeneral ConstructionPermit IssuedN TECH DESIGN OF AMERICA06/15/2022
DOB NOWFoundationSigned-offN TECH DESIGN OF AMERICA06/13/2022
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
09/20/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/18/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/11/2023Pass-Final CND-Occupancy InspectionPassView ↗
04/03/2023Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
04/03/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
04/03/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/03/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 70
DateRequirementInspectorRole
10/03/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationYounes Abouyaalaspecial
10/03/2023Energy Code Compliance InspectionsYounes Abouyaalaprogress
10/03/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
10/03/2023Post-installed AnchorsYounes Abouyaalaspecial
10/03/2023Maintenance informationYounes Abouyaalaenergy_progress
10/03/2023HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
10/03/2023HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
10/03/2023HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
09/14/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
09/14/2023Sprinkler SystemsYounes Abouyaalaspecial
09/14/2023Post-installed AnchorsYounes Abouyaalaspecial
09/12/2023Post-installed AnchorsYounes Abouyaalaspecial
09/12/2023HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
09/12/2023Maintenance informationYounes Abouyaalaenergy_progress
09/12/2023HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
09/12/2023HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
09/12/2023Energy Code Compliance InspectionsYounes Abouyaalaprogress
09/12/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationYounes Abouyaalaspecial
09/12/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
08/22/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
08/22/2023Post-installed AnchorsYounes Abouyaalaspecial
08/22/2023Sprinkler SystemsYounes Abouyaalaspecial
10/14/2022Fire-Resistant Penetrations and JointsINDARDEO PARBHUNATHspecial
10/14/2022Exterior Insulation and Finish Systems (EIFS)INDARDEO PARBHUNATHspecial
10/14/2022Energy Code Compliance InspectionsYounes Abouyaalaprogress
Latest 25 of 70.
▾Documents — 68 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/29/2026B00719887-P1Request digital key ↗
08/26/2026B00709787-P4Request digital key ↗
08/26/2026B00709787-P3Request digital key ↗
Showing 3 of 11 on file for this type
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026B00709787-P1Open ↗
08/13/2026B00709787-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026B00709787-I1Open ↗
08/13/2026B00709787-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00709787-I1Open ↗
▸Seals & Professional Certifications33
▸DOB NOWProgress Inspector Seal & Signature12
09/02/2026B00709787-P1Open ↗
09/02/2026B00709787-P1Open ↗
08/29/2026B00709787-S1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/29/2026B00719887-I1Open ↗
08/29/2026B00719887-P1Open ↗
08/26/2026B00709787-P4Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/02/2026B00709787-P1Open ↗
09/02/2026B00709787-P1Open ↗
08/29/2026B00709787-S1Open ↗
Showing 3 of 10 on file for this type
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026B00709787-P1Open ↗
08/13/2026B00709787-I1Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/26/2026B00709787-P1Open ↗
08/26/2026B00709787-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00709787-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00709787-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00709787-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026B00709787-I1Open ↗
▸Inspections & Test Reports4
▸DOB NOWSOIL REPORT2
08/29/2026B00719887-P1Open ↗
08/14/2026B00719887-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/14/2026B00719887-I1Open ↗
▸DOB NOWTR4 Plot Diagram1
08/14/2026B00719887-I1Open ↗
▸Other Documents7
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B00709787-I1Open ↗
08/13/2026B00709787-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/26/2026B00709787-I1Open ↗
08/26/2026B00709787-P1Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00709787-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B00709787-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/14/2026B00719887-I1Open ↗