| Firm | Filings | Most Recent |
|---|---|---|
| KCE CONSULTING ENGINEERING PLLC | 3 | 03/20/2026 |
| VASILIOS ARTEMIOU PE | 2 | 01/21/2026 |
| YOEL ROZENBERG | 2 | 06/17/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MOD CONSULTANTS LLC | General Contractor | 5 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 6 | 03/20/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | MOD CONSULTANTS LLC | 06/17/2026 |
| DOB NOW | General Construction | Permit Issued | MOD CONSULTANTS LLC | 06/04/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | MOD CONSULTANTS LLC | 06/02/2026 |
| DOB NOW | Structural | Permit Issued | MOD CONSULTANTS LLC | 06/01/2026 |
| DOB NOW | Support of Excavation | Permit Issued | FANG YE | 06/01/2026 |
| DOB NOW | Construction Fence | Permit Issued | MOD CONSULTANTS LLC | 07/08/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/20/2026 | Permit Issued | MOD CONSULTANTS LLC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | Permit Issued | MOD CONSULTANTS LLC | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | Permit Issued | MOD CONSULTANTS LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/18/2026 | Post-installed Anchors | SHAHRIAR QUAYYUM | special |
| 03/18/2026 | Structural Steel - Welding | SHAHRIAR QUAYYUM | special |
| 03/18/2026 | Structural Steel - High Strength Bolting | SHAHRIAR QUAYYUM | special |
| 03/18/2026 | Structural Steel - Details | SHAHRIAR QUAYYUM | special |
| 03/18/2026 | Structural Cold-Formed Steel | SHAHRIAR QUAYYUM | special |
| 03/18/2026 | Structural Stability – Alterations of existing buildings | SHAHRIAR QUAYYUM | special |
| 02/26/2026 | Final | SHAHRIAR QUAYYUM | progress |
| 01/16/2026 | Shutoff dampers | SHAHRIAR QUAYYUM | energy_progress |
| 01/16/2026 | Duct leakage testing, insulation and design | SHAHRIAR QUAYYUM | energy_progress |
| 01/16/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 01/16/2026 | Mechanical Systems | SHAHRIAR QUAYYUM | special |
| 01/16/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 01/16/2026 | Post-installed Anchors | SHAHRIAR QUAYYUM | special |
| 01/16/2026 | Final | SHAHRIAR QUAYYUM | progress |
| 01/16/2026 | HVAC-R and service water piping design and insulation | SHAHRIAR QUAYYUM | energy_progress |
| 01/16/2026 | HVAC-R and service water heating equipment | SHAHRIAR QUAYYUM | energy_progress |
| 01/16/2026 | HVAC-R and service water heating system controls | SHAHRIAR QUAYYUM | energy_progress |
| 01/15/2026 | Sprinkler Systems | SHAHRIAR QUAYYUM | special |
| 01/15/2026 | Post-installed Anchors | SHAHRIAR QUAYYUM | special |
| 01/15/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |