| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/22/2026 | Permit Issued | RICHARD NEU | — |
| 11/28/2025 | Permit Issued | LIGHTFORCE ELECL CONTNG I | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | B&B MECH PLBG & HTG LLC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/20/2026 | Permit Issued | PLATINUM SERVICES NY LLC | Scaffold, Sidewalk Shed |
| Owner | Filings | Most Recent |
|---|---|---|
| 57TH DEV | 25 | 09/13/2026 |
| PLATINUM SERVICES NY | 5 | 04/09/2026 |
| CITYSCAPE BUILDERS | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/03/2024 | $2.5M | — | — → — | — not available |
| 12/17/2021 | $2.1M | — | 1118 57 LOFTS LLC → Private party | — not available |
| 06/24/2021 | $999K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ASHER ARCHITECT | 5 | 08/24/2026 |
| ALWAYS FAST SERVICES CORP | 1 | 01/20/2026 |
| R & O ENGINEERING | 4 | 11/26/2025 |
| EYAL LEVITT ARCHITECT PC | 1 | 07/29/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ERETZ BUILDERS ASSISTANCE. | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CITYSCAPE BUILDERS LLC | General Contractor | 5 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 2 | 04/09/2026 |
| LIGHTFORCE ELECL CONTNG I | Electrical | 1 | 03/22/2026 |
| TARGET PIPING NY LLC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIG APPLE GROUP NY A RMA | 9168 | 9 | 07/15/2026 |
| METRO FIRE CONTROL LLC | 4538 | 1 | 07/29/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 01/27/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PLATINUM SERVICES NY LLC | 01/20/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | PLATINUM SERVICES NY LLC | 01/20/2026 |
| DOB NOW | Structural | Permit Issued | CITYSCAPE BUILDERS LLC | 01/14/2026 |
| DOB NOW | General Construction | Permit Issued | CITYSCAPE BUILDERS LLC | 11/13/2025 |
| DOB NOW | Foundation | Permit Issued | CITYSCAPE BUILDERS LLC | 09/09/2025 |
| DOB NOW | General Construction | Permit Issued | CITYSCAPE BUILDERS LLC | 08/25/2025 |
| DOB NOW | Support of Excavation | Signed-off | CITYSCAPE BUILDERS LLC | 08/25/2025 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/24/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 08/24/2026 | Ventilation and air distribution system | — | energy_progress |
| 08/24/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/24/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 08/24/2026 | Maintenance information | — | energy_progress |
| 08/24/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/05/2026 | HVAC-R and service water piping design and insulation | SOORJBALLY HARILALL | energy_progress |
| 08/05/2026 | HVAC-R and service water heating system controls | SOORJBALLY HARILALL | energy_progress |
| 08/05/2026 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 08/05/2026 | Maintenance information | SOORJBALLY HARILALL | energy_progress |
| 08/05/2026 | HVAC-R and service water heating equipment | SOORJBALLY HARILALL | energy_progress |
| 08/03/2026 | Final | — | progress |
| 08/03/2026 | Mechanical Systems | — | special |
| 07/13/2026 | HVAC-R and service water heating equipment | SOORJBALLY HARILALL | energy_progress |
| 07/13/2026 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 07/13/2026 | HVAC-R and service water piping design and insulation | SOORJBALLY HARILALL | energy_progress |
| 07/13/2026 | HVAC-R and service water heating system controls | SOORJBALLY HARILALL | energy_progress |
| 07/13/2026 | Maintenance information | SOORJBALLY HARILALL | energy_progress |
| 12/02/2025 | Fenestration areas | SOORJBALLY HARILALL | energy_progress |
| 12/02/2025 | Energy Code Compliance Inspections | SOORJBALLY HARILALL | progress |
| 12/02/2025 | Fire-Resistance Rated Construction | SOORJBALLY HARILALL | progress |
| 12/02/2025 | Air barrier - visual inspection | SOORJBALLY HARILALL | energy_progress |
| 12/02/2025 | Fenestration and door U-factor and product ratings | SOORJBALLY HARILALL | energy_progress |
| 12/02/2025 | Interior lighting power | SOORJBALLY HARILALL | energy_progress |
| 12/02/2025 | Metering | SOORJBALLY HARILALL | energy_progress |