| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/13/2026 | — | — | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NLHZ 36,000 BTU · Heat Pump Outdoor ×7 MXZ-SM48NLHZ 48,000 BTU · Heat Pump Outdoor ×2 MXZ-SM60NL 60,000 BTU · Heat Pump Outdoor ×2 PUZ-AK12NL 18,000 BTU · Heat Pump Outdoor ×1 Ventilation Greenheck G-98-VG 400 CFM · Kitchen Exhaust ×2 G-120-VG 975 CFM · Exhaust Fan ×1 G-97-VG 225 CFM · Exhaust Fan ×1 G-99-VG 500 CFM · Exhaust Fan ×1 SQ-99-VG 575 CFM · Exhaust Fan ×1 USF-15 2,100 CFM · Exhaust Fan ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | — | — | Concrete |
| Firm | Filings | Most Recent |
|---|---|---|
| WEXLER ASSOCIATES | 3 | 04/13/2026 |
| ALL CITY ENGINEERING, P.C. | 3 | 04/13/2026 |
| INM ARCHITECTS PC | 1 | 03/24/2026 |
| STUDIOSC ARCHITECTURE PLLC | 1 | 01/29/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMB BUILDING CONSULTING | 2 | 03/21/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/05/2026 | Air barrier — testing | — | energy_progress |
| 05/06/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 05/06/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 05/06/2026 | Construction Operations Influencing Adjacent Structures | — | special |
| 05/05/2026 | Subgrade Inspections | — | special |
| 04/24/2026 | Structural Steel - Details | — | special |
| 04/24/2026 | Structural Steel - Welding | — | special |
| 04/13/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 04/13/2026 | Post-installed Anchors | — | special |
| 04/07/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 04/07/2026 | Subgrade Inspections | — | special |
| 04/07/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 04/07/2026 | Post-installed Anchors | — | special |
| 04/07/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 04/07/2026 | Concrete - Cast-In-Place | — | special |
| 04/07/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 03/26/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/26/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/26/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 03/26/2026 | Energy Code Compliance Inspections | — | progress |
| 03/26/2026 | Maintenance information | — | energy_progress |
| 03/26/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 03/26/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/26/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/26/2026 | Energy Code Compliance Inspections | — | progress |