| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2023 | — | — | Concrete |
| Firm | Filings | Most Recent |
|---|---|---|
| ELEVATED ENGINEERING NYC | 3 | 06/01/2023 |
| KAO HWA LEE ARCHITECTS PC | 1 | 04/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNSHINE PLAZA LLC | 4 | 03/21/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/01/2023 | Concrete - Cast-In-Place | — | special |
| 05/29/2023 | Exterior lighting power | — | energy_progress |
| 05/29/2023 | Maintenance information | — | energy_progress |
| 05/29/2023 | Metering | — | energy_progress |
| 05/29/2023 | Lighting controls | — | energy_progress |
| 05/29/2023 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 05/29/2023 | Air barrier — testing | — | energy_progress |
| 05/29/2023 | Electric vehicle service equipment requirements | — | energy_progress |
| 05/29/2023 | Fenestration areas | — | energy_progress |
| 05/29/2023 | Insulation placement and R values | — | energy_progress |
| 05/29/2023 | Lighting in dwelling units | — | energy_progress |
| 05/29/2023 | Fenestration air leakage | — | energy_progress |
| 05/29/2023 | Interior lighting power | — | energy_progress |
| 05/15/2023 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 05/15/2023 | Final | — | progress |
| 05/15/2023 | Footing and Foundation | — | progress |
| 05/15/2023 | Subgrade Inspections | — | special |
| 05/15/2023 | Post-installed Anchors | — | special |
| 05/15/2023 | Final | — | progress |
| 05/15/2023 | Concrete - Cast-In-Place | — | special |