| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/03/2019 | Complete | LENS ELECTRIC, INC | General Wiring |
| 01/03/2018 | Complete | WCK ELECTRIC CORP. | — |
| Owner | Filings | Most Recent |
|---|---|---|
| HKS CONSTRUCTION | 8 | 07/08/2026 |
| ALEF CONSTRUCTION | 9 | 03/22/2026 |
| USA PRINCE PROPERTIES | 17 | 03/22/2026 |
| ALEF CONSTRUCITON INC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/30/2016 | $910K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| CAVALRY ASSOCIATES | 2 | 04/25/2022 |
| M.INT'L ENGINEERING PLLC | 1 | 01/24/2022 |
| HAIDER ENGINEERING, P.E. | 1 | 01/25/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| CAVALRY LLC | 3 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 1 | 03/21/2026 |
| CAVALRY ASSOCIATES COM | 3 | 03/21/2026 |
| HAIDER ENGINEERING P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HKS CONSTRUCTION CORP | General Contractor | 7 | 07/08/2026 |
| ALEF CONSTRUCTION INC | General Contractor | 4 | 07/08/2026 |
| PLBG P & H INC | Plumbing | 3 | 03/22/2026 |
| ASHER HERSHKOWITZ ARCHITECT | General Contractor | 2 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| M. INT'L ENGINEERING PLLC | 3129 | 1 | 04/05/2022 |
| HRF SERVICES CORP | 5616 | 1 | 01/24/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | ALEF CONSTRUCTION INC | 08/19/2022 |
| DOB NOW | General Construction | Signed-off | ALEF CONSTRUCTION INC | 05/10/2022 |
| DOB NOW | Structural | Signed-off | ALEF CONSTRUCTION INC | 03/10/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 10/18/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 03/08/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 01/26/2018 |
| BIS | — | ISSUED | ALEF CONSTRUCTION INC | 10/08/2020 |
| BIS | PL | ISSUED | PLBG P & H INC | 09/04/2020 |
| BIS | — | ISSUED | ALEF CONSTRUCTION INC | 10/05/2018 |
| BIS | EQ | ISSUED | ALEF CONSTRUCTION INC | 10/05/2018 |
| BIS | PL | ISSUED | WNW & SONS PLBG & HTG INC | 07/19/2018 |
| BIS | SP | ISSUED | WNW & SONS PLUMBING & HTG | 07/19/2018 |
| BIS | PL | ISSUED | PLBG P & H INC | 07/03/2018 |
| BIS | — | ISSUED | ALEF CONSTRUCTION INC | 11/16/2017 |
| BIS | — | ISSUED | ALEF CONSTRUCTION INC | 09/28/2017 |
| BIS | — | ISSUED | ALEF CONSTRUCTION INC | 04/05/2017 |
| BIS | EQ | ISSUED | ALEF CONSTRUCTION INC | 04/05/2017 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/27/2022 | Energy Code Compliance Inspections | MICHAEL VORLAND | progress |
| 04/27/2022 | Final | MICHAEL VORLAND | progress |
| 04/27/2022 | Structural Stability – Alterations of existing buildings | NANIK MASSAND | special |
| 04/25/2022 | Final | — | progress |
| 04/25/2022 | Structural Stability – Alterations of existing buildings | — | special |
| 04/25/2022 | Energy Code Compliance Inspections | — | progress |
| 12/20/2017 | Final | JAFAR HAIDER | progress |