← Back
All parking garages
62-15 34 AVENUE
QUEENS · BIN 4027109
💬 Discuss this project
1953Year Built
1Stories
G1Building Class
M1-1Zoning
6,026 sfGross Floor Area
1Units
4 Open Violations ▸
All parking garages · Owner of record: ALEENA REAL ESTATE, LLC · 6,283 sf lot · 0.96 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof1p · 1 filing · 20 docs
Mezzanine2p · 1 filing · 20 docs
1 job · most recent 12/17/2024
FiledStatusContractorScope
12/17/2024Permit IssuedOGC ELECTRICAL CONTRACTOR1 meters, 1 new_meters
1 job · most recent 10/29/2025
Masonry Wood
FiledStatusContractorScope
10/29/2025Signed-offJOHN EVAN CONTRACTING CORMasonry, Wood
1 job · most recent 11/17/2023
Fence
FiledStatusContractorScope
11/17/2023Permit IssuedFERHATI LLCFence
Building Lifecycle
All (84)Filed (7)Permit Issued (6)Signed Off (2)Violation (18)Inspection (6)Objection (15)Special Inspection (30)
05/27/2026
Signed off — Alteration
REPAIR & REBUILD BUILDING AFTER FIRE DAMAGE OF THE ROOF, EXTERIOR WALLS & STRUCTURAL ELEMENTS. AS PER IED# 343260 , ALL EMERGENCY DEMOLITION WORK WAS DONE UNDER EMERGENCY WORK CONTROL# 343260.
Q00978726-I1
04/14/2026
Signed off — Alteration
PLUMBING WORK IN CONJUNCTION WITH: Q00978726-I1
Q01102672-I1
03/10/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/05/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/29/2025
Filed — Alteration
REPAIR & REBUILD BUILDING AFTER FIRE DAMAGE OF THE ROOF, EXTERIOR WALLS & STRUCTURAL ELEMENTS. AS PER IED# 343260 , ALL EMERGENCY DEMOLITION WORK WAS DONE UNDER EMERGENCY WORK CONTROL# 343260.
Q00978726-P3
10/29/2025
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Younes Abouyaala
10/29/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
10/29/2025
Special inspection requirement — Final
NAVEEN KUMAR
10/29/2025
Special inspection requirement — Structural Wood Frame
Younes Abouyaala
10/29/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
10/29/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
10/29/2025
Special inspection requirement — Masonry
Younes Abouyaala
10/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
10/29/2025
Special inspection requirement — Wood – Seismic Resistance
Younes Abouyaala
10/29/2025
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
10/28/2025
Special inspection requirement — Structural Wood Frame
Younes Abouyaala
10/28/2025
Special inspection requirement — Wood – Seismic Resistance
10/28/2025
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Younes Abouyaala
10/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
10/28/2025
Special inspection requirement — Masonry
Younes Abouyaala
10/28/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
10/28/2025
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
10/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
10/28/2025
Special inspection requirement — Final
NAVEEN KUMAR
10/28/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
09/29/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/29/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
09/29/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/29/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/08/2025
Violation issued (ECB, closed)
Construction
05/07/2025
Violation issued (ECB, closed)
Construction
05/06/2025
Violation issued (ECB, closed)
Construction
05/06/2025
Violation issued (ECB, closed)
Unknown
05/06/2025
Violation issued (ECB, closed)
Unknown
05/06/2025
Violation issued (ECB, closed)
Unknown
05/06/2025
Violation issued (ECB, closed)
Construction
03/11/2025
Filed — Alteration
REPAIR & REBUILD BUILDING AFTER FIRE DAMAGE OF THE ROOF, EXTERIOR WALLS & STRUCTURAL ELEMENTS. AS PER IED# 343260 , ALL EMERGENCY DEMOLITION WORK WAS DONE UNDER EMERGENCY WORK CONTROL# 343260.
Q00978726-P2
02/07/2025
Permit issued — Plumbing
Q01102672-I1-PL
01/30/2025
Permit issued — General Construction
Q00978726-I1-GC-CX
01/06/2025
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH: Q00978726-I1
Q01102672-I1
12/23/2024
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/17/2024
Permit issued — Construction Fence
Q00964595-I1-FN
12/11/2024
Filed — Alteration
REPAIR & REBUILD BUILDING AFTER FIRE DAMAGE OF THE ROOF, EXTERIOR WALLS & STRUCTURAL ELEMENTS. AS PER IED# 343260 , ALL EMERGENCY DEMOLITION WORK WAS DONE UNDER EMERGENCY WORK CONTROL# 343260.
Q00978726-P1
12/11/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
12/11/2024
Special inspection requirement — Masonry
Younes Abouyaala
12/11/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
12/11/2024
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Younes Abouyaala
12/11/2024
Special inspection requirement — Wood – Seismic Resistance
12/11/2024
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
12/11/2024
Special inspection requirement — Final
NAVEEN KUMAR
12/11/2024
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
12/11/2024
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
12/11/2024
Special inspection requirement — Structural Wood Frame
Younes Abouyaala
10/30/2024
Objection raised — Other
10/30/2024
Objection raised — Other
10/30/2024
Objection raised — Other
10/30/2024
Objection raised — Other
10/30/2024
Objection raised — Other
10/30/2024
Objection raised — Other
10/30/2024
Objection raised — Other
Latest 60 of 84 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FERHATI2407/08/2026
ALEENA REAL ESTATE, LLC303/22/2026
JOHN EVAN CONTRACTING COR603/22/2026
FERHATI LLC GC 605602203/22/2026
JOHN EVENS CONTRACTING CO103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SELF EMPLOYED610/29/2025
MOHAMMAD AHEAD, PE110/15/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JOHN EVAN CONTRACTING CORGeneral Contractor903/21/2026
FERHATI LLCGeneral Contractor207/08/2026
ALL PRO PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519610/29/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offALL PRO PLBG & HTG INC02/07/2025
DOB NOWGeneral ConstructionSigned-offJOHN EVAN CONTRACTING COR01/30/2025
DOB NOWConstruction FencePermit IssuedFERHATI LLC12/17/2024
DOB NOWGeneral ConstructionSigned-offJOHN EVAN CONTRACTING COR05/22/2024
DOB NOWStructuralSigned-offJOHN EVAN CONTRACTING COR04/26/2024
DOB NOWConstruction FencePermit IssuedFERHATI LLC11/20/2023
BIS—ISSUEDDAVE-ED OPERATING CORP07/16/1992
BIS—ISSUEDDAVE-ED OPERATING CORP.07/10/1992
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/10/2026Pass-Final CND-Occupancy InspectionPassView ↗
11/05/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/29/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/29/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
09/29/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/29/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
10/29/2025Construction Operations Influencing Adjacent StructuresYounes Abouyaalaspecial
10/29/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
10/29/2025FinalNAVEEN KUMARprogress
10/29/2025Structural Wood FrameYounes Abouyaalaprogress
10/29/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
10/29/2025Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
10/29/2025MasonryYounes Abouyaalaspecial
10/29/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
10/29/2025Wood – Seismic ResistanceYounes Abouyaalaspecial
10/29/2025Structural Steel - DetailsYounes Abouyaalaspecial
10/28/2025Structural Wood FrameYounes Abouyaalaprogress
10/28/2025Wood – Seismic Resistance—special
10/28/2025Construction Operations Influencing Adjacent StructuresYounes Abouyaalaspecial
10/28/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
10/28/2025MasonryYounes Abouyaalaspecial
10/28/2025Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
10/28/2025Structural Steel - DetailsYounes Abouyaalaspecial
10/28/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
10/28/2025FinalNAVEEN KUMARprogress
10/28/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
12/11/2024Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
12/11/2024MasonryYounes Abouyaalaspecial
12/11/2024Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
12/11/2024Construction Operations Influencing Adjacent StructuresYounes Abouyaalaspecial
12/11/2024Wood – Seismic Resistance—special
Latest 25 of 34.
▾Documents — 56 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/23/2026Q00964595-I1Request digital key ↗
08/21/2026Q01102672-I1Request digital key ↗
08/18/2026Q00978726-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
11/17/2011420504779Open ↗
▸Seals & Professional Certifications39
▸DOB NOWSpecial Inspector Seal & Signature17
09/25/2026Q01102672-I1Open ↗
09/01/2026Q00978726-P3Open ↗
09/01/2026Q00978726-P3Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
09/25/2026Q01102672-I1Open ↗
09/01/2026Q00978726-P3Open ↗
09/01/2026Q00978726-P3Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/23/2026Q00964595-I1Open ↗
08/21/2026Q01102672-I1Open ↗
08/18/2026Q00978726-P1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
11/17/2011420504779Open ↗
11/17/2011420504779Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
11/17/2011420504779Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/21/2026Q01102672-I1Open ↗
08/13/2026Q01114520-I1Open ↗
08/13/2026Q00978726-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
11/17/2011420504779Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY1
11/17/2011420504779Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
11/18/2011420504779Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
11/17/2011420504779Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
11/17/2011420504779Open ↗