| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/12/2021 | Complete | KJK ELECTRIC INC | General Wiring |
| Firm | Filings | Most Recent |
|---|---|---|
| BASSIRI | 2 | 01/26/2024 |
| BILLAH ENGINEERING PLLC | 4 | 04/15/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| ECDESIGN STUDIO | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CROWN PLUMBING INC | Plumbing | 3 | 07/08/2026 |
| EXCELLENT METROPOLITAN | General Contractor | 1 | 07/08/2026 |
| KLE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BASSIRI | 8394 | 2 | 01/26/2024 |
| BILLAH ENGINEERING | 5838 | 1 | 04/15/2022 |
| G ENGINEERING PC | 7778 | 1 | 09/09/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | KLE CONSTRUCTION INC | 08/15/2023 |
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 02/22/2023 |
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 10/25/2022 |
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 10/29/2021 |
| DOB NOW | General Construction | Signed-off | EXCELLENT METROPOLITAN | 10/19/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/08/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/31/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/22/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/04/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/18/2022 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/29/2024 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 01/29/2024 | Final | FARHAD BASSIRI-TEHRANI | progress |
| 01/29/2024 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 01/29/2024 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 01/26/2024 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 01/26/2024 | Final | FARHAD BASSIRI-TEHRANI | progress |
| 01/26/2024 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 01/26/2024 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 05/03/2022 | Fire-Resistant Penetrations and Joints | XIONGCAI GU | special |
| 05/03/2022 | Fire-Resistance Rated Construction | XIONGCAI GU | progress |
| 05/03/2022 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 04/28/2022 | Fire-Resistance Rated Construction | MOHAMMAD BILLAH | progress |
| 04/28/2022 | Energy Code Compliance Inspections | MOHAMMAD BILLAH | progress |
| 04/28/2022 | Fire-Resistant Penetrations and Joints | MOHAMMAD BILLAH | special |