| Owner | Filings | Most Recent |
|---|---|---|
| SANG 888, LLC | 7 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| A&T CORP | 4 | 03/10/2026 |
| YOUN DESIGN CORP. | 1 | 10/11/2025 |
| DUNCAN ARCHITECT PLLC | 3 | 07/10/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| AJ EXPEDITING | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GREENBUILD CONST GRP INC | General Contractor | 3 | 03/21/2026 |
| TRI STATE CONSTRUCTION SE | General Contractor | 1 | 06/23/2026 |
| YOUN DESIGN CORP | General Contractor | 1 | 07/08/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A & T DESIGN GROUP LLC | 1088 | 4 | 03/10/2026 |
| KCE CONSULTING ENGINEERIN | 3712 | 2 | 10/03/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | TRI STATE CONSTRUCTION SE | 05/27/2026 |
| DOB NOW | General Construction | Signed-off | YOUN DESIGN CORP | 10/21/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 05/20/2025 |
| DOB NOW | General Construction | Signed-off | GREENBUILD CONST GRP INC | 10/29/2024 |
| BIS | FP | ISSUED | NEW YORK BUINESS FIRE SYSTEM INC | 01/07/2008 |
| BIS | FP | ISSUED | NY BUSINESS FIRE SYSTEM INC | 08/30/2002 |
| BIS | OT | ISSUED | PANE STONE CONST. | 12/07/1994 |
| BIS | FP | ISSUED | FIRE FOE CORP | 06/23/1992 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/31/2024 | Complete | GALLANT ELEC'L CONST, INC | General Wiring |
| 12/06/2024 | Permit Issued | GALLANT ELEC'L CONST, INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/17/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/25/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/26/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/20/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/14/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/10/2026 | Fire-Resistant Penetrations and Joints | ROBERT LIN | special |
| 06/30/2025 | Fire-Resistant Penetrations and Joints | ROBERT LIN | special |
| 06/09/2025 | Fire-Resistant Penetrations and Joints | ROBERT LIN | special |
| 10/09/2024 | Concrete - Cast-In-Place | Kemba Walcott | special |
| 10/09/2024 | Post-installed Anchors | Kemba Walcott | special |
| 10/09/2024 | Structural Steel - Details | Kemba Walcott | special |
| 10/09/2024 | Structural Wood Frame | Kemba Walcott | progress |
| 10/09/2024 | Final | Kemba Walcott | progress |
| 10/09/2024 | Structural Steel - High Strength Bolting | Kemba Walcott | special |
| 10/09/2024 | Structural Steel - Welding | Kemba Walcott | special |