| Owner | Filings | Most Recent |
|---|---|---|
| INNOSPARK DESIGN | 4 | 09/13/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AARON MCDONALD ARCHITECT | 4 | 08/07/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BUILDWISE CONSTRUCTION GR | General Contractor | 1 | 06/07/2026 |
| W.R. PLBG AND HTG CORP | Plumbing | 1 | 06/07/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AARON MCDONALD ARCHITECT | 5118 | 4 | 08/07/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | W.R. PLBG AND HTG CORP | 06/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | BUILDWISE CONSTRUCTION GR | 06/05/2026 |
| BIS | OT | ISSUED | KAMTECH RESTORATION CORP | 03/03/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/07/2026 | Permit Issued | BUILDWISE CONSTRUCTION GR | Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/07/2026 | Permit Issued | W.R. PLBG AND HTG CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| 04/08/2022 | Complete | BERGER QUALITY ELEC'L CON | — |
| 04/06/2022 | Complete | BERGER QUALITY ELEC'L CON | 1 meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/07/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/24/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/21/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2026 | Fire-Resistant Penetrations and Joints | Aaron McDonald | special |
| 08/07/2026 | Energy Code Compliance Inspections | Aaron McDonald | progress |
| 08/07/2026 | HVAC-R and service water heating equipment | Aaron McDonald | energy_progress |
| 08/07/2026 | HVAC-R and service water piping design and insulation | Aaron McDonald | energy_progress |
| 08/07/2026 | HVAC-R and service water heating system controls | Aaron McDonald | energy_progress |
| 08/04/2026 | Fire-Resistant Penetrations and Joints | Aaron McDonald | special |
| 08/04/2026 | Energy Code Compliance Inspections | Aaron McDonald | progress |
| 08/04/2026 | HVAC-R and service water heating system controls | Aaron McDonald | energy_progress |
| 08/04/2026 | HVAC-R and service water piping design and insulation | Aaron McDonald | energy_progress |
| 08/04/2026 | HVAC-R and service water heating equipment | Aaron McDonald | energy_progress |
| 06/02/2026 | Permanent certificate | Aaron McDonald | energy_progress |
| 06/02/2026 | Fire-Resistant Penetrations and Joints | Aaron McDonald | special |
| 06/02/2026 | Interior lighting power | Aaron McDonald | energy_progress |
| 06/02/2026 | HVAC-R and service water piping design and insulation | Aaron McDonald | energy_progress |
| 06/02/2026 | Energy Code Compliance Inspections | Aaron McDonald | progress |
| 06/02/2026 | Fire-Resistance Rated Construction | Aaron McDonald | progress |
| 06/02/2026 | HVAC-R and service water heating system controls | Aaron McDonald | energy_progress |
| 06/02/2026 | Insulation placement and R values | Aaron McDonald | energy_progress |
| 06/02/2026 | HVAC-R and service water heating equipment | Aaron McDonald | energy_progress |
| 05/27/2026 | Final | Aaron McDonald | progress |
| 05/27/2026 | Mechanical Systems | Aaron McDonald | special |