| Owner | Filings | Most Recent |
|---|---|---|
| 786 CORONA | 10 | 07/08/2026 |
| ACE GROUP NY | 4 | 04/09/2026 |
| 108-01 ROOSEVELT AVE | 3 | 03/22/2026 |
| J STONE BUILDERS | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ASKON ARCHITECTS, P.C. | 4 | 08/11/2026 |
| MOHAMMAD HAQUE | 1 | 11/08/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J STONE BUILDERS INC | General Contractor | 2 | 04/09/2026 |
| HIGH QUALITY ELEC.OF NYC | Electrical | 1 | 03/22/2026 |
| ACE GROUP NY CORP | General Contractor | 1 | 04/09/2026 |
| ZONE PLUMBING & HEATING C | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MOHAMMAD AHEAD - PROFESSI | 9286 | 3 | 08/11/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | J STONE BUILDERS INC | 02/02/2026 |
| DOB NOW | Plumbing | Permit Issued | ZONE PLUMBING & HEATING C | 11/24/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | ACE GROUP NY CORP | 11/10/2025 |
| DOB NOW | General Construction | Permit Issued | J STONE BUILDERS INC | 09/05/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/11/2026 | Permit Issued | ZONE PLUMBING & HEATING C | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | ANI ELECTRIC CORP | General Wiring |
| 11/13/2025 | Permit Issued | HIGH QUALITY ELEC.OF NYC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/11/2026 | Permit Issued | J STONE BUILDERS INC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/10/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/12/2026 | Maintenance information | MOHAMMAD AHEAD | energy_progress |
| 03/12/2026 | Metering | MOHAMMAD AHEAD | energy_progress |
| 03/12/2026 | HVAC-R and service water piping design and insulation | MOHAMMAD AHEAD | energy_progress |
| 03/12/2026 | Energy Code Compliance Inspections | MOHAMMAD AHEAD | progress |
| 03/12/2026 | Fire-Resistant Penetrations and Joints | MOHAMMAD AHEAD | special |
| 08/29/2025 | Fire-Resistant Penetrations and Joints | MOHAMMAD AHEAD | special |
| 08/29/2025 | Energy Code Compliance Inspections | MOHAMMAD AHEAD | progress |
| 08/29/2025 | HVAC-R and service water piping design and insulation | MOHAMMAD AHEAD | energy_progress |
| 08/29/2025 | Maintenance information | MOHAMMAD AHEAD | energy_progress |
| 08/29/2025 | Metering | MOHAMMAD AHEAD | energy_progress |
| 03/09/2025 | Maintenance information | MOHAMMAD AHEAD | energy_progress |
| 03/09/2025 | Exterior lighting power | MOHAMMAD AHEAD | energy_progress |
| 03/09/2025 | Lighting in dwelling units | MOHAMMAD AHEAD | energy_progress |
| 03/09/2025 | Metering | MOHAMMAD AHEAD | energy_progress |
| 03/09/2025 | Lighting controls | MOHAMMAD AHEAD | energy_progress |
| 03/09/2025 | Permanent certificate | MOHAMMAD AHEAD | energy_progress |
| 02/13/2025 | Fire-Resistance Rated Construction | MOHAMMAD AHEAD | progress |
| 02/13/2025 | Energy Code Compliance Inspections | MOHAMMAD AHEAD | progress |
| 02/13/2025 | Air barrier - visual inspection | MOHAMMAD AHEAD | energy_progress |
| 02/13/2025 | Fenestration air leakage | MOHAMMAD AHEAD | energy_progress |
| 02/13/2025 | Fenestration areas | MOHAMMAD AHEAD | energy_progress |
| 02/13/2025 | Fenestration and door U-factor and product ratings | MOHAMMAD AHEAD | energy_progress |
| 02/13/2025 | Insulation placement and R values | MOHAMMAD AHEAD | energy_progress |
| 02/13/2025 | Interior lighting power | MOHAMMAD AHEAD | energy_progress |
| 02/13/2025 | Masonry | MOHAMMAD AHEAD | special |