← Back
Five to six families
109-40 CORONA AVENUE
QUEENS · BIN 4048295
💬 Discuss this project
1920Year Built
2Stories
C2Building Class
R6BZoning
3,300 sfGross Floor Area
5Units
Rent Stabilized10 Open Violations 9 unresolved · 1 paperwork only ▸
Five to six families · Owner of record: FABIO REALTY LLC · 2,139 sf lot · 1.54 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalFire Protection
Roof17p · 1 filing · 20 docs
Floor 315p · 1 filing · 20 docs
Floor 214p · 1 filing · 20 docs
Floor 114p · 1 filing · 20 docs
Basement14p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FABIO REALTY403/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BFS ARCHITECT PC710/25/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
5 POINTS REHAB LLCGeneral Contractor907/08/2026
LEMODE PLBG & HTG CORPPlumbing307/08/2026
LEMODE PLUMBING & HEATINGFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BFS ARCHITECT PC7477610/25/2024
Building Lifecycle
All (93)Filed (7)Permit Issued (9)Signed Off (4)Violation (13)Inspection (14)Objection (16)Special Inspection (30)
03/25/2026
Permit issued — Foundation
Q00795296-I1-FO-EA
11/25/2025
Violation issued (HPD, open)
I
04/03/2025
Signed off — Alteration
Proposed interior demolition consisting of removal of non-load bearing partitions and finishes. No change to the use, occupancy or egress under this application.
Q00769320-I1
04/03/2025
Signed off — Alteration CO
PROPOSED PLUMBING FOR THREE STORY; FIVE-FAMILY DWELLING FILED IN CONJUNCTION WITH GC# Q00795296-I1
Q00795296-S2
02/26/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/26/2025
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments)
Certified
View inspection ↗
01/27/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
01/14/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/09/2025
Signed off — Alteration CO
PROPOSED PLUMBING FOR THREE STORY; FIVE-FAMILY DWELLING FILED IN CONJUNCTION WITH GC# Q00795296-I1
Q00795296-S3
01/08/2025
Permit issued — Mechanical Systems
Q00795296-S3-MS
12/18/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/12/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/04/2024
Violation issued (HPD, open)
I
11/26/2024
Special inspection requirement — Fenestration air leakage
Belal Salim
11/26/2024
Special inspection requirement — Permanent certificate
Belal Salim
11/26/2024
Special inspection requirement — Insulation placement and R values
Belal Salim
11/26/2024
Special inspection requirement — Air barrier - visual inspection
Belal Salim
11/26/2024
Special inspection requirement — Interior lighting power
Belal Salim
11/26/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Belal Salim
11/26/2024
Special inspection requirement — Air barrier — testing
Belal Salim
11/26/2024
Special inspection requirement — Fenestration areas
Belal Salim
11/26/2024
Special inspection requirement — Maintenance information
Belal Salim
11/26/2024
Special inspection requirement — Metering
Belal Salim
11/26/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
BRIAN FLYNN
11/26/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Belal Salim
11/26/2024
Special inspection requirement — Concrete - Cast-In-Place
Belal Salim
11/26/2024
Special inspection requirement — Subgrade Inspections
Belal Salim
11/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Belal Salim
11/26/2024
Special inspection requirement — Masonry
Belal Salim
11/26/2024
Special inspection requirement — Energy Code Compliance Inspections
Belal Salim
11/26/2024
Special inspection requirement — Final
Belal Salim
11/26/2024
Special inspection requirement — Fire-Resistance Rated Construction
Belal Salim
11/26/2024
Special inspection requirement — Footing and Foundation
Belal Salim
11/15/2024
Objection resolved — Addressed
11/15/2024
Objection resolved — Addressed
11/15/2024
Objection resolved — Addressed
11/13/2024
Objection raised — Admin
11/13/2024
Objection raised — Zoning
11/13/2024
Objection raised — Other
11/05/2024
Objection resolved — Addressed
10/31/2024
Objection raised — Scope
10/25/2024
Filed — Alteration CO
PROPOSED PLUMBING FOR THREE STORY; FIVE-FAMILY DWELLING FILED IN CONJUNCTION WITH GC# Q00795296-I1
Q00795296-P4
03/22/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
03/20/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Belal Salim
03/20/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Belal Salim
03/20/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Belal Salim
03/20/2024
Special inspection requirement — Post-installed Anchors
Belal Salim
03/20/2024
Special inspection requirement — Energy Code Compliance Inspections
Belal Salim
03/20/2024
Special inspection requirement — Sprinkler Systems
Belal Salim
03/20/2024
Special inspection requirement — HVAC-R and service water heating system controls
Belal Salim
03/20/2024
Special inspection requirement — Maintenance information
Belal Salim
03/20/2024
Special inspection requirement — Metering
Belal Salim
03/20/2024
Special inspection requirement — HVAC-R and service water heating equipment
Belal Salim
02/26/2024
Filed — Alteration CO
PROPOSED PLUMBING FOR THREE STORY; FIVE-FAMILY DWELLING FILED IN CONJUNCTION WITH GC# Q00795296-I1
Q00795296-S3
02/06/2024
Permit issued — General Construction
Q00795296-I1-GC
01/09/2024
Inspection — Certified StandPipe - SD - Alarm Sys 64/09 - Finish
Certified
View inspection ↗
01/09/2024
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
12/21/2023
Filed — Alteration CO
PROPOSED PLUMBING FOR THREE STORY; FIVE-FAMILY DWELLING FILED IN CONJUNCTION WITH GC# Q00795296-I1
Q00795296-P1
12/01/2023
Signed off — Alteration
Q00770810-I1
12/01/2023
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
Latest 60 of 93 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit Issued5 POINTS REHAB LLC03/25/2026
DOB NOWMechanical SystemsSigned-off5 POINTS REHAB LLC01/08/2025
DOB NOWGeneral ConstructionPermit Issued5 POINTS REHAB LLC02/06/2024
DOB NOWPlumbingSigned-offLEMODE PLUMBING & HEATING10/19/2023
DOB NOWSprinklersSigned-offLEMODE PLBG & HTG CORP10/19/2023
DOB NOWPlumbingSigned-offLEMODE PLBG & HTG CORP10/03/2023
DOB NOWGeneral ConstructionSigned-off5 POINTS REHAB LLC06/06/2023
DOB NOWPlumbingSigned-offLEMODE PLBG & HTG CORP09/26/2022
DOB NOWGeneral ConstructionSigned-off5 POINTS REHAB LLC09/19/2022
1 project · most recent 10/25/2024
Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
10/25/2024Permit Issued5 POINTS REHAB LLCHeating Systems, Ventilation Systems
Heating
Navien NCB-190/080 74,000 BTU · Boiler ×20
Ventilation
Air King ES248ADA 150 CFM · Kitchen Exhaust ×20
Delta SLM501 50 CFM · Exhaust Fan ×20
1 project · most recent 10/25/2024
Sprinkler System
FiledStatusContractorScope
10/25/2024Signed-offLEMODE PLUMBING & HEATINGSprinkler System
1 project · most recent 10/25/2024
Gas Storm Water/Sanitary
FiledStatusContractorScope
10/25/2024Signed-offLEMODE PLBG & HTG CORPGas, Storm, Water/Sanitary
2 projects · most recent 12/14/2023
General Wiring
FiledStatusContractorScope
12/14/2023CompleteAL ELECTRICAL GROUP INCGeneral Wiring
01/24/2023CompleteAL ELECTRICAL GROUP INCGeneral Wiring
▾Field Inspections (DOB CAP) — 14
DateTypeResultReport
02/26/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/26/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments)CertifiedView ↗
01/27/2025Pass-Final General Construction Non-Directive 14PassView ↗
01/14/2025Fail-Final General Construction Non-Directive 14FailView ↗
12/18/2024Pass-Final CND-Occupancy InspectionPassView ↗
12/12/2024Pass-Final CND-Occupancy InspectionPassView ↗
03/22/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
01/09/2024Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
01/09/2024Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
12/01/2023Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
12/01/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/01/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/01/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/29/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 42
DateRequirementInspectorRole
11/26/2024Fenestration air leakageBelal Salimenergy_progress
11/26/2024Permanent certificateBelal Salimenergy_progress
11/26/2024Insulation placement and R valuesBelal Salimenergy_progress
11/26/2024Air barrier - visual inspectionBelal Salimenergy_progress
11/26/2024Interior lighting powerBelal Salimenergy_progress
11/26/2024Fenestration and door U-factor and product ratingsBelal Salimenergy_progress
11/26/2024Air barrier — testing Belal Salimenergy_progress
11/26/2024Fenestration areasBelal Salimenergy_progress
11/26/2024Maintenance informationBelal Salimenergy_progress
11/26/2024MeteringBelal Salimenergy_progress
11/26/2024Subsurface Investigations (Borings/Test Pits)BRIAN FLYNNspecial
11/26/2024Structural Stability – Alterations of existing buildingsBelal Salimspecial
11/26/2024Concrete - Cast-In-PlaceBelal Salimspecial
11/26/2024Subgrade InspectionsBelal Salimspecial
11/26/2024Fire-Resistant Penetrations and JointsBelal Salimspecial
11/26/2024MasonryBelal Salimspecial
11/26/2024Energy Code Compliance InspectionsBelal Salimprogress
11/26/2024FinalBelal Salimprogress
11/26/2024Fire-Resistance Rated ConstructionBelal Salimprogress
11/26/2024Footing and FoundationBelal Salimprogress
03/20/2024HVAC-R and service water piping design and insulationBelal Salimenergy_progress
03/20/2024Fire-Resistant Penetrations and JointsBelal Salimspecial
03/20/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationBelal Salimspecial
03/20/2024Post-installed AnchorsBelal Salimspecial
03/20/2024Energy Code Compliance InspectionsBelal Salimprogress
Latest 25 of 42.
▾Documents — 50 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/26/2026Q00770810-I1Request digital key ↗
08/23/2026Q00795296-S3Request digital key ↗
08/23/2026Q00795296-P1Request digital key ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026Q00795296-P4Open ↗
08/13/2026Q00795296-I1Open ↗
▸Seals & Professional Certifications19
▸DOB NOWProgress Inspector Seal & Signature8
09/23/2026Q00795296-S2Open ↗
09/23/2026Q00795296-S2Open ↗
09/23/2026Q00795296-S2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/26/2026Q00769320-I1Open ↗
08/26/2026Q00770810-I1Open ↗
08/23/2026Q00795296-S3Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026Q00795296-S2Open ↗
09/20/2026Q00795296-I1Open ↗
09/20/2026Q00795296-I1Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment1
▸DOB NOWSprinkler system Application Sign-off1
08/23/2026Q00795296-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/23/2026Q00795296-I1Open ↗
08/15/2026Q00795296-P4Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/26/2026Q00770810-I1Open ↗
08/23/2026Q00795296-P1Open ↗
08/23/2026Q00795296-S3Open ↗
Showing 3 of 7 on file for this type
▸Inspections & Test Reports3
▸DOB NOWSOIL REPORT2
08/13/2026Q00795296-I1Open ↗
08/13/2026Q00795296-P4Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00795296-I1Open ↗
▸Other Documents9
▸DOB NOWPlot Diagram2
08/13/2026Q00795296-I1Open ↗
08/13/2026Q00795296-P4Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q00795296-I1Open ↗
08/13/2026Q00795296-P4Open ↗
▸DOB NOWProperty Ownership Certification2
08/23/2026Q00795296-I1Open ↗
08/15/2026Q00795296-P4Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q00795296-I1Open ↗
08/13/2026Q00795296-P4Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q00795296-I1Open ↗