| Owner | Filings | Most Recent |
|---|---|---|
| TABRIZ DESIGN GROUP | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 2 | 07/16/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 2 | 07/16/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 05/30/2025 |
| BIS | PL | ISSUED | AP PLUMBING & HVAC LLC | 07/09/2018 |
| BIS | OT | ISSUED | ALL AMERICAN BUILDING & DEVELOP | 07/03/2018 |
| BIS | PL | ISSUED | QMB PLUMBING & HEATING INC | 03/06/2013 |
| BIS | OT | ISSUED | OWNER | 03/06/2013 |
| BIS | PL | ISSUED | QMB PLUMBING & HEATING INC | 06/15/2012 |
| BIS | — | ISSUED | ZHUO YUE CONSTRUCTION INC | 06/13/2012 |
| BIS | — | ISSUED | ZHUO YUE CONSTRUCTION INC | 06/13/2012 |
| BIS | EQ | ISSUED | ZHUO YUE CONSTRUCTION INC | 06/13/2012 |
| BIS | OT | ISSUED | NRG MAGIC CONSTRUCTION IN | 11/21/2008 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2025 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2025 | Signed-off | SUNRUN INSTALLATION SVC | 68 panels, 27.54 kw, 714.68 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/24/2025 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 07/24/2025 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 07/24/2025 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 07/24/2025 | Final | Walid Abdulla | progress |
| 07/24/2025 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 07/08/2025 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 07/08/2025 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 07/08/2025 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 07/08/2025 | Final | Walid Abdulla | progress |
| 07/08/2025 | Air barrier - visual inspection | Walid Abdulla | energy_progress |