| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/15/2018 | $847K | — | Private party → Private party | $479/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SERDAR CEYLAN ARCHITECT, PC | 7 | 07/17/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| L&L CONSTRUCTION DEVELOP | General Contractor | 4 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CEYLAN DESIGN AND CONSULT | 8422 | 2 | 06/24/2026 |
| WELLDONE INSPECTION INC. | 8628 | 2 | 06/24/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | L&L CONSTRUCTION DEVELOP | 04/29/2026 |
| DOB NOW | General Construction | Permit Issued | L&L CONSTRUCTION DEVELOP | 04/27/2026 |
| DOB NOW | General Construction | Permit Issued | L&L CONSTRUCTION DEVELOP | 04/10/2026 |
| DOB NOW | Construction Fence | Permit Issued | L&L CONSTRUCTION DEVELOP | 04/08/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/25/2025 | — | — | Air Conditioning Systems | Cooling Mitsubishi Electric MXZ-4C72NA2 36,000 BTU · Condensing Unit ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/02/2026 | Permit Issued | AL-LECTRIC ELECT'L CONTRG | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/26/2026 | Permit Issued | L&L CONSTRUCTION DEVELOP | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/17/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/17/2026 | Maintenance information | — | energy_progress |
| 08/17/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/17/2026 | Fenestration and door U-factor and product ratings | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Fire-Resistant Penetrations and Joints | QIUFAN JIANG | special |
| 06/17/2026 | Mechanical Systems | SERDAR CEYLAN | special |
| 06/17/2026 | Structural Stability – Alterations of existing buildings | QIUFAN JIANG | special |
| 06/17/2026 | Energy Code Compliance Inspections | SERDAR CEYLAN | progress |
| 06/17/2026 | Final | SERDAR CEYLAN | progress |
| 06/17/2026 | Insulation placement and R values | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Permanent certificate | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Ventilation and air distribution system | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Fenestration areas | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Protection of exposed foundation insulation | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Maintenance information | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Shutoff dampers | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Interior lighting power | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Air barrier — testing | QIUFAN JIANG | energy_progress |
| 06/17/2026 | HVAC-R and service water heating equipment | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Lighting controls | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | HVAC-R and service water piping design and insulation | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Air barrier - visual inspection | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | Fenestration air leakage | SERDAR CEYLAN | energy_progress |
| 06/17/2026 | HVAC-R and service water heating system controls | SERDAR CEYLAN | energy_progress |
| 03/04/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |