| Owner | Filings | Most Recent |
|---|---|---|
| M2 PROPERTIES | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LAWRENCE MAREK ARCHITECT | 3 | 03/12/2025 |
| YOU GAO | 1 | 02/03/2025 |
| PAPA ARCHITECTURE PC | 3 | 12/05/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| CHERICO KING ARCHITECT P C | 6 | 03/21/2026 |
| INDESIGN STUDIO | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TUDOR HVAC MECHANICAL INC | General Contractor | 3 | 03/21/2026 |
| ALL AMERICAN CONSTRUCTION | General Contractor | 1 | 07/08/2026 |
| TITAN BUILDERS & CONSTR | General Contractor | 1 | 07/08/2026 |
| SAFEPIPE PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| VINESKI-MAY PLBG & HTG LL | Plumbing | 1 | 07/08/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHERICO KING ARCHITECT PC | 5674 | 3 | 03/12/2025 |
| YOU GAO | 9407 | 1 | 02/03/2025 |
| CHRISTOPHER V. PAPA ARCHI | 1663 | 1 | 10/21/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | DESTHERS, JOSEPH | 02/25/2025 |
| DOB NOW | Plumbing | Signed-off | BELLEROSE PLBG & HTG | 12/12/2024 |
| DOB NOW | General Construction | Permit Issued | ALL AMERICAN CONSTRUCTION | 12/10/2024 |
| DOB NOW | Plumbing | Signed-off | VINESKI-MAY PLBG & HTG LL | 11/12/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TUDOR HVAC MECHANICAL INC | 10/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TITAN BUILDERS & CONSTR | 10/24/2024 |
| BIS | OT | ISSUED | DYR-EX GENERAL CONTRC INC | 08/16/2020 |
| BIS | — | ISSUED | FRANK TORRONE & SONS INC | 01/24/2005 |
| BIS | OT | ISSUED | SNI CONSTRUCTION & MANAGEMENT, I | 10/20/2004 |
| BIS | PL | ISSUED | VIS INDUSTRIES | 10/20/2004 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/12/2025 | Permit Issued | ALL AMERICAN CONSTRUCTION | Ventilation Systems | Ventilation Xlt 3240H 1,600 CFM · Kitchen Exhaust ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2025 | Signed-off | BELLEROSE PLBG & HTG | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/13/2023 | Complete | T. DIRUSSO ELEC'L CONT IN | 2 meters, 1 new_meters |
| 09/15/2021 | Complete | WILLDAN ELECTRICAL OF NY | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/24/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/11/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/17/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/11/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/29/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/11/2025 | HVAC-R and service water piping design and insulation | LAWRENCE MAREK | energy_progress |
| 03/11/2025 | HVAC-R and service water heating equipment | LAWRENCE MAREK | energy_progress |
| 03/11/2025 | HVAC-R and service water heating system controls | LAWRENCE MAREK | energy_progress |
| 03/11/2025 | Energy Code Compliance Inspections | LAWRENCE MAREK | progress |
| 03/11/2025 | Fire-Resistant Penetrations and Joints | LAWRENCE MAREK | special |
| 01/27/2025 | Structural Stability – Alterations of existing buildings | You Gao | special |
| 01/27/2025 | Final | You Gao | progress |
| 11/26/2024 | Duct leakage testing, insulation and design | LAWRENCE MAREK | energy_progress |
| 11/26/2024 | Fire-Resistant Penetrations and Joints | LAWRENCE MAREK | special |
| 11/26/2024 | Energy Code Compliance Inspections | LAWRENCE MAREK | progress |
| 11/26/2024 | Fire-Resistance Rated Construction | LAWRENCE MAREK | progress |
| 11/26/2024 | Ventilation and air distribution system | LAWRENCE MAREK | energy_progress |
| 11/26/2024 | Interior lighting power | LAWRENCE MAREK | energy_progress |
| 11/26/2024 | Lighting controls | LAWRENCE MAREK | energy_progress |
| 11/22/2024 | Final | LAWRENCE MAREK | progress |
| 11/22/2024 | Mechanical Systems | LAWRENCE MAREK | special |
| 10/21/2024 | Heating Systems | Christopher Papa | special |
| 10/21/2024 | Fire-Resistant Penetrations and Joints | Christopher Papa | special |
| 10/21/2024 | Concrete - Cast-In-Place | Christopher Papa | special |
| 10/21/2024 | HVAC-R and service water piping design and insulation | Christopher Papa | energy_progress |
| 10/21/2024 | Energy Code Compliance Inspections | Christopher Papa | progress |
| 10/21/2024 | HVAC-R and service water heating equipment | Christopher Papa | energy_progress |
| 10/21/2024 | Fire-Resistance Rated Construction | Christopher Papa | progress |
| 10/21/2024 | Duct leakage testing, insulation and design | Christopher Papa | energy_progress |
| 10/21/2024 | HVAC-R and service water heating system controls | Christopher Papa | energy_progress |