1950Year Built
3Stories
C0Building Class
R5BZoning
2,698 sfGross Floor Area
3Units
Three families · Owner of record: 2034 STANHOPE STREET LLC · 2,100 sf lot · 1.28 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Floor 3Under Construction28p · 3 filings · 20 docs
Floor 2Under Construction25p · 3 filings · 20 docs
Floor 1Under Construction25p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
2034 STANHOPE STREET LLC708/29/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NMI ARCHITECTURE, PLLC508/18/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HOMEPRO GENERAL CONTRACTINGGeneral Contractor208/14/2026
L&L CONSTRUCTION DEVELOPGeneral Contractor107/08/2026
XH&RC PLBG AND HTG INCPlumbing108/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JUN YAN, PE7170208/18/2026
NMI ARCHITECTURE, PLLC6825408/18/2026
TRIANGLE INSPECTION & TES7495208/10/2026
Building Lifecycle
All (58)Filed (5)Permit Issued (4)Objection (19)Special Inspection (30)
08/18/2026
Filed — Alteration CO
This application is filed to convert the existing 1st floor to class "A" apartment, change the building from two to three family, no change in building bulk, Spk& Pl system to be filed separately
Q01271738-P1
08/17/2026
Special inspection requirement — Energy Code Compliance Inspections
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Fire-Resistance Rated Construction
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Interior lighting power
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Metering
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Lighting controls
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Permanent certificate
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Fenestration areas
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Fenestration air leakage
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Lighting in dwelling units
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Insulation placement and R values
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NASHAT IBRAHIM
08/17/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
JUN YAN
08/13/2026
Permit issued — Mechanical Systems
Q01267402-S1-MS
08/10/2026
Filed — Alteration
Filing this MECH application in conjunction with ALt-1 application # Q01271738-I1 for all new HVAC units, no change of use, egress or OCcupancy
Q01267402-S1
08/10/2026
Special inspection requirement — HVAC-R and service water heating equipment
NASHAT IBRAHIM
08/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NASHAT IBRAHIM
08/10/2026
Special inspection requirement — Heating Systems
NASHAT IBRAHIM
08/10/2026
Special inspection requirement — Post-installed Anchors
Rajasekhar Sakhamuri
08/10/2026
Special inspection requirement — Energy Code Compliance Inspections
NASHAT IBRAHIM
08/10/2026
Special inspection requirement — HVAC-R and service water heating system controls
NASHAT IBRAHIM
08/10/2026
Special inspection requirement — Maintenance information
NASHAT IBRAHIM
08/10/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
NASHAT IBRAHIM
08/10/2026
Special inspection requirement — Permanent certificate
NASHAT IBRAHIM
08/07/2026
Permit issued — Plumbing
Q01267402-I1-PL
08/05/2026
Special inspection requirement — Final
NASHAT IBRAHIM
08/05/2026
Special inspection requirement — Mechanical Systems
NASHAT IBRAHIM
07/14/2026
Permit issued — General Construction
Q01271738-I1-GC
05/26/2026
Permit issued — General Construction
Q01402688-I1-GC
05/20/2026
Filed — Alteration
This Application is filed for all related interior Demo work in conjunction with Alt-1 Application # Q01271738-I1 for non ST walls, Floor& Clg finish, no change of Use, egress or occupancy under this application
Q01402688-I1
04/30/2026
Special inspection requirement — Lighting controls
NASHAT IBRAHIM
04/30/2026
Special inspection requirement — Lighting in dwelling units
NASHAT IBRAHIM
04/28/2026
Objection raised — Other
04/27/2026
Special inspection requirement — Permanent certificate
NASHAT IBRAHIM
04/27/2026
Special inspection requirement — Interior lighting power
NASHAT IBRAHIM
04/27/2026
Special inspection requirement — Metering
NASHAT IBRAHIM
04/13/2026
Special inspection requirement — HVAC-R and service water heating system controls
NASHAT IBRAHIM
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/10/2026
Objection raised — Other
04/10/2026
Objection resolved — Addressed
04/08/2026
Filed — Alteration
Filing this MECH application in conjunction with ALt-1 application # Q01271738-I1 for all new HVAC units, no change of use, egress or OCcupancy
Q01267402-I1
04/08/2026
Filed — Alteration CO
This application is filed to convert the existing 1st floor to class "A" apartment, change the building from two to three family, no change in building bulk, Spk& Pl system to be filed separately
Q01271738-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedHOMEPRO GENERAL CONTRACTING08/13/2026
DOB NOWPlumbingPermit IssuedXH&RC PLBG AND HTG INC08/07/2026
DOB NOWGeneral ConstructionPermit IssuedHOMEPRO GENERAL CONTRACTING07/14/2026
DOB NOWGeneral ConstructionPermit IssuedL&L CONSTRUCTION DEVELOP05/26/2026
1 project · most recent 08/10/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/10/2026Permit IssuedHOMEPRO GENERAL CONTRACTIHeating and Air Conditioning Systems
Heat / Cool
Gree GREE, R32 MULTI-ZONE SERIES. GS5M48HP230V1MO 4 tons · Vrf Outdoor ×2
GREE, R32 MULTI-ZONE SERIES. GS4M30HP230V1MO 25 tons · Vrf Outdoor ×1
1 project · most recent 08/31/2026
General Wiring
FiledStatusContractorScope
08/31/2026Permit IssuedGOODALL ELECTRIC CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
08/17/2026Energy Code Compliance InspectionsNASHAT IBRAHIMprogress
08/17/2026Fire-Resistance Rated ConstructionNASHAT IBRAHIMprogress
08/17/2026Interior lighting powerNASHAT IBRAHIMenergy_progress
08/17/2026MeteringNASHAT IBRAHIMenergy_progress
08/17/2026Lighting controlsNASHAT IBRAHIMenergy_progress
08/17/2026Permanent certificateNASHAT IBRAHIMenergy_progress
08/17/2026Fenestration areasNASHAT IBRAHIMenergy_progress
08/17/2026Fenestration air leakageNASHAT IBRAHIMenergy_progress
08/17/2026Lighting in dwelling unitsNASHAT IBRAHIMenergy_progress
08/17/2026Fenestration and door U-factor and product ratingsNASHAT IBRAHIMenergy_progress
08/17/2026Insulation placement and R valuesNASHAT IBRAHIMenergy_progress
08/17/2026Fire-Resistant Penetrations and JointsNASHAT IBRAHIMspecial
08/17/2026Structural Stability – Alterations of existing buildingsJUN YANspecial
08/10/2026HVAC-R and service water heating equipmentNASHAT IBRAHIMenergy_progress
08/10/2026Fire-Resistant Penetrations and JointsNASHAT IBRAHIMspecial
08/10/2026Heating SystemsNASHAT IBRAHIMspecial
08/10/2026Post-installed AnchorsRajasekhar Sakhamurispecial
08/10/2026Energy Code Compliance InspectionsNASHAT IBRAHIMprogress
08/10/2026HVAC-R and service water heating system controlsNASHAT IBRAHIMenergy_progress
08/10/2026Maintenance informationNASHAT IBRAHIMenergy_progress
08/10/2026HVAC-R and service water piping design and insulationNASHAT IBRAHIMenergy_progress
08/10/2026Permanent certificateNASHAT IBRAHIMenergy_progress
08/05/2026FinalNASHAT IBRAHIMprogress
08/05/2026Mechanical SystemsNASHAT IBRAHIMspecial
04/30/2026Lighting controlsNASHAT IBRAHIMenergy_progress
Latest 25 of 43.
▾Documents — 62 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/29/2026Q01271738-P1Request digital key ↗
08/17/2026Q01267402-S1Request digital key ↗
08/17/2026Q01267402-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications48
▸DOB NOWProgress Inspector Seal & Signature33
08/31/2026Q01271738-I1Open ↗
08/31/2026Q01271738-I1Open ↗
08/31/2026Q01271738-I1Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
08/31/2026Q01271738-I1Open ↗
08/31/2026Q01271738-I1Open ↗
08/25/2026Q01267402-S1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/19/2026Q01271738-P1Open ↗
08/17/2026Q01267402-S1Open ↗
08/17/2026Q01267402-I1Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/19/2026Q01271738-P1Open ↗
08/15/2026Q01271738-I1Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/19/2026Q01271738-P1Open ↗
08/17/2026Q01267402-S1Open ↗
08/17/2026Q01267402-I1Open ↗
Showing 3 of 5 on file for this type
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
08/19/2026Q01271738-P1Open ↗
08/15/2026Q01271738-I1Open ↗