| Owner | Filings | Most Recent |
|---|---|---|
| 1866 MENAHAN ST LLC | 1 | 03/22/2026 |
| STEPHEN D VERSACE 2021 IR | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/01/2024 | $1.2M | — | — → — | $500/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| SELF | 2 | 07/14/2026 |
| MURRAY ENGINEERING PC | 2 | 12/09/2025 |
| FLORINELA MURESAN | 3 | 11/14/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAM CONSULTANTS, INC. | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KWA CONSTR & SERVICES INC | General Contractor | 4 | 07/08/2026 |
| CROSSFIELD PLBG.&HTG.CORP | Fire Protection | 1 | 07/02/2026 |
| DAZONG HVAC & R, INC | General Contractor | 1 | 07/08/2026 |
| HAWK. AA LLC | General Contractor | 1 | 07/08/2026 |
| CROSSFIELD PLBG.&HTG | Plumbing | 1 | 06/02/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HAMANN ENGINEERING, PLLC | 4949 | 7 | 07/14/2026 |
| EDRA ENGINEERING & INSPEC | 2820 | 5 | 12/09/2025 |
| PILLORI ASSOCIATES | 2317 | 1 | 12/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | CROSSFIELD PLBG.&HTG.CORP | 06/30/2026 |
| DOB NOW | Foundation | Signed-off | KWA CONSTR & SERVICES INC | 06/25/2026 |
| DOB NOW | General Construction | Permit Issued | KWA CONSTR & SERVICES INC | 06/17/2026 |
| DOB NOW | Structural | Permit Issued | KWA CONSTR & SERVICES INC | 06/17/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | DAZONG HVAC & R, INC | 06/01/2026 |
| DOB NOW | Plumbing | Permit Issued | CROSSFIELD PLBG.&HTG | 05/01/2026 |
| DOB NOW | Structural | Permit Issued | HAWK. AA LLC | 04/16/2026 |
| DOB NOW | General Construction | Permit Issued | KWA CONSTR SERVICES | 11/10/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/14/2026 | Signed-off | KWA CONSTR & SERVICES INC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | Permit Issued | CROSSFIELD PLBG.&HTG.CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | Permit Issued | CROSSFIELD PLBG.&HTG | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/12/2026 | Permit Issued | P & Z ELECTRIC CORP | General Wiring |
| 05/31/2024 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | Permit Issued | CROSSFIELD PLBG.&HTG.CORP | Steel, Masonry, Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2026 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 08/20/2026 | Insulation placement and R values | CARL HAMANN | energy_progress |
| 08/20/2026 | Fenestration air leakage | CARL HAMANN | energy_progress |
| 08/20/2026 | Lighting in dwelling units | CARL HAMANN | energy_progress |
| 08/20/2026 | Permanent certificate | CARL HAMANN | energy_progress |
| 08/20/2026 | Maintenance information | CARL HAMANN | energy_progress |
| 08/20/2026 | Interior lighting power | CARL HAMANN | energy_progress |
| 08/20/2026 | Metering | CARL HAMANN | energy_progress |
| 08/20/2026 | Fenestration and door U-factor and product ratings | CARL HAMANN | energy_progress |
| 08/20/2026 | Air barrier - visual inspection | CARL HAMANN | energy_progress |
| 08/20/2026 | Fire-Resistance Rated Construction | CARL HAMANN | progress |
| 07/13/2026 | Insulation placement and R values | CARL HAMANN | energy_progress |
| 07/13/2026 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 07/13/2026 | Fire-Resistance Rated Construction | CARL HAMANN | progress |
| 07/13/2026 | Permanent certificate | CARL HAMANN | energy_progress |
| 07/13/2026 | Interior lighting power | CARL HAMANN | energy_progress |
| 07/13/2026 | Air barrier - visual inspection | CARL HAMANN | energy_progress |
| 07/13/2026 | Fenestration and door U-factor and product ratings | CARL HAMANN | energy_progress |
| 07/13/2026 | Metering | CARL HAMANN | energy_progress |
| 07/13/2026 | Maintenance information | CARL HAMANN | energy_progress |
| 07/13/2026 | Fenestration air leakage | CARL HAMANN | energy_progress |
| 07/13/2026 | Lighting in dwelling units | CARL HAMANN | energy_progress |
| 01/14/2026 | Subsurface Investigations (Borings/Test Pits) | Gregory Pillori | special |
| 01/08/2026 | Metering | CARL HAMANN | energy_progress |
| 01/08/2026 | Interior lighting power | CARL HAMANN | energy_progress |