| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/26/2023 | Signed-off | JSB WORKS INC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/26/2023 | Signed-off | ORBIT SPRINKLER CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/26/2023 | Signed-off | ORBIT PLBG & HTG INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/03/2022 | Complete | FRIED ELECTRIC CO. | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| 228 JEFFERSON ST | 20 | 07/08/2026 |
| PUTNAM 888 LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/31/2022 | $700K | — | — → — | $125/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LESTER KATZ, NCARB | 6 | 10/26/2023 |
| VASILIOS ARTEMIOU PE | 1 | 02/14/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 12 | 03/21/2026 |
| XPDITE GROUP 103 | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JSB WORKS INC | General Contractor | 4 | 07/08/2026 |
| ORBIT SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ESNYC CONSULTING INC | 4099 | 7 | 10/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | JSB WORKS INC | 04/27/2023 |
| DOB NOW | Sprinklers | Signed-off | ORBIT SPRINKLER CORP | 03/28/2023 |
| DOB NOW | Plumbing | Signed-off | ORBIT PLBG & HTG INC | 02/16/2023 |
| DOB NOW | General Construction | Permit Issued | JSB WORKS INC | 01/27/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/24/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/21/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/28/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/02/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/01/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/31/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/10/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/08/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/03/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/03/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/08/2023 | Fire-Resistant Penetrations and Joints | sajjad javaid | special |
| 11/08/2023 | Energy Code Compliance Inspections | sajjad javaid | progress |
| 11/08/2023 | Fire-Resistance Rated Construction | sajjad javaid | progress |
| 11/08/2023 | Lighting controls | sajjad javaid | energy_progress |
| 11/08/2023 | Metering | sajjad javaid | energy_progress |
| 11/08/2023 | Maintenance information | sajjad javaid | energy_progress |
| 11/08/2023 | Lighting in dwelling units | sajjad javaid | energy_progress |
| 11/08/2023 | Interior lighting power | sajjad javaid | energy_progress |
| 10/26/2023 | Fire-Resistant Penetrations and Joints | sajjad javaid | special |
| 10/26/2023 | Energy Code Compliance Inspections | sajjad javaid | progress |
| 10/26/2023 | Fire-Resistance Rated Construction | sajjad javaid | progress |
| 10/26/2023 | Lighting in dwelling units | sajjad javaid | energy_progress |
| 10/26/2023 | Lighting controls | sajjad javaid | energy_progress |
| 10/26/2023 | Maintenance information | sajjad javaid | energy_progress |
| 10/26/2023 | Metering | sajjad javaid | energy_progress |
| 10/26/2023 | Interior lighting power | sajjad javaid | energy_progress |
| 05/30/2023 | Metering | sajjad javaid | energy_progress |
| 05/30/2023 | Lighting in dwelling units | sajjad javaid | energy_progress |
| 05/30/2023 | Fire-Resistant Penetrations and Joints | sajjad javaid | special |
| 05/30/2023 | Energy Code Compliance Inspections | sajjad javaid | progress |
| 05/30/2023 | Fire-Resistance Rated Construction | sajjad javaid | progress |
| 05/30/2023 | Lighting controls | sajjad javaid | energy_progress |
| 05/30/2023 | Interior lighting power | sajjad javaid | energy_progress |
| 05/30/2023 | Maintenance information | sajjad javaid | energy_progress |
| 05/04/2023 | Maintenance information | sajjad javaid | energy_progress |